1 / 29

I-74 Iowa-Illinois Corridor

I-74 Iowa-Illinois Corridor. Presentation to: Iowa DOT Commission May 8, 2012 Ames, Iowa Mitchell Dillavou– Director, Engineering Bureau. 1935. Original bridge opened. Cost: $1.5 million. 1960. Second bridge opened. Cost: $6.2 million. 1970’s. Iowa and Illinois took over ownership

ganya
Download Presentation

I-74 Iowa-Illinois Corridor

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. I-74 Iowa-Illinois Corridor Presentation to: Iowa DOT Commission May 8, 2012 Ames, Iowa Mitchell Dillavou– Director, Engineering Bureau

  2. 1935 Original bridge opened. Cost: $1.5 million

  3. 1960 Second bridge opened. Cost: $6.2 million

  4. 1970’s Iowa and Illinois took over ownership Toll Booths Removed. I-74 was connected.

  5. Today 2010 traffic: 61,500 vehicles per day 2035 estimated traffic: 98,500 VPD Poor geometrics for an interstate route The bridges are functionally obsolete

  6. 1998 Major Investment StudyNeeded Improvement Locations

  7. I-74 Corridor Study Milestones • 2000: I-74 Corridor Study began • 2003: Draft Environmental Impact Study completed • 2005: Preferred Alternative identified • 2006: Main Span Bridge Type chosen • 2007: Preliminary Engineering completed • 2009: Final Environmental Impact Study, and Federal Highway Admin. Record of Decision

  8. Corridor Study Limits

  9. Mississippi River Crossing Preferred Alternative

  10. Finalist Bridge Types • Scheme 1 - Basket Handle True Arch Twin Bridge • Aerial view • River view • Bettendorf shoreline view • Approach view • Motorist’s view

  11. Finalist Bridge Types • Scheme 2 - Modified Basket Handle Tied Arch Twin Bridges with Vertical Pier and Vertical Hangers • Aerial view • River view • Bettendorf shoreline view • Approach view • Motorist’s view

  12. Finalist Bridge Types • Scheme 3 - Basket Handle Tied Arch Twin Bridges with Vertical Pier and Vertical Hangers • Aerial view • River view • Bettendorf shoreline view • Approach view • Motorist’s view

  13. Finalist Bridge Types • Scheme 4 - Cable Stayed Single Bridge with Semi-Fan Stay Arrangement • Aerial view • River view • Bettendorf shoreline view • Approach view • Motorist’s view

  14. Selected Alternative: Basket Handle True Arch Twin Bridge

  15. I-74 Project Locations

  16. Central Section Cost Estimate (YOE)

  17. Central Section Design Preliminary Design • Completed in April 2009 • $9.1 Million in Consultant Services (Iowa share) • $0.3 Million Iowa DOT Staff Final Design • $9.7 Million expended to date (Iowa Share) • 71% Complete • $13.0 Million Consultant Services funds to be expended (Iowa share) • $5.5 Million Iowa DOT Staff funds to be expended

  18. Iowa ROW Summary ROW Purchased (Central & North Sections) • 47 Parcels • $6.9 Million ROW to be Purchased (Central Section) • 79 Parcels • $16.9 Million

  19. Illinois ROW Summary ROW Purchased • 7 Parcels • $0.7 Million ROW to be Purchased • 59 Parcels • $3.8 Million

  20. Iowa Investment to Date • ROW $ 6.9 Million • Design $19.5 Million • Construction $16.3 Million • Iowa DOT Staff $ 2.1 Million Total $44.8 Million

  21. Iowa Cost Estimate Phase I 2013-2017 ROW $16.9 M Construction $13.7 M Maintenance of Existing Bridges $ 2.3 M Iowa DOT Staff $ 5.5 M Consultant Engineering (design) $13.0 M $51.4 M

  22. Iowa Cost Estimate Phase II – Central Section Beyond 2017, $ in YOE Main Span $118.2 M Approach Span $123.1 M Viaducts $128.9 M Mainline Roadway $ 40.2 M Bridge Demolition $ 15.3 M Maintenance of Existing Bridges $ 3.5 M Lighting, Signing, Landscaping, ITS $ 23.5 M Consultant Engineering (Constr.) $ 40.9 M Iowa DOT Staff $ 1.0 M $494.6 M

  23. Illinois Cost Estimate Phase II – Central Section Beyond 2017, $ in YOE Main Span $118.2 M Approach Span $123.1 M Viaducts & Mainline Roadway $356.1 M Bridge Demolition $ 17.2 M Lighting, Landscaping, ITS $ 10.1 M Consultant Engineering (Constr.) $ 40.9 M $665.6 M

  24. Central Section Cost Estimate YOE IOWA ILLINOIS $494.6 M $665.6 M

  25. Iowa Cost Estimate Totals • Completed Work $ 44.8 M • Phase I $ 51.4 M • Phase II $494.6 M • Phase III (North Section) $202.5 M Total Cost $793.3 M

  26. Anticipated Maintenance Cost (Iowa Share) Option 1 – In service until 2025 • Main Bridge $ 3.0 M • Approach Bridges $ 2.8 M • Total $ 5.8 M Option 2 – In service until 2035 • Main Bridge $14.2 M • Approach Bridges $ 8.7 M • Total $22.9 M

  27. Corridor Federal Funding • Earmarks $74.6 Million • Unobligated Amount $ 7.2 Million

  28. Questions?

More Related