1 / 30

Readiness Review Course

Screening or Scoping Meeting (ORR vs RA, Authorization Authority (AA) Defined, Startup Notification Report (SNR) Discussed, Schedule). Contractor Plan of Action (CPOA) Prepared. DOE Plan of Action (POA) Prepared by DOE Line Mgr. AA Reviews and Approves CPOA and POA.

gaius
Download Presentation

Readiness Review Course

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Screening or Scoping Meeting (ORR vs RA, Authorization Authority (AA) Defined, Startup Notification Report (SNR) Discussed, Schedule) Contractor Plan of Action (CPOA) Prepared DOE Plan of Action (POA) Prepared by DOE Line Mgr AA Reviews and Approves CPOA and POA Startup Notification Report Prepared and Submitted Contractor RR Implementation Plan (IP) prepared by Contractor RR Team and approved by CTL DOE TL Pre-Assessment Preparation and Planning (Team Selected Initial Team Mtg Pre-Site Visit, IP Drafted) AA Approves SNR and Nominates DOE Team Leader (TL) Prerequisites met (MSA) Readiness Review Process Begins Contractors RR and Final Report DOE RR IP approved by TL Corrective Action Plan (CAP) Submitted and Approved DOE RR and Final Report CAP Submitted and Approved Prestart Findings Closed Contractor Issues Readiness to Proceed (RTP) Prestart Findings Closed DOE Endorsement of RTP and MSA AA Authorizes Startup AA Authorizes Start of RR to RR TL Readiness ReviewCourse Facility Scoping Meeting – Mod 3 Nov 2006

  2. Screening or Scoping Meeting (ORR vs RA, Authorization Authority (AA) Defined, Startup Notification Report (SNR) Discussed, Schedule) Contractor Plan of Action (CPOA) Prepared DOE Plan of Action (POA) Prepared by DOE Line Mgr AA Reviews and Approves CPOA and POA Startup Notification Report Prepared and Submitted Contractor RR Implementation Plan (IP) prepared by Contractor RR Team and approved by CTL DOE TL Pre-Assessment Preparation and Planning (Team Selected Initial Team Mtg Pre-Site Visit, IP Drafted) AA Approves SNR and Nominates DOE Team Leader (TL) Prerequisites met (MSA) Readiness Review Process Begins Contractors RR and Final Report DOE RR IP approved by TL Corrective Action Plan (CAP) Submitted and Approved DOE RR and Final Report CAP Submitted and Approved Prestart Findings Closed Contractor Issues Readiness to Proceed (RTP) Prestart Findings Closed DOE Endorsement of RTP and MSA AA Authorizes Startup AA Authorizes Start of RR to RR TL Readiness Review Process 1 Year Prior to RR Nov 2006

  3. Learning Objectives • An understanding of the importance and purpose of a pre-planning or scoping meeting • Project Management, DOE O 413.3A, M 413.3-1 • Facility Preparation, Planning, Timing, Verification • Understand the AA Selection • Identify Prerequisites Nov 2006

  4. Project Management DOE O 413.3A, M 413.3-1 • Define the work scope . . . • Construction, modification, support SSCs . . . • Equipment testing and subsequent repairs . . . • Documentation development-DSA, procedures, etc. . . • Training, qualification, surrogate operations . . . • Identify task relationships . . . • Predecessor: Procedures . . . • Successor: Operator Training . . . • Plan realistic task duration . . . Essential! • When changes occur, identify all affected tasks . . . Nov 2006

  5. Project Management DOE O 413.3A, M 413.3-1 Nov 2006

  6. Facility Prep and Planning • Engineered controls in place and tested; • Procedures complete, V&V, CM; • Training complete; • Surveillances demonstrated and current; • Management programs in place: • Specific Administrative controls implemented and verified effective. • Issues and other Tracking systems functioning. Nov 2006

  7. Plan to Achieve Readiness • Identify and address Core Requirements early in the schedule: • Prerequisites! • Allow time for implementation: • Training . . . • Procedure V&V . . . • Practice . . . • Can’t Start Too Early! Nov 2006

  8. The Authorization Authority (AA) • DOE Management Official (or Designee) who approves the: • SNR, • CPOA, POA, CAPs, • Appointment of the DOE Team Leader, • Endorsement of Readiness to Proceed, • The startup or restart of a facility. (DOE O 425.1C) Nov 2006

  9. DOE-STD-3006-2000Table 1 – Startup and Restart Requirements Summary Nov 2006

  10. Determination of AA DOE O 425.1C Requirements Nov 2006

  11. Identify Prerequisites • Part of Project Planning – Measurable Milestones • Detailed and Measurable . . . • Tied to Core Requirements - are they met? • Documented in CPOA, POA and IPs Nov 2006

  12. Identify Prerequisites (continued) • Specific Startup Requirements: • Identify ALL SSCs including support systems; • Authorization and Safety Basis; • Operator Training Requirements Completed; • Procedures Finalized (V&V); • Test Program Complete, results approved; • DSA fully implemented; etc; . . . Nov 2006

  13. Authorization Agreement Authorization Basis (AB) S/RID EIS SER Safety Basis (SB) ORR/RA DSA (or equivalent) TSR, HAR, FHA, BIO, USQ NESS Defined Work Scope Special Terms & Conditions WSS PHA Environmental Permits Drawings (facility, tooling, etc.) Technical Manuals Engineering Calculation Notes Contractor Safety Programs Site S&S Plan Emergency Preparedness Plan Identify Prerequisites(continued) Nov 2006

