Mod 373 “Governance of NTS Connection Processes”

This report discusses the contents, options, and requirements of feasibility studies for National Transmission System (NTS) connections, based on location and type. It addresses statutory legislation, health and safety obligations, and provides example content headings for different types of studies.

Download Presentation

Mod 373 “Governance of NTS Connection Processes”

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Mod 373 “Governance of NTS Connection Processes” Review Group 0291 11 August 2010 WG0508: Feasibility Study Report – Contents

  2. Background (1) • Feasibility Studies are invariably bespoke in nature in order to fulfil the customer’s requirements - dependent on the location and type of NTS connection required • Feasibility Studies may be requested by customers on an ‘optioneering’ basis; can therefore be speculative • The current Feasibility Study Agreement does not confer any obligations on either party to develop or modify an NTS connection • National Grid does not generally require a Feasibility Study to be undertaken where the customer requires a new NTS connection in a ‘greenfield’ site

  3. Background (2) • National Grid is required to adhere to statutory legislation and has legal obligations in relation to the NTS connections process: • Health and Safety at Work Act 1974 • Pipeline Safety Regulations (PSR) 1996 • Reg 5 – design of a pipeline • Pressure Systems (Safety) Regulations (PSSR) 2000 • Imposes a duty on designers, manufacturers etc to ensure systems are fit for purpose so as to prevent danger (Reg 4) • Responsibility on National Grid to ensure Safe Operating Limits (SOL) on our customers’ and our own equipment are not exceeded

  4. Feasibility Study - Contents (1) • Contents of a feasibility study report depend on the nature of the study being undertaken • Example content headings for a power station ramp rate study: • Introduction • The Model • Scenarios Modelled • Conclusions

  5. Feasibility Study - Contents (2) • Example content headings for increase in offtake pressure where NGG owns the metering installation: • Introduction • Background • Filters • Metering • Gas Pre Heat System • Fuel Gas Skid Unit • Regulator Arrangement • Transient Study • Conclusions and Recommendations

  6. Feasibility Study - Contents (3) • Example content headings for new connection at large, complex existing site: • Executive Summary & Introduction • Codes of Practice & Legislation • National Grid Site Facilities • Design Parameters • New Connection • Mechanical Design • Gas Flow and Isolation Valves Configuration • Corrosion Protection • Electrical and Instrumentation • Description of Equipment and Devices • Crossing and Installation Techniques

  7. Feasibility Study - options • Standalone – as is • Combined with Conceptual Design Study (CDS) – does not include final detailed design and construction • review the use and purpose of the CDS in order to achieve this • Others?