Coastal Protection and Restoration Authority (CPRA) Office of Coastal Protection and Restoration. Lands, easements, rights-of-way and relocations (LERRD’s) Up date on Flood Protection and Levee Projects. Office of Coastal Protection and Restoration.
E N D
Coastal Protection and Restoration Authority(CPRA)Office of Coastal Protection and Restoration Lands, easements, rights-of-way and relocations (LERRD’s) Up date on Flood Protection and Levee Projects
Office of Coastal Protection and Restoration • Non Federal Sponsor (CPRA) responsible for $300 million of (LERRDS) • Right of Way Conference was held on February • Representatives present: • USACOE • OCPR • SLFPA-W • SLFPA-E • DOTD • Determine Roles • Determine path forward and funding mechanisms • Standardize procedures across Levee Districts • Put together a game plan to meet schedules and budgets • Utilize Levee District Strengths • Augment with contractors
Office of Coastal Protection and Restoration UPDATE FOR SLFPA –W WEST JEFFERSON LEVEE DISTRICT AND ALGIERS LEVEE DISTRICT • Continue to grant Right of Entry (ROE)/Authorization for Entry (AFE) through Levee Districts ( 22 by the end of August) • Number of reaches: 32 • Relocation of Utilities, pipelines, highways (115)
Office of Coastal Protection and Restoration UPDATE FOR SLFPA –E PONTCHARTRAIN LEVEE DISTRICT • Continue to grant ROE/AFE through Levee Districts (granted 4 AFE’s for construction) • Number of reaches: 17 • Relocation of Utilities, pipelines, highways (25)
Office of Coastal Protection and Restoration UPDATE FOR SLFPA –E EAST JEFFERSON LEVEE DISTRICT • Continue to grant ROE/AFE through Levee Districts (granted 6 AFE’s for construction) • Number of reaches: 15 • Relocation of Utilities, pipelines, highways (39)
Office of Coastal Protection and Restoration UPDATE FOR SLFPA –E ORLEANS LEVEE DISTRICT • Continue to grant ROE/AFE through Levee Districts (granted 7 AFE’s for construction) • Number of reaches: 18 • Relocation of Utilities, pipelines, highways (56) • Property exchange with USF & WS
Office of Coastal Protection and Restoration UPDATE FOR SLFPA –E LAKE BORGNE LEVEE DISTRICT • Continue to grant ROE/AFE through Levee Districts (4 pending for construction) • Number of reaches: 7 • Relocation of Utilities, pipelines, highways (33)
Office of Coastal Protection and Restoration BIG PICTURE ISSUES • Acquisitions are on going (a lot of moving parts) • Borrow sites • Highway Crossings • Schedules • Most of this work will be done within 12 months • LERRDS for mitigation • Opportunities for Credit
Office of Coastal Protection and Restoration Questions?