This report provides an update on the CSC digitization process, including new features such as neutron background and simplified strip timing. Validation results for occupancy, amplitude, timing, pedestals & noise, resolution, and segments are also presented. A comparison with CMSSW versions 1_1_0 and 1_3_0_pre1 is included, along with conclusions and the need for integration with SVSuite.

flinchum
Download Presentation

CSC Digi & RecHit Validation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CSC Digi & RecHit Validation Rick Wilkinson

  2. CSC Digitization Status • No changes from CMSSW 1_0_0 to 1_3_0. • LOTS of new features ready for 1_4_0: • Neutron Background • Correlated Noise • Simplified strip timing • Realistic strip readout • Old code only saved ~6 strips around a hit • Now Front End Boards (CFEBs) read 16 strips at a time • Relevant to DAQ studies • New comparator timing Rick Wilkinson

  3. CSC Digi & RecHit Validation DIGIS • Occupancy • Amplitude • Timing • Pedestals & Noise • Resolution • Layers with one SimHit • REC HITS • Occupancy • Resolution • Pulls • SEGMENTS • Nothing, yet Rick Wilkinson

  4. Comparisons • CMSSW 1_1_0 and 1_3_0_pre1 are identical • In the following plots, we compare to development version, meant for 1_4_0. • RED means REFERENCE (1_2_0_pre9) • BLUE means NEW (development) • If there are nine plots, it’s one for each chamber type Rick Wilkinson

  5. Strip Digis: Timing • Want to tune timing so the peak is in time bin 5 • Plot ratios of bin4/bin5 and bin6/5 OLD: Signal too late. Too much in bin 6 NEW: Now a little too much in bin 4 Rick Wilkinson

  6. Strip Digis: Occupancy OLD: ~6 strips around a hit NEW: All 16 strips in Cathode Front End Board (CFEB) Rick Wilkinson

  7. Wire Digis: Timing Acceptable, but some chambers showing up late Rick Wilkinson

  8. Rec Hits: Resolution • Layers with one SimHit • Plot r df • Resolutions look fine • Expect 100-300 mm Rick Wilkinson

  9. Conclusion • CSCs have a validation system now for digis & rec hits • Can do Chi2 tests, make plots. • Things look fine for 1_3_0 • Differences with development (1_4_0) expected and seen. • Need to integrate with SVSuite! Rick Wilkinson