290 likes | 459 Views
HIGHWAY/UTILITY PROGRAM OVERVIEW. ROADWAY CONFERENCE APRIL 20, 2009. PURPOSE OF UTILITY PROGRAM. Clear the R/W of direct and indirect utility conflicts: Through the most effective, efficient and economic solution possible for both the Utility & ODOT
E N D
HIGHWAY/UTILITY PROGRAMOVERVIEW ROADWAY CONFERENCE APRIL 20, 2009
PURPOSE OF UTILITY PROGRAM • Clear the R/W of direct and indirect utility conflicts: • Through the most effective, efficient and economic solution possible for both the Utility & ODOT • While preserving the operational safety, integrity, and function of the highway facility • And without delay to project development or construction
Size of Utility Relocation Program • Over 4000 utilities • Relocate 200-300 utilities/yr • 30-50 are reimbursable • ODOT costs $2-$25 million/yr • Utility costs $15-$25 million/yr
Region Utility Specialist(RUS) Role • Coordinate clearing the ROW of Utilities prior to construction, or • Make proper arrangements for relocation to occur during construction so as not to delay the contractor
State Utility Liaison(SUL) Role Soft Deliverables: • QA/QC: Ensure policy and procedures are followed through review of deliverables • Approve & Authorize reimbursable utility work & payments • Train, guide, mentor, and advise the Utility Specialist and others • Assist the Utility Specialist or take the lead on engineering solutions and negotiations with utilities
RUS & SUL Deliverables2 - Categories Projects w/Non-Reimbursable Conflict Projects w/Reimbursable conflicts
1. RUS DeliverablesNon-Reimbursable Utility Conflicts Preliminary Utility Report Conflict Letter – Non Reimbursable Timing Letter Utility Specifications Utility Certification Package for Utility work in ODOT project
Preliminary Utility Report • Provides information on type, size & location of existing utilities, potential impacts, cost and cost responsibility for relocation. • Preliminary information used for: • Scope, Schedule and Budget • Design considerations to minimize significant utility impacts • Potential ROW needs for utilities • Determination of SUL Involvement • Update the Utility database
Conflict and Timing letters • Specified by OAR 734-055 • ODOT’S Utility Accommodation Policy • Governs the location, installation, construction, relocation, maintenance and use of pole lines, buried cables, pipe lines upon State Highway right-of-way.
Conflict Letter • OAR 734-055-045 (2): “Upon receiving written notice from the Engineer to remove, relocate or repair the said facility, applicant shall within 30 days or within the time frame contained in the notice, provide to the Engineer its time estimated requirements for accomplishing the directed action.”
Timing Letter • OAR 734-055-045 (4): “The Engineer in a second notice shall direct applicant, within a specified time frame and consistent with a coordination plan, to complete the removal, relocation or repair of said facility. The time frame outlined in the notice shall take into consideration the applicant's estimated time requirements to accomplish the directed action.”
Utility Certification • Required by 23 CFR 635.309(b) • PD-02 PS&E Checklist
2. SUL DeliverablesNon-Reimbursable Utility Conflicts • Develop Utility Agreement for Utility work included in ODOT contract at the Utility’s cost (Second Moves) • Send out a Letter of Agreement to be signed by the Utility • Send the signed Letter of Agreement to HPO so that they can obtain advance deposit from Utility • Reconcile expenditures at end of project and provide docs to HPO for closing account • Create and retain file for audit purposes
SUL DeliverablesNon-Reimbursable Utility Conflictscont. • Review conflict & timing letter and specifications for clarity, completeness and consistency. • Provide guidance and leadership on communication, coordination and cooperation with internal and external stakeholders • Assist the Utility Specialist or take the lead on engineering impacts and solutions and negotiations with utilities and internal folks
RUS & SUL Deliverables2 - Categories Non-Reimbursable Projects Projects w/Reimbursable conflicts
1. RUS Deliverables:Reimbursable Utility Conflicts • Reimbursable Utilities are primarily governed by: • 23 CFR 645A: Utility Relocation and Accommodation on Federal-Aid Highway Projects • Policy applies to all state projects regardless of funding type (State, Federal, Bonds, etc.)
ODOT/Utility Agreement • 49 CFR 24.307 requires the Utility and State to reach prior agreement on the nature of the utility relocation work to be accomplished, the eligibility of the work for reimbursement, the responsibilities for financing and accomplishing the work, and the method of accumulating costs and making payment.
ODOT Utility Informal AgreementSimplified View Conflict Letter – Proposal (RUS) Reimbursement Package – Offer (Utility) Authorization to Proceed – Acceptance (SUL)
Agreement Authorizations Utility Agreements are necessary to provide authorization to: Reimburse the utility for their costs Provide for the outsource of Preliminary Engr. Contracts by Utility Allow for Advance Purchase of Materials the Outsource of Construction by Utility provide multiple authorizations for compliance to State Contract Laws
RUS Deliverables:Reimbursable Utility Conflicts • Preliminary Utility Report • Conflict Letter = ODOT Proposal • Signed Utility Offer for compensation • Utility Specifications (Section 150.50) • Utility Certification (Release Project for Ad) • Utility Property Rights Documentation • Transfer of Property Right docs • Reimbursement Certification • Utility Invoice Submittal
2. SUL Deliverables:Reimbursable Utility Conflicts • Prepare Utility Package for FHWA funding approval - Full Federal oversight projects • Development and Execution of Utility Agreements • Provide Authorization/”Notice to proceed” for: • Utility Engineering and Installation • Review and Recommend invoices to be paid Create and retain file for audit purposes
Key DeliverablesFrom Other Disciplines • Survey • Right of Way • Roadway, Traffic, Bridge/Geo/Hydro • District Maintenance
Key Deliverables • Survey • Complete and Accurate 2-dimentional base map of all existing utilities using ONE CALL • Targeted 3-dimensional surveys upon request • Survey field staking for Utility relocation purposes
Key Deliverables • Right of Way Section - Clear Utility Property Rights when required • Issue and/or determine appropriate property right to Utility
Key Deliverables • Roadway – Traffic – Bridge/Geo/Hydro • Provide specific plans for utility conflict analysis at critical points in project development schedule: 30%, 50%-70%, 90%.
Key Deliverables • District Maintenance – Utility Permits • Obtain Performance Bonds • Issue Standard Permits • Issue X-Permits
Key Deliverables • Construction Office • Enforce and obtain contractor schedule's to include the Utility schedules
Items to keep in mind • Fiber Optics –it could take a year to get the line relocated. • Identifying utility conflicts early speeds up coordination with the utilities. • Work with your utility specialist they are there to help you.
End of Presentation www.oregon.gov/ODOT/HWY/ROW/utility_resource.shtml