1 / 51

Green Building at 33rd and Chestnut

Green Building at 33rd and Chestnut. Group 23: Andrew Good Brad Ryals Bill Curran Andrew Hale Advisor: Professor Lou DaSaro. Background. -Drexel University -Need for Integrated Sciences Building -Designed and operated with an environmentally conscious approach

fox
Download Presentation

Green Building at 33rd and Chestnut

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Green Building at 33rd and Chestnut Group 23: Andrew Good Brad Ryals Bill Curran Andrew Hale Advisor: Professor Lou DaSaro

  2. Background -Drexel University -Need for Integrated Sciences Building -Designed and operated with an environmentally conscious approach -Preliminary architectural layout -Commitment to increased energy efficiency and development of a sustainable environment

  3. Problem Statement Understand architectural, spatial, and occupational requirements of Drexel’s Integrated Sciences Building. Generate engineered designs for all major building systems in a fashion consistent with Drexel’s green desires.

  4. LEED Checklist -Means of quantifying achievement of green and sustainable goals: LEED Accreditation -Project Goal: Silver Status Summary of LEED point goals

  5. Site Background -Location: -NE Corner of S.33rd & Chestnut St. Philadelphia, PA -Area of lot: 1.03 acres -Current Conditions: -Parking lot -Sidewalk -Grass

  6. Site Background -Photos: Existing Sidewalk Site Location: View from SW Existing Parking Lot

  7. Site Background Sociologic -College campus Demographic Mostly 18-24 year olds Geologic -Schist Topographic: -Elevations +47 to +42 Economic -Parking revenue

  8. Site Background -Storm water runoff -Minimize increase -Utilities: -Relocation required -Subsurface Obstructions: -Septa R.O.W -Korman Center Basement

  9. Design Constraints -External criteria -Project-specific criteria

  10. External Criteria Uncontrollable factors innate to site placement -Location of Philadelphia -Immediate external constraints due to: -Geographic region -City requirements -Site conditions

  11. External Criteria -Geographic region constraints: -Rainfall -Wind -Seismic -Climate

  12. External Criteria -Average yearly rainfall: Philadelphia, Pa -2007 World Book Encyclopedia - 44 to 48 inches

  13. External Criteria -Wind speed: Philadelphia, PA -IBC 2006 Figure 1609 - 90mph

  14. External Criteria -Seismic -IBC 2006: -Spectral response acceleration for short period (0.2sec) -Ss=0.35 -Spectral response acceleration for 1 sec period -S1=0.08 Values will be used with site coefficient values to calculate design spectral response acceleration.

  15. External Criteria -Climate: Philadelphia, PA -IECC 2006 Section 301 -Climate zone 4A

  16. IECC 2006 TABLE 301.3(2) INTERNATIONAL CLIMATE ZONE DEFINITIONS External Criteria -Climate zone 4A

  17. External Criteria -City Requirements: -Philadelphia Building Code 2007 -International Building Code 2006 -International Fire Code 2006 -International Mechanical Code 2006 -International Energy Conservation Code 2006 -ICC Electrical Code

  18. External Criteria -Site conditions: -Depth of bedrock -Ground water table -Soil composition

  19. External Criteria -Geotechnical investigation: -Bedrock at 34’ -GWT at 14’-17’ -Composition: fill, silty sand, schist bedrock

  20. Project-Specific Criteria Constraints established by the client Client: Drexel University -Spatial requirements -Improved energy efficiency -Model of green building technology -Architecture consistent with campus -Minimal cost

  21. Project-Specific Criteria Spatial Requirements: -20,500 SF Office space -11,200 SF Classrooms -50,000 SF Laboratory space

  22. Project-Specific Criteria Modified footprint: -25,000 SF Office space -12,000 SF Classrooms -48,000 SF Laboratory Space

  23. Project-Specific Criteria Original Footprint Improve energy efficiency: -Atrium requires gross excess of conditioned air. Adjusted Footprint

  24. Footprint Efficiency-Equest Simulation Energy Saving Electric: 40% Gas: 30%

  25. Project-Specific Criteria Model of green building technology: -Incorporate green building techniques -Utilize LEED certification system to quantify the degree of sustainability

  26. Law Building Race Street Dorm Bossone Center Project-Specific Criteria Architecture consistent with new buildings:

  27. Project-Specific Criteria Minimal cost: -Value engineered design within budget -Justify increased initial cost with decreased operating costs

  28. Initial Design Concepts Major systems: -Site -Structural -Mechanical -Electrical -Plumbing Must satisfy external and project-specific criteria as efficiently as possible.

  29. Initial Site Design Introduction: Site design determines impervious areas, placement of walkways, and the extent of landscaping.

