1 / 37

Basis of Estimates Selecting Pay Items

Basis of Estimates Selecting Pay Items. Melissa Hollis Basis of Estimates Coordinator Engineering Systems Support Section State Specifications and Estimates Office October 2014. Basis of Estimates. Part 1: Introduction to the Basis of Estimates Chapters 1-10 Part 2: Selecting Pay Items

Download Presentation

Basis of Estimates Selecting Pay Items

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Basis of Estimates Selecting Pay Items Melissa Hollis Basis of Estimates Coordinator Engineering Systems Support Section State Specifications and Estimates Office October 2014

  2. Basis of Estimates • Part 1: Introduction to the Basis of Estimates • Chapters 1-10 • Part 2: Selecting Pay Items • Chapters 11-20 • For FDOT and Consultant designers • Update training for bulletins, as needed • Part 3: Estimating and Review • Recent changes • Pricing details for FDOT Estimators

  3. Part 1: Introduction to the Basis of Estimates • BOE Online • Chapter 11: 100s • MOB, MOT, Erosion, Clearing & Grubbing • Chapter 12: 200s • Earthwork, Base • Chapter 13: 300s • Asphalt, Friction Course • Concrete Pavement • Chapter14: 400s • Structures, Drainage • Chapter 15: 500s • Curb, Sidewalk, Guardrail, Fence

  4. Part 1: Introduction to the Basis of Estimates • BOE Online • Chapter 16: 600s • Signals, Conduit, Pull Boxes • Chapter 17: 700s • Signing, Pavement Marking, Lighting • Chapter 18: 800s • Mass Transit- Railroad • Chapter 19: 900s • Special, Developmental • Chapter 20: 1000s • Utilities

  5. Chapter 6 Pay Items • Example Pay Item Groups • 334- 1- AA Superpave Asphaltic Concrete, TN • 700- 1- AB Single Post Sign, AS

  6. Chapter 10: Formatting Pay Items Every Pay item group: Details Structure Active items

  7. 100s: Maintenance of Traffic • 102-1 Maintenance of Traffic, LS • NO Erosion Control Devices- use 104 items • NO Temp Fencing- use Ped LCDs or 550 items • NO Temp Drainage quantities • NO Temp Asphalt- use Special Detour • NOT a “catch all” for other work • NO contingency quantities • NO weather quantities

  8. 100s: Maintenance of Traffic • 102-2 Special Detour, LS • Temporary Asphalt • Show the location and a typical section with minimum design • DO NOT show base quantities • DO NOT show asphalt quantities • Why? • The contractor is responsible for “installing and maintaining the detour”. If we provide quantities, then we have the possibility of claims when the detour requires additional materials. • Bulletin Pending

  9. 100s: Maintenance of Traffic • 102-3 Commercial Material for Driveway Maintenance, CY • Through 2014: may use estimated quantity based on xxx cy per mile • Effective 2015: Identify locations and quantity on summary box

  10. 102-74- Channelizing Device, LF • Vehicular • Pedestrian • Read Index 600, including recent changes for Ped LCDs • Orange “Construction Fence” is not an acceptable channelization device.

  11. 102-104 and 102-107- Temp Signals • 102-104 Temp Signalization, ED • Includes maintenance of the signals throughout the duration of the project. • Includes moving signal heads • Includes “temporary heads” or poles, as needed • 102-107 Temp Detection, ED • Includes maintenance of the detection throughout the duration of the project • Includes temporary detector • What types are acceptable? • A: Provide temporary traffic detection equipment listed on the APL.

  12. 100s: Maintenance of Traffic • 104- xx Erosion Control • DO NOT include quantities “based on replacement every xx months” • Why? • maintenance and replacement of items is included in the item. • Products are selected from the Erosion and Sediment Control Handbook. DO NOT call for hay or straw bales, or any specific product. • 104-10-3 Sediment Barrier, LF • 104-18 Inlet Protection, EA (per each inlet)

  13. 100s • 107: Litter Removal and Mowing • Identify locations in the plans • Yes- this may require several plans sheets for urban areas, but it is still an overall reduction in pages from the comp book.

  14. 200s Base Materials • 285-7xx- Optional Base, SY • 286- Turnout Construction

  15. 300s Pavement • 327-70 Milling, SY • 334-1-AA Superpave, TN • AA options set by State Materials Office to coordinate with current specs & binders • NOT for temporary locations • 337-7-AA Friction Course, TN • AA options set by State Materials Office • 339-1 Misc Asphalt, TN • Used for under guardrail, bicycle paths, etc. • NO TESTING

  16. 300s Pavement • 350s Concrete Pavement • NOT FOR BRIDGES • 350-5: Joints (new and existing pavement) are paid separately for the sealing/resealing) • 350-6: Sealing Cracks • See 458 for bridge joints • 353 Concrete Pavement Slab Replacement • NOT FOR BRIDGES, SLOPE PAVEMENT, ETC.

  17. 400s Structures • 400- Concrete, CY • Concrete by class • For culverts, endwalls, superstructure, substructure, etc. • READ THE IDS (Instructions for Design Standards) for the intended application • NOT for incidental concrete, such as lighting or signals poles, pull boxes, or cabinet foundations/bases. Incidental concrete is included in work/materials for these items. • 415- Reinf Steel, LB • READ THE IDS; some steel is incidental

  18. 425-430s Drainage • 425 Inlets • 430 Drainage Pipe • NOT for utility use/JPA projects • Read the Standard/IDS for drainage structures • 430-18- Jack & Bore • drainage pipe only • Special: • Minor changes to standard: note changes in the plans; payment under standard pay item • No applicable standard: call for assistance with pay item. “Special” pay items are blocked.

