This report discusses the contents, options, and requirements of feasibility studies for National Transmission System (NTS) connections, based on location and type. It addresses statutory legislation, health and safety obligations, and provides example content headings for different types of studies.
E N D
Mod 373 “Governance of NTS Connection Processes” Review Group 0291 11 August 2010 WG0508: Feasibility Study Report – Contents
Background (1) • Feasibility Studies are invariably bespoke in nature in order to fulfil the customer’s requirements - dependent on the location and type of NTS connection required • Feasibility Studies may be requested by customers on an ‘optioneering’ basis; can therefore be speculative • The current Feasibility Study Agreement does not confer any obligations on either party to develop or modify an NTS connection • National Grid does not generally require a Feasibility Study to be undertaken where the customer requires a new NTS connection in a ‘greenfield’ site
Background (2) • National Grid is required to adhere to statutory legislation and has legal obligations in relation to the NTS connections process: • Health and Safety at Work Act 1974 • Pipeline Safety Regulations (PSR) 1996 • Reg 5 – design of a pipeline • Pressure Systems (Safety) Regulations (PSSR) 2000 • Imposes a duty on designers, manufacturers etc to ensure systems are fit for purpose so as to prevent danger (Reg 4) • Responsibility on National Grid to ensure Safe Operating Limits (SOL) on our customers’ and our own equipment are not exceeded
Feasibility Study - Contents (1) • Contents of a feasibility study report depend on the nature of the study being undertaken • Example content headings for a power station ramp rate study: • Introduction • The Model • Scenarios Modelled • Conclusions
Feasibility Study - Contents (2) • Example content headings for increase in offtake pressure where NGG owns the metering installation: • Introduction • Background • Filters • Metering • Gas Pre Heat System • Fuel Gas Skid Unit • Regulator Arrangement • Transient Study • Conclusions and Recommendations
Feasibility Study - Contents (3) • Example content headings for new connection at large, complex existing site: • Executive Summary & Introduction • Codes of Practice & Legislation • National Grid Site Facilities • Design Parameters • New Connection • Mechanical Design • Gas Flow and Isolation Valves Configuration • Corrosion Protection • Electrical and Instrumentation • Description of Equipment and Devices • Crossing and Installation Techniques
Feasibility Study - options • Standalone – as is • Combined with Conceptual Design Study (CDS) – does not include final detailed design and construction • review the use and purpose of the CDS in order to achieve this • Others?