  30. Initial Site Design System requirements: -Adequately handle storm-water - 100 yr 24 hour rainfall ≈ 7” -Facilitate efficient pedestrian circulation - Estimated 1,300 pedestrians / hr -Utilize site area and provide welcoming appearance

  31. Initial Site Design System Alternatives: -Porous concrete walkways Pros: Level walkway, aesthetic Cons: Increased heat island effect -Pervious Concrete Pros: Promotes vegetation Cons: Requires maintenance

  32. Initial Site Design System Alternatives: -Green roof Pros: Direct use of water collected Cons: Maintenance costs -Rainwater Harvesting Pros: Low cost, recycles water Cons: Not aesthetically pleasing

  33. Initial Structural Design Introduction: Structural design determines how loads exerted on the building will be directed to the foundation system.

  34. Initial Structural Design System requirements: -Provide adequate resistance to loads. -Live loads (IBC 2006): 100psf-corridors on 1st floor, 80psf- 2nd floor corridors and above, 40psf-classrooms -Dead loads: 70psf-roof, 95psf-floors -Wind loads: -12.7psf sidewalls, 14.5psf windward, -9psf leeward -Seismic loads: 50psf exerted on veneer -Must not disrupt serviceability. -L/360 deflection

  35. Initial Structural Design System alternatives: -Framed structural system Pros: Quick construction Cons: Expensive -Load bearing structural system Pros: Simple design Cons: Limited span length Framed structure > Load bearing structure

  36. Initial Structural Design System alternatives: -Concrete Frame Pros: Regional, recycled material Cons: Progress susceptible to weather -Steel Frame Pros: High strength to weight ratio Cons: Long lead time

  37. Initial Mechanical Design -Introduction: Mechanical design determines the type and sizing of heating and cooling equipment. -Outdoor design temperatures: Winter: 0 F Summer: 95 F -Indoor design temperatures: Winter: maximum of 72 F Summer: minimum of 75 F

  38. Initial Mechanical Design System Requirements: -Sensible/Latent loads -People: 0.6 MBtu/h -Lights/Equipment: 2.4 MBtu/h -Ventilation: 27,000 CFM Based on ASHRAE approximations

  39. Initial Mechanical Design System Alternatives: -Geothermal Heat Pump Pros: Uses groundwater for heat exchange Cons: Additional excavation -VAV system Pros: Variability of flow to spaces Cons: High energy to provide cooling

  40. Initial Electrical Design Introduction: The electrical system needs to be able to power the building’s lighting and equipment (Lab, HVAC, and Office)

  41. Initial Electrical Design System Requirements: -Electrical Lighting Demand -Classrooms 1.2 W/sf -Offices 1.0 W/sf -Electrical Equipment Demand -Offices 0.81 W/sf IECC 2006 & ASHRAE Fundamentals

  42. Initial Electrical Design System Alternatives: -Solar power Pros: Lower demand charges Cons: Variable supply -Wind power Pros: Reduce dependence on non- renewable energy Cons: Not aesthetically pleasing

  43. Initial Plumbing Design Introduction: The plumbing system distributes potable water to the building fixtures and also is responsible for removing wastewater.

  44. Initial Plumbing Design System Requirements: Estimated Minimum Plumbing Facilities -Toilets: 30 (Max 1.6 gpf) -Lavatories: 30 -Lab Sinks: 60 IBC 2006& from GRCH, Inc. Lab study

  45. Initial Plumbing Design System Alternatives: -Grey water system Pros: Effective water resource management. Cons: Additional piping required. -Conventional sanitary system Pros: Standard procedure - zero learning curve. Cons: Increases strain on regional sanitary sewer system.

  46. -Project and design budget -Design schedule Project Planning

  47. Project and Design Budgets

  48. Design Schedule

  49. Race Street Dorm Pic: http://www.drexel.edu/depts/pdc/pages/projects.asp Law Building Pictures: http://www.drexel.edu/law/law-building.asp Bossone Building Pictures: http://www.drexel.edu/univrel/events/bossone.asp LEED Logo: http://danielsandhouse.com/images/LEED_logo.gif Cut cost: https://www.storesonlinepro.com/files/1701548/uploaded/cut%20costs.jpg Electric: http://www.hse.gov.uk/workplacetransport/images/warning-electricity-2.gif Plumbing: http://discussion.autodesk.com/servlet/JiveServlet/download/188-544838-5548548-150193/plumbing_system.png Plumbing Aerial Site photo: http://maps.google.com/maps?ie=UTF-8&tab=wl Geologic map: http://www.sas.upenn.edu/earth/new.html Topographic map: http://www.drexel.edu/depts/pdc/pages/topographic.asp Precipitation map: http://www.worldbook.com/wb/Students?content_spotlight/climates/north_american_climate_pennsylvania References

  50. Acknowledgments We would like to thank the following individuals for their contributions and guidance this term: Professor DaSaro Professor Mitchell Dr. Martin Mr. Warren Waldorf

More Related