  14. Planning for Failure Nov 2006

  15. Questions Nov 2006

  16. Screening or Scoping Meeting (ORR vs RA, Authorization Authority (AA) Defined, Startup Notification Report (SNR) Discussed, Schedule) Contractor Plan of Action (CPOA) Prepared DOE Plan of Action (POA) Prepared by DOE Line Mgr AA Reviews and Approves CPOA and POA Startup Notification Report Prepared and Submitted Contractor RR Implementation Plan (IP) prepared by Contractor RR Team and approved by CTL DOE TL Pre-Assessment Preparation and Planning (Team Selected Initial Team Mtg Pre-Site Visit, IP Drafted) AA Approves SNR and Nominates DOE Team Leader (TL) Prerequisites met (MSA) Readiness Review Process Begins Contractors RR and Final Report DOE RR IP approved by TL Corrective Action Plan (CAP) Submitted and Approved DOE RR and Final Report CAP Submitted and Approved Prestart Findings Closed Contractor Issues Readiness to Proceed (RTP) Prestart Findings Closed DOE Endorsement of RTP and MSA AA Authorizes Startup AA Authorizes Start of RR to RR TL Readiness ReviewCourse Facility Scoping Meeting – Mod 3 Nov 2006

  17. Screening or Scoping Meeting (ORR vs RA, Authorization Authority (AA) Defined, Startup Notification Report (SNR) Discussed, Schedule) Contractor Plan of Action (CPOA) Prepared DOE Plan of Action (POA) Prepared by DOE Line Mgr AA Reviews and Approves CPOA and POA Startup Notification Report Prepared and Submitted Contractor RR Implementation Plan (IP) prepared by Contractor RR Team and approved by CTL DOE TL Pre-Assessment Preparation and Planning (Team Selected Initial Team Mtg Pre-Site Visit, IP Drafted) AA Approves SNR and Nominates DOE Team Leader (TL) Prerequisites met (MSA) Readiness Review Process Begins Contractors RR and Final Report DOE RR IP approved by TL Corrective Action Plan (CAP) Submitted and Approved DOE RR and Final Report CAP Submitted and Approved Prestart Findings Closed Contractor Issues Readiness to Proceed (RTP) Prestart Findings Closed DOE Endorsement of RTP and MSA AA Authorizes Startup AA Authorizes Start of RR to RR TL Readiness Review Process 1 Year Prior to RR Nov 2006

  18. Learning Objectives • An understanding of the importance and purpose of a pre-planning or scoping meeting • Project Management, DOE O 413.3A, M 413.3-1 • Facility Preparation, Planning, Timing, Verification • Understand the AA Selection • Identify Prerequisites Nov 2006

  19. Project Management DOE O 413.3A, M 413.3-1 • Define the work scope . . . • Construction, modification, support SSCs . . . • Equipment testing and subsequent repairs . . . • Documentation development-DSA, procedures, etc. . . • Training, qualification, surrogate operations . . . • Identify task relationships . . . • Predecessor: Procedures . . . • Successor: Operator Training . . . • Plan realistic task duration . . . Essential! • When changes occur, identify all affected tasks . . . Nov 2006

  20. Project Management DOE O 413.3A, M 413.3-1 Nov 2006

  21. Facility Prep and Planning • Engineered controls in place and tested; • Procedures complete, V&V, CM; • Training complete; • Surveillances demonstrated and current; • Management programs in place: • Specific Administrative controls implemented and verified effective. • Issues and other Tracking systems functioning. Nov 2006

  22. Plan to Achieve Readiness • Identify and address Core Requirements early in the schedule: • Prerequisites! • Allow time for implementation: • Training . . . • Procedure V&V . . . • Practice . . . • Can’t Start Too Early! Nov 2006

  23. The Authorization Authority (AA) • DOE Management Official (or Designee) who approves the: • SNR, • CPOA, POA, CAPs, • Appointment of the DOE Team Leader, • Endorsement of Readiness to Proceed, • The startup or restart of a facility. (DOE O 425.1C) Nov 2006

  24. DOE-STD-3006-2000Table 1 – Startup and Restart Requirements Summary Nov 2006

  25. Determination of AA DOE O 425.1C Requirements Nov 2006

  26. Identify Prerequisites • Part of Project Planning – Measurable Milestones • Detailed and Measurable . . . • Tied to Core Requirements - are they met? • Documented in CPOA, POA and IPs Nov 2006

  27. Identify Prerequisites (continued) • Specific Startup Requirements: • Identify ALL SSCs including support systems; • Authorization and Safety Basis; • Operator Training Requirements Completed; • Procedures Finalized (V&V); • Test Program Complete, results approved; • DSA fully implemented; etc; . . . Nov 2006

  28. Authorization Agreement Authorization Basis (AB) S/RID EIS SER Safety Basis (SB) ORR/RA DSA (or equivalent) TSR, HAR, FHA, BIO, USQ NESS Defined Work Scope Special Terms & Conditions WSS PHA Environmental Permits Drawings (facility, tooling, etc.) Technical Manuals Engineering Calculation Notes Contractor Safety Programs Site S&S Plan Emergency Preparedness Plan Identify Prerequisites(continued) Nov 2006

  29. Planning for Failure Nov 2006

  30. Questions Nov 2006

More Related