THEMIS Electric Field Instrument (EFI) • Instrument Suite PER • The THEMIS EFI, IDPU and II&T Teams
Outline • Personnel and Organization • Summary of EFI Status at I-PER • Test Results To-Date (Instrument- and Suite-Level) • Summary • Vibration • TVAC • Electrical • PFR Status • Fulfillment of Mission Requirements • Tests To Be Completed at Suite Level
Personnel and Organization • Organizational Chart (all UCB unless noted): • Prof. F. Mozer (EFI Co-I). • Drs. J. Bonnell, G. Delory, A. Hull (Project Scientists) • P. Turin (Lead ME), Dr. D. Pankow (Advising ME) • B. Donakowski (EFI Lead ME, SPB, Facilities) • G. Dalton (SPB, EFI GSE ME), K. McKee (ME), S. Martin (MT) • R. Duck (AXB ME) • D. Schickele (Preamp, Sensor Cables, Facilities ME) • S. Grimmer, R. Gupta (ME GSRs) • S. Jelinsky, S. Marker (Facilities and TVAC Staff) • S. Harris (BEB Lead EE), H. Richard (BEB EE) • J. Lewis, F. Harvey (GSE) • Technical Staff (H. Bersch, Y. Irwin, H. Yuan, B. Dalen, N. Castillo, Wm. Greer (UCLA), et al.) • R. Ergun (DFB Co-I; CU-Boulder) • J. Westfall, A. Nammari, K. Stevens (DFB SysE, EEs; CU-Boulder) • C. Cully (DFB GSR; CU-Boulder)
EFI Status at I-PER • Requirements and Design: • No major changes to Requirements or Design since M-CDR (see Changes Since M-CDR and PFR Status for details). • All RFAs from previous reviews closed out. • Procurement: • All procurement is complete. • Personnel, Assembly and Test: • Team has done an amazing job. • 5 full FLT complements and 1 set of FLT Spare SPBs and AXBs will have been completed and either delivered to II&T or have completed II&T by the end of June ’05 (roughly 6 weeks per set). • BEB assembly complete in Dec ’04; bench testing through FM3 complete. • DFB assembly complete in Feb ’05; bench testing through FM3 complete. • Reduction in Force to begin May and June ’05. • Final EFI team will have one half-time Scientist (Instrument Lead), two half-time MechE (shared with Probe I&T) and one half-time ElectE (shared with Probe I&T).
Changes Since M-CDR • Final changes to Mechanical and Electrical Designs (see also PFR Status): • AXB • AXB Boom length reduced to 7.0 meters tip-to-tip based on CBE of Probe mass properties as of Nov ’04 and std. GSFC and UCB dynamic stability requirements and boom mode resonance keep-outs. • AXB Sensor length reduced from 40 to 30 inches to improve straightness and stability of deploy. • SPB • SPB Sensor (Sphere) coating changed to DAG-213 b/c of non-uniform TiN coating. • Spheres are refurbished (replaced) at end of II&T flow during final restow to ensure high-quality DAG-213 surface on-orbit. • SPB Doors held open, rather than closed upon Sphere deploy. Slight modifications to Door Retention Plungers to make actuation more robust. • DFB • Analog bandwidth on AC-coupled E-field channels on DFB increased to 8 kHz to match maximum ADC sampling rates. • AKR-band filter modified to better reject signals below 100 kHz (1-pole to N-pole). • Spin-axis (AXB) E-field gain reduced to better accomidate the possible voltage offset due to spacecraft charging. • BEB • Additional power supply filter capacitors added to reduce susceptibility to conducted noise from LVPS switching supplies in AKR band (approx. 210 kHz).
F1 Testing To-Date • Preamp • Special Thermal Qualification and Acceptance Test. • SPB and AXB • Cable Proof-Loading Test. • Fine Wire TVAC Deploy Test (SPB only). • Functional (Deploy) Test. • Vibration Test. • TVAC Test (Deploy and Functional Electrical). • Calibration (SciCal, with BEB). • Mass Properties and ICD Conformance. • BEB • Functional (