101 N. Park Street Brownfield Redevelopment Project Update & Summary December 30, 2009

101 N. Park Street Brownfield Redevelopment Project Update & Summary December 30, 2009. Bridge Front - 1999 Clovelly Centre- 2001 101 N. Park - 2008. Redevelopment Evolution. Bridgestone Firestone Service Station. AUTO HOISTS. Leaking Waste Oil UST. A N N I E S. FUEL UST s.

Download Presentation

101 N. Park Street Brownfield Redevelopment Project Update & Summary December 30, 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 101 N. Park StreetBrownfield RedevelopmentProject Update & SummaryDecember 30, 2009

  2. Bridge Front -1999Clovelly Centre-2001101 N. Park -2008 Redevelopment Evolution

  3. Bridgestone Firestone Service Station AUTO HOISTS Leaking Waste Oil UST A N N I E S FUEL UST s

  4. Grease Pit Area 2001: Post Demolition Contaminated Soil ( destined for landfill ) Leaking Waste Oil UST Area

  5. Soil Contaminated ( black staining ) From Waste Oil UST

  6. City Sidewalk Improperly Abandoned Piping from Fuel USTs

  7. Soil and Groundwater Contamination Significant Clean-up in 2001

  8. Meanwhile: Foundations Complete at Radio Center Phase 1

  9. Clovelly Centre Project Stalls September 2001

  10. Time Takes its Toll Retaining Wall in Basement Slowly Fails 101 N. Park Street Project Initiated Winter-Spring 2009

  11. Shoring Retaining Walls and Rehab Concrete Column Foundations

  12. Dewatering for Elevator Shaft Construction Shaft Pit Area Dewatering Pump

  13. 101 N. Park

  14. FIFTH FLOOR LAYOUT

  15. FOURTH FLOOR LAYOUT

  16. 3RD & 2ND FLOOR LAYOUT

  17. STREET LEVEL

  18. BASEMENT PARKING

  19. On-site Progress December 22, 2009

  20. Happy New Year 2010