Presentasjon av Ediels Change of Supplier (CoS) prosjekt. Ove Nesvik e-mail: ove.nesvik@edisys.no SFG / NEEG møte 4. februar 2002. Ediel modell. The vision of the project is to produce a model of the electricity power market to:
E N D
Presentasjon av Ediels Change of Supplier (CoS) prosjekt Ove Nesvik e-mail: ove.nesvik@edisys.no SFG / NEEG møte 4. februar 2002
Ediel modell The vision of the project is to produce a model of the electricity power market to: • Provide a basis for facilitation and harmonisation in planning, trade, settlement and other processes important for the electricity power market. • Provide a basis for a common way of exchanging information in the electricity power market. • To make the models based on international accepted standards, so that the result can be understood and used by as many as possible. • To make the deregulated electricity power market understandable for the participating parties.
CoS - Deltagere Diego García, HEW (D), Chairman Eric Roca, RTE (F) Henk Schoenmakers, Electrabel (BE) Joachim Schlegel, RWE (D) Kees Sparreboom, TenneT (NL) Lars-Erik Löf, Dalakraft (S) Leif Morland, SchlumbergerSema (N) Lisbeth Sejersen, NESA (DK) Oscar Ludwigs, SvK (S) Ove Nesvik, EdiSys (N), Secretary Roy Simensen, Lyse (N)
CoS - Status Finland PRODAT Norge PRODAT Sverige PRODAT Tyskland UTILMD Nederland UTILMD fra 1/1 2002 Belgia UTILMD fra 1/1 2003 Danmark UTILMD fra 1/1 2003 Frankrike ?
CoS Fase 1 - Resultater • En modell (dokument) som beskriver CoS prosessen i deltagerlandene • En Implementation Guide som dekker leverandørbytte iformasjon i Danmark, Tyskland og Nederland
CoS Fase II • Flytting (inn og ut) • Fakturering • ”Master data” (målepunkter, målere, parter, fakturering) • Opprettelse og avslutning av målepunkter • Konkurs • Bytte til ”leverandør av siste instans”
Old New 1: Contractual offer 4: E01 Acknowledge termination (DE) 2: Contract and Optional authorisation 3: E01 Contract termination (DE) 5: Information on contract closure (DE) 6: 392 Notification to Metering point administrator of start of supply (Change of Supplier) May include a meter reading 7: E14 Request for action regarding metered data (Validity check) (BE) 8: E11 Metered data, meter stands (Validity check) (BE) 12: Meter reading 9: 414 Confirmation of start of supply (Change of Supplier) May include master data for the 10: 406 Information or confirmation of end of supply (Change of Supplier) metering point 11: Information regarding start of supply (DE) 13: E14 Request for action regarding metered data (Validity check) (BE) Only if a meter reading is received from 14: E11 Metered data, meter stands (Validity check) (BE) the Customer and this is to be verified. 15: E11 Metered data, meter stands (Change of supplier) 16: E11 Metered data, meter stands (Change of supplier) Blue text will not be further detailed. Normally not implemented as e.messages Only for profiled settled In addition to the arrows shown: metering points - In the Netherlands and in Belgium the Metering point administrator will send an update message to the old and the new Balance responsible party - In Germany the Balance responsible party will be informed of changes inside his portefolio from his Balance suppliers Consumer Balance supplier Metering point administrator Metered data collector Balance supplier
SG. 4 O 99999 IDE M 1 LOC DTM STS TAX PTY FTX AGR INP SG. 5 SG. 6 SG. 7 O 9 O 9 O 9 O 9 O 9 O 9 O 9 O 9 O 99 O 99 O 99 RFF CCI SEQ M 1 M 1 M 1 CAV PIA SG. 8 SG. 9 O 99 O 9 O 99 O 99 QTY CCI M 1 M 1 DTM STS CAV O 9 O 9 O 99 UTILMD Transaction id. Register Metering point Grid area Meter time frame
CoS - Evaluering • Både modellen og IG‘en vil være en basis for nasjonale brukerveiledninger • Resultatet dekker flere varianter enn opprinnelig ønsket • Modellen har minere detaljeringsgrad enn UMM beskriver • CoS prosessen er mer komplisert enn andre prosesser innefor kraftbransjen • Viktig med arbeid mellom møtene