Manage construction projects efficiently and analyze timelines for optimal performance. Includes demo, grading, piling, form and pour activities for various floors and structure elements. Evaluate delays, accelerations, critical paths, and turnover processes.
E N D
1995 Demo & Grading Demo & Grading Pilings Pilings Form & Pour Pile Caps/Grade Beams Form & Pour Pile Caps/Grade Beams Form & Pour 1st Flr/Columns/Walls Form & Pour 1st Flr Form & Pour 2nd Flr/Columns/Walls Form & Pour 2nd Flr Form & Pour 3rd Flr/Columns/Walls Form & Pour Roof (Dry In) Form & Pour 3rd Flr Bldg Specialties & Finishes Form & Pour Roof (Dry In) Receive & Set Equipment Planned Duration Process Piping Process Electrical Actual Duration Instrumentation Checkout & Turnover Line 1 Delay Line 2 Acceleration Line 3 Planned vs Actual Critical Path 1994 1995 1996 1997 Piling Delay Causes Acceleration 1/3/96 “Dry In” ON TIME