1 / 26

Monterey Peninsula Water Supply Project Cost/Financial Workshop

Monterey Peninsula Water Supply Project Cost/Financial Workshop. December 13, 2012. CPUC Cost Workshop Financial Modeling Utility Rate Base Financing Wednesday, December 12: 1:00 p.m. to 5:00 p.m. . Key Assumptions. Plant Size scenarios 9.0 MGD

frey
Download Presentation

Monterey Peninsula Water Supply Project Cost/Financial Workshop

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Monterey Peninsula Water Supply ProjectCost/Financial Workshop December 13, 2012

  2. CPUC Cost WorkshopFinancial ModelingUtility Rate Base FinancingWednesday, December 12: 1:00 p.m. to 5:00 p.m.

  3. Key Assumptions • Plant Size scenarios • 9.0 MGD • 5.4 MGD, supplemented with 3,500 AFY of GWR(1) • Financing Scenarios: • Primary Case -- SRF Debt & CAW Equity • Alternative Case – actual cost of debt & CAW Equity • Customer Surcharge totaling $99M(2) • Utilize $20M of CAW short term debt during construction • Cost of Capital: • Cost of SRF Debt 2.50% • Cost of Equity: 9.99% • 53% equity / 47% debt • Cost of CAW Debt: 5.00%market(3) (vs. 6.63% authorized) • Property taxes avoided on plant funded with SRF and Surcharge #2 • GWR is assumed to cost between $2,500/AF to $3,000/AF based on information provided by the MRWPCA • $99 M equals about 33% of rate base. Currently, contributions equal about 10% of rate base. • Current market rate for AWK 30-year debt is approximately 4.5%, for both taxable and tax-exempt issuances. S&P and Moody’s recently raised their outlook for AW debt, which could result in lower future debt costs

  4. We believe the entire project, including the pipeline, qualifies for SRF loans • We have proposed a rate base offset of $100M through a surcharge on customers’ bills • We will use $15M - $20M of our short-term credit capacity to extend the period between draws and limit interest expense during construction • The surcharge and SRF amounts are exempt from real property taxes, at an annual savings of $2.5M CAW Strategy to Limit Revenue Requirement

  5. Capital & Financing Summary For Desal Plant Capital Cost Financing ¹ As compared to approved WPA equivalent of $277.5M ($297.5 original RDP cost, minus $6M maintenance reserve and $14M pre-effective costs) ² Includes Desal Plant only. The CAW in-service area facilities Revenue Requirement is estimated at an additional $13.2M with SRF ³ Based on assumed cost of $2,500/AFY

  6. Sources & Uses of Cash 5.4 MGD Plant – SRF Financing Based on the latest procedural schedule the dates would shift out six months later but the dollar impact would remain the same.

  7. Sources & Uses of Cash 9.0 MGD Plant – SRF Financing Based on the latest procedural schedule the dates would shift out six months later but the dollar impact would remain the same.

  8. Annual Customer Surcharge Based on the latest procedural schedule the dates would shift out six months later but the dollar impact would remain the same.

  9. Projected Impact to Monterey Water Bills • Assumptions: • Usage = 1ccf = 100 cubic feet = 748 gallons • Data to determine Percentile Bill usage is from May 2011 consumption data • Proposed 2017 bill includes multiple estimates • Current bills calculated based on approved tariff rates and surcharges as of December 7, 2012

  10. CPUC Cost WorkshopFinancial ModelingDiscuss Compliance Filing and Present Financial ModelWednesday, December 12: 1:00 p.m. to 5:00 p.m.Thursday, December 13: 9:30 a.m. to 12:30 p.m.

  11. Development & Submission of Financial Model • CAW began developing the current model in February 2012 • Main objective was to create a framework for evaluating alternatives that could be easily updated as cost estimates & other assumptions change and to allow for different capital and financing scenarios • This model was used for the application filed by CAW in April 2012 • During the Fall of 2012, CAW worked jointly with representatives from DRA and MPWMD on further development of the model • CAW made the following changes to the financial model based on discussions with DRA and MPWMD: • Consolidated key assumptions into one user page • Created high-level summary output for users • Identified O&M expenses as either fixed or variable and added an input to allow plant production at less than 100% capacity • Added functionality to allow for a contribution to construction costs from an outside public agency • Provided a third financing scenario to allow for a combination of SRF debt and CAW debt • On 11/15/12, CAW submitted the financial model to the CPUC and all parties to be used to compute various revenue requirement scenarios

  12. Financial Model Inputs - Plant

  13. Financial Model Inputs - Financing

  14. Financial Modeling Inputs – Surcharge & Contributions

  15. Project Summary Output

  16. CPUC Cost WorkshopFinancial ModelingRun Financial Model for Possible Project ScenariosBreak Out SessionWednesday, December 12: 1:00 p.m. to 5:00 p.m.Thursday, December 13: 9:30 a.m. to 12:30 p.m.

  17. Appendix

  18. California American In-service Area Facilities ¹ Does not include AFUDC ² Does not include any customer surcharge

  19. Capital & Financing Summary For Desal Plant – No Surcharge ¹ As compared to approved WPA equivalent of $277.5M ($297.5 original RDP cost, minus $6M maintenance reserve and $14M pre-effective costs) ² Includes Desal Plant only. The CAW In-service Area Facilities Revenue Requirement is estimated at an additional $13.2M with SRF ³ Based on assumed cost of $2,500/AFY

  20. Projected Impact to Monterey Water Bills (no surcharge #2) • Assumptions: • Usage = 1ccf = 100 cubic feet = 748 gallons • Data to determine Percentile usage is from May 2011 • Proposed 2017 bill includes multiple estimates • Current bills calculated based on approved tariff rates and surcharges as of December 7, 2012

  21. Capital Financing Considerations #1

  22. Capital Financing Considerations #2

  23. Capital Financing Considerations #3

  24. Capital Financing Considerations #4

  25. Capital Financing Considerations #5

  26. Capital Financing Considerations #6

More Related