140 likes | 294 Views
County Emergency Management “Typing” Project. Timeline/Issues January to July 2012 FEPA Mid Year Work Session 2012. “Typing” Project Timeline. DEM Director Koon advises FEPA President Jerry Smith that Governor has directed “typing” project – January 17, 2012
E N D
County Emergency Management “Typing” Project Timeline/Issues January to July 2012 FEPA Mid Year Work Session 2012
“Typing” Project Timeline DEM Director Koon advises FEPA President Jerry Smith that Governor has directed “typing” project – January 17, 2012 DEM Director Koon announces “typing” project at FEPA Annual Meeting Closing Session – February 10, 2012 FEPA requests information from DEM on “typing” project status – March 6, 2012
“Typing” Project Timeline • DEM (Evan Rosenberg) provides status report to FEPA: - March 10, 2012 • Internal DEM Work Group – 2 members from each DEM functional area (Response, Recovery, Preparedness, Mitigation) • Internal Work Group to suggest typing variables, response due to Evan March 19, 2012 • FEPA circulates DEM status report to County EM Directors – prompts discussion to include county EM on work group – March 15, 2012
“Typing” Project Timeline • DEM/County EM Director Conference Call DEM advises “typing” work group will include one county EM Representative from each FEPA Area – April 18, 2012 • DEM Director Koon advises DEM Emergency Management Advisory Working Group of “typing” project deadline of August 1, 2012 May 17, 2012
“Typing” Project Timeline • DEM releases first set of “typing” proposed metrics to EM Work Group – June 7, 2012 • DEM Status Report to County Directors – June 8, 2012 • First EM Work Group Conference Call with DEM – June 11, 2012 • Intra-regional Conference Calls June 12-14, 2012
“Typing” Project Timeline • FEPA advises FAC/Small County Coalition of local issues/concerns with project – June 14, 2012 • DEM requests responses to first set of metrics June 13, 2012 • FEPA BOD Conference Call on EM “Typing” Project – June 15, 2012 • DEM Project Status Report to County Directors June 15, 2012
“Typing” Project Timeline • FEPA Letter to Byran Koon – June 18, 2012 • DEM releases 2nd version of “typing” project metrics – June 18, 2012 • Second EM Work Group conference call with DEM – June 18, 2012 • Palm Beach Post Article on County EM “Typing” Project posted to website June 19, 2012
“Typing” Project Timeline • DEM/County Director Conference Call – EM “Typing” Project Agenda Item – June 20, 2012 • FEPA Participates in Florida Association of Counties Annual Meeting – June 19-22, 2012 • DEM response letter to FEPA – June 22, 2012 • DEM Project Status Report to County Directors – June 22, 2012
“Typing” Project Timeline • DEM releases 3rd draft of metrics list to EM Work Group– June 23, 2012 • DEM Releases Population Data (city/county/urban rural) to Work Group June 24, 2012 • Third EM Work Group Conference Call with DEM – June 25, 2012 – extremely limited participation due to TS Debby
“Typing” Project Timeline • Area 5 Work Group Representative Resigns – June 25, 2012 • Fourth County Work Group Conference Call – July 3, 2012 • FEPA meets with FAC, SCC, FSA, FRCA representatives on “Typing” Project Concerns – July 5, 2012 • DEM Releases 4thdraft of metrics list to EM Work Group and “Potential” grouping of counties based on population – July 5, 2012
“Typing” Project Timeline • FAC and Small County Coalition Representatives Meet with Director Koon Regarding “Typing” Project Concerns – July 9, 2012 • DEM Project Status Report to EM County Directors – July 9, 2012 • FAC/SCC issue Alternate Project Proposal to DEM – July 11, 2012 • Fifth EM Work Group Conference Call –DEM Releases 5th metrics list (25 items) immediately prior to call - July 13, 2012
“Typing” Project Timeline • FAC, Small County Coalition, FEPA Representatives Meet with Director Koon Regarding “Typing” Project Concerns and Alternate Project Proposal – July 16, 2012 • Sixth EM Work Group Conference Call July 17,2012
“Typing” Project Issues • Project Purpose • Ultimate Use of Data • Timeline • County Government Authorities • “Ranking” vs. Capabilities • Metric Selection • Existing Statutory/Program Requirements • Data Collection • Data Analysis/Verification • “Normalization” of Data • County Capabilities vs. Regional Capabilities and Resources through Mutual Aid