An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Design-Build Project Delivery The J. K. Spruce Experience Katherine Yates Assistant General Counsel

  2. Overview • J.K. Spruce #2 planned as early as 1986. • Chose Design-build methodology. • Issued Two Phase RFP. • Two Offerors Responded/Awarded July 2005. • Provisional acceptance expected no later than March 2010.

  3. Traditional Process • Chapter 252 of Local Gov. Code governed procurement activities. • Design-Bid-Build was only available method. • Bids advertised, opened and awarded publicly. • Award based on Lowest responsible bidder.

  4. New Processes • Chapter 271, Subchapter H added in 2001. • Authorized “best value” determination. • Five new methods for project delivery: • Competitive sealed proposals • Design-build • Construction manager-agency • Construction manager-at-risk • Job-order contracting

  5. Design-Build process • Single entity provides design and construction. Structure depends on various factors. • Two phase procurement process: • Phase One RFQ based on qualifications, references, past experience. • Phase Two RFP based on schedule, implementation plan, technical approach, cost. • Award to “best value” offeror.

  6. Design-Build Advantages • Fast-track schedule of construction achievable. • Single point of contact for owner and design-builder contractually accountable. • Cost savings due to close working relationship and cooperative exchange of value engineering ideas. • Less owner administrative burden due to single selection process. • Construction efficiency improved. • No need to mediate designer/constructor interface. • Ability to fix project costs earlier in the process.

  7. Potential Disadvantages • Greater project cost or schedule extensions due to owner design changes or permit or environmental conditions. • Owner-engineer oversight poorly constructed. • Labor intensive preparation of RFQ/RFP and design criteria package. • Owner loss of control over design and designer’s independent oversight on construction. • Designer selected on basis of price rather than qualifications. • Fewer entities have capacity to provide design-build services so larger entities dominate process. • Influence by non-design team member to maximize profit over design standards. • Designer has greater magnitude of liability because linked to construction.

  8. Initiation of CPS Energy Process • Board Resolution selecting “best value” process. • Engage Owner-Engineer to develop Design Criteria Package. • Functional specification and conceptual layout. • Desired equipment margins. • Quality and performance guarantees. • Transmission access. • Geotechnical and environmental information. • Engaged the services of a surety consultant • Joint development of RFQ/RFP and evaluation matrices. • Pre pre-bid meeting held with interested parties.

  9. Phase One-RFQ • RFQ advertised and sent to attendees. • Pre-bid meeting held with Site visit. • Evaluation criteria: • Ability to bond penal value of $250 million. • Financial status. • Reputation in industry. • Past experience. • Resumes of proposed project team. • References. • Two offerors qualified to proceed to Phase Two.

  10. Phase Two • Offerors given the RFP. • Agreement to reimburse losing entity of up to $1 million for preparation costs. • Evaluation criteria: • Costs • Implementation plan • Project schedule • Safety record • Workforce and training plans • Costing methodology • Initial Design drawing and schematics

  11. (con’t.) Phase Two • Interviews conducted to clarify exceptions and technical response. • Offerors asked to resubmit responses based on discussion and to provide pricing to remove exceptions. • Signed agreement “fixing” responses for evaluation. • Evaluation and recommendation of selected offeror. • Negotiations with selected offeror and award based on reaching satisfactory contract.

  12. Keys to Success • Clear and comprehensive Design Criteria package and project scope fully defined. • Effective integration of proposed Design-Build Team. • Full and consistent communication between all parties. • Project does not require extensive environmental permitting or ROW acquisition. • Designer retains authority to make design decisions and maintains direct line of communication to owner. • Multiple entities compete and adequate bonding/financing and insurance are available. • Owner involvement and capability of effectively overseeing and administering design-build system.

  13. Commercial Considerations • Testing and commissioning done by third party. • Contract price. • Payment and performance bonds. • Construction risks. • Bidding stipend. • Bonus for early completion. • Payment of prevailing wage.