1 / 10

Local Area Study

Local Area Study. Mitigation Plan Update and Uncertainty Scenarios 2012 - 2013. Mitigation Plans Updates. East Helena bus fault or transformer outage Ranked # 7 - Outages result in complete loss of the Helena 69 kV system

forest
Download Presentation

Local Area Study

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Local Area Study Mitigation Plan Update and Uncertainty Scenarios 2012 - 2013

  2. Mitigation Plans Updates • East Helena bus fault or transformer outage • Ranked # 7 - Outages result in complete loss of the Helena 69 kV system • Construct 100 kV loop to radial fed Helena area 100 kV distribution substation • Tie proposed distribution substation needed for continued growth in the Helena area to new 100 kV facilities • Construct and tie new 100 MVA 100/69 kV auto substation to new 100 kV facilities • Add breakers to East Helena 69 kV bus to complete breaker-and-a-half scheme

  3. Mitigation Plans Updates • Broadview to Billings Area 230 kV double contingency • Ranked # 8 - Outage results in low to very low voltage in the Billings Area • Problem worsens after loss of Corette and continued Billings area growth • Build a new 230 kV line from Broadview into Billings • Assumes slightly diverse route from existing Broadview to Billings 230 kV lines • Clyde Park bus fault or transformer outage • Ranked # 13 - Outages result in loss of Livingston and Big Timber Loads • Upgrade Big Timber Auto to a 50 MVA transformer • Reconductor weak 50 kV line near Big Timber • Add capacitors to Big Timber and Livingston area distribution substations

  4. Uncertainty Scenarios Scenarios Considered: • Extreme Winter • Low Thermal, Heavy Import • High Wind System Wide • High Generation North of Great Falls (NOGF) • Similar to stakeholder suggestion Study Assumptions: • N-0 and N-1 conditions considered • All existing Special Protection Schemes considered

  5. Extreme Winter Scenario Details • 2017 Extreme Winter load profile (1:50 forecast) • Hydro plants significantly reduced • Rivers/reservoirs partially frozen • Thermal plants dispatched at max • Corette assumed to be mothballed • Wind dispatched at 5% Scenario Findings • 230 kV and 161 kV systems more heavily relied on to supply the underlying 100 kV systems • Loss of Butte area 161/100 kV tie overloads remaining 161/100 kV tie • 100 kV system in Judith Gap area overloads from loss of major 230 kV line in Great Falls area

  6. Low Thermal, Heavy Import Scenario Details • 2017 Heavy Summer load profile • All major thermal plants are offline • Wind dispatched at 5% • Path 8 heavily importing Scenario Findings • Kalispell 115 kV tie line overloads (within emergency limits) for the loss of Rattlesnake 230/161 kV auto transformer • Loss of Butte area 161/100 kV tie overloads remaining 161/100 kV tie • Steamplant bus outage causes additional overloads on Billings area 100 kV ties to the higher voltage BES

  7. High Wind System Wide Scenario Details • 2017 Heavy Summer and Light Autumn load profiles • Existing wind projects dispatched at capacity • All other generation dispatched same as original case • MATL has little to no flow at Great Falls Scenario Findings • No new thermal issues • Minor high voltage under outage conditions identified in Two Dot area

  8. High Generation NOGF Scenario Details • 2017 Light Spring load profile • Great Falls and NOGF area hydro generation at max • Other Montana hydro dispatched same as original case • Great Falls and NOGF area wind generation at max • Remaining wind generation dispatched at moderate levels • MATL importing at Great Falls near 300 MW • Path 8, 18, 80 transfers similar to original case

  9. High Generation NOGF Scenario Findings • Butte area 100 kV line heavily loaded under N-0 conditions • Loss of Great Falls – Ovando 230 kV line overloads 100 kV lines in Helena area • Loss of Great Falls – Judith Gap – Broadview 230 kV line overloads 100 kV lines in Harlowton, Judith Gap, and Broadview areas

  10. Conclusions • System still robust in most areas, few new potential problems found. • Benefits of widely dispersed generation are demonstrated. • Potential weaknesses in the 100 kV system were identified. • Line or transformer upgrades and/or new facilities could be required to mitigate problems observed. • This analysis is “Informational” and not the primary driver for mitigation. • Because of the uncertain nature of these scenarios, formal mitigation plans have not been developed. • In some cases, new generation or TSR requests would drive mitigation for problems observed.

More Related