  19. 450-455s Piling & other foundations • 450 Beams • 455 Drilled Shafts • Call for other sizes/shapes • 455 Protection of Existing Structures • PENDING for July 2015 • Spec & Pay Item move to 108 • New plan requirements • New guidance in 2015 PPM- locations (buildings) to be protected must be identified in the plans • 458 Bridge Joints

  20. 500s: Incidental Construction • 515 Railings • 521 Traffic Barrier/Railings • Read the IDS • Guide rail, handrails, Ped/Bike with Infil • 520 Curb Elements “Curb” • Curb • Curb & Gutter • Traffic Separator • 522 Sidewalk (4” & 6”) • 527 Detectable Warnings

  21. 500s: Incidental Construction • 524 Slope and Ditch Pavement • New/replacement • Cleaning & Sealing Joints

  22. 500s: Incidental Construction • Guardrail • End to End measurement • End Anchorage- per ea • one for each end, type as applicable

  23. 500s: Incidental Construction • Guardrail • End to End measurement • Paid as type outside of transition • End Anchorage- per ea • Bridge anchorage • Other end, type as applicable Correct: Roadway W-Beam Incorrect: Thrie Beam + Roadway W-Beam

  24. 500s: Incidental Construction • 546 Rumble Strips • Sets- approach to intersection, across roadway • Shoulder • PENDING: Center line and Edge Line (Rumble Stripe) Spec and pay item will change unit of measurement from “Per mile” to “net mile”- end to end minus bridges, vs. stripe measure • 550 Fence • Temp Fence, only as identified in spec • Does NOT include “orange construction fence”

  25. 500s: Incidental Construction • 590 Irrigation System, LS • 591 Landscape Sleeve, LF • Developmental Standard Index 591 • Project-by-project approvals for standard • Pay items assigned to approved projects • Cost effective vs. Jack & Bore later • Design effective, if coordinated with landscape plans • Not for “possible” future system, where locations cannot be coordinated

  26. 600s: Traffic Control Signals and Devices • COPS: Coordination of Products and Specifications • QPL merge with APL, effective with Jan 2015 lettings • Web links for both with provide redirect to new application • Specifications and Pay items: most changes have been completed • Minor changes pending • 639- Power/Electrical Service • 740 series- Traffic Monitoring (Transp Statistics)

  27. 600s: Traffic Control Signals and Devices • 630 Conduit • 635 Pull, Splice, and Junction Boxes • 670 Traffic Controller Assembly • 671 Controller “electronics” • 676 Cabinet “shell, with or without wiring” • Removal Items- No Section 690 • Remove pole and “all attachments” • Span wire or arm • Signal assembly • Pedestrian Detector • Pedestrian Signal • Ask about other items; ongoing changes

  28. 700s: Signing, Pavement Marking & Lighting • 700- Signs • If it looks like a sign, acts like a sign… • From PPM Vol 2, 23.6.2: • Any signs to be mounted on signal span wires should be shown and listed on the signalization plan for illustration and placement purposes.Sign details should be included on the signing plans. (Per Chester Henson, State Roadway Design- signing expert, signs mounted on mast arms should be addressed the same way.) • PPM Vol 2, 24.6.2: • Any span wire or mast arm mounted signs shall be coordinated with the appropriate signing and pavement marking plans to avoid duplication. • The sign details for traffic signal signs must be included on the signalization plans, if signing and pavement markings are not included in the plans package.

  29. 700s: Signing, Pavement Marking & Lighting • 700-6 Highlighted sign • LED Border • 700-7 Embedded DMS • 700-8 Front Access DMS • 700-9 Walk-in DMS • Static sign paid separately • 700-10 DMS Structure

  30. 700s: Signing, Pavement Marking & Lighting • 701- Audible & Vibratory • 709- Two Reactive Components • 711- Thermoplastic • Hot Applied “Standard” • Rumble Stripe “with 546” • Preformed • 713- Permanent Tape • Pending: Guidance/Bulletin for July 2015 • Contrast for light asphalt and concrete • Locations for Rumble Stripe vs 701

  31. 700s: Architectural, Shared Use Path, Incidental • 750, 751 series- Buildings • 751 “Other Architectural” • Bus Shelter • Bicycle Rack • Trash Receptacle • Bench • Pedestrian Plaza • 780 ITS Road Weather Info System(RWIS) • 785 ITS items moved to 600 series for cabinet, poles, etc.

  32. 800s: Mass Transit • Rail pay item structure was created 5+ years ago. • Call if you have a project with rail or other mass transit needs. • New pay items will be made available as needed.

  33. 900s: Special Items • Developmental • Developmental Specifications • Developmental Standards • Other Special Use pay items • Follow rules for requesting developmental secifications or standards • Pay Items will be made available for approved projects.

  34. 1000s: Utility Items • Standard Items • No cost history • Project Specific Tech Specs • Do Not “borrow” pay items from drainage, signals, or signing • Generic Pay Items • Refer to Chapter 6 for the rules • “Wide open” for utility applications • No need to track cost history • No FDOT standards or specifications • Monitored for non-utility applications

  35. BOE Advice • If you don’t see a pay item that you need, please ask. • Existing/available Item groups • Request that an item be opened/activated, if needed • Request that we restore an old item/structure, if needed • Verify that old specs/standards are applicable • Request that we create a new item group • Consider requesting a Developmental Specification and Pay Item • Consider a Generic Pay Item

  36. Thank you for your time! Melissa Hollis Basis of Estimates Coordinator Estimating Systems Support Section State Specifications and Estimates Office Melissa.Hollis@dot.state.fl.us

More Related