1 / 13

HBD Air Cooling System

HBD Air Cooling System. TK Hemmick for the HBD group 8/25/06. Why is Cooling Needed? . The noise debugging of the HBD showed that RF shield covers must be applied above the pre-amp cards. These covers give excellent noise performance but trap heat. The pre-amps & LDO regulators reach 50-60C.

gaerwn
Download Presentation

HBD Air Cooling System

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HBD Air Cooling System TK Hemmick for the HBD group 8/25/06

  2. Why is Cooling Needed? • The noise debugging of the HBD showed that RF shield covers must be applied above the pre-amp cards. • These covers give excellent noise performance but trap heat. • The pre-amps & LDO regulators reach 50-60C. • These temperatures are not a fire hazard, but they would limit the lifetime of the pre-amps. • So…we designed a way to cool them.

  3. How can cooling be accomplished? • The covers: • Block normal convention (the problem). • Form a channel for air (the solution). • There are 6 covers around the azimuth and 6 gaps between the covers. • The gaps have sufficient room for a 3/8” tube from which to supply air. • How much air? • How to deliver air?

  4. Overview of Information • System requirements: • Power load handling. • Amount of air required (theory) • Amount of air required (measurement) • Air handling system. • Pressure & Flow (theory) • Pressure & flow (measurement) • System parts (Prototype & Proposal) • Exploded view of parts. • Materials list. • MSDS links.

  5. Power load. • One preamp card requires: • +6V at 1.8 A • -6V at 1.2 A • 18 Watts • LDO regulators on board can handle higher temp, preamps cannot. • Pre-amps = +5V at 1.8 A & -5V at 1.2 A • 15 Watts. • Air flow should remove 15 Watts from every board.

  6. Air requirements (theory) • One board… • 15 Watts = 15 Joules/sec. • Air can be approximated well as an ideal diatomic gas (CP=7/2 R) • 15 Joules in one second. • Allow 20 degree rise. • Requires 0.64 liters in one second. • Requires ~40 l/min~80 cfh NOTE: Upper limit (ignores natural convective cooling)

  7. Air requirements (measurement) • One circuit card was outfitted with a small tube to spread air flow over card. • Tube = 3/8” diameter, 2.5” water, 5 small holes (uniform flow w/ reasonable pressure & small holes) • Pre-amp temp as a function of flow is plotted. • 50 cfh is good target for cooling each board. • 6 board per side = 300 cfh = 5 cfm per side.

  8. Pressure and Flow (theory) • P in final tube = 2.5” water • DPtot <0.2” water to assure uniform air delivery. • F = 5 cfm, L=15” (conservative) • h=1.8x10-5 Pascal x sec • r = 0.26 inches (d=0.52 inches). • Flow is not purely laminar… • Set ID of tubing to ¾” F 5/6F 4/6F 3/6F 2/6F 1/6F http://www.google.com/search?hl=en&lr=&client=firefox-a&rls=org.mozilla%3Aen-US%3Aofficial&q=2*%28%2815*5+cubic+feet+per+minute+*+8+*+1.8E-5+pascal+seconds+*+15+inches%29%2F%286*pi*0.4+torr%29%29%5E0.25+in+inches&btnG=Search

  9. Pressure & Flow (measurement-1) • Assemble prototype manifold. • All tubing dimensions correct. • Measure air flow parameters.

  10. Pressure & Flow (measurement-2) • Measured parameters: • 5 cfm flow. • Pressure in tubes = 2.5” water. • 0.1” water difference from first to last tube. • 6” water is pressure at supply. • Design parameters met exactly. 100% success. Air flow uniform in all holes.

  11. Exploded (Prototype) Part List • Tubing • ¾” ID Poly-flow tubing • ½” ID Latex (surgical) tubing • Nylon plumbing • TEE, coupling; hose barb; elbow; cap. • PTEG Plastic: • 3/8” nominal tubing. Link pointing to MSDS Files: http://skipper.physics.sunysb.edu/HBD/MSDS/

  12. Example Commercial Blower… • The above small (2” x 2”) commercial blower meets all the specifications for our needs. • http://www.acal-radiatron.com/download/micronel/u51dl-tec.pdf • This will be evaluated and compared to other similar units. • Blower selection will be discussed separately.

  13. Proposed System • Manifold: • PVC pipe, ¾” ID, running underneath HBD cable tray. • Nylon NPT3/8”Hose Barb at 6 locations. • Jumper (manifold  individual tube) • 3/8” latex surgical tubing. • Flow tube: • 3/8” ID mylar tube (0.010” thick wall) • Nylon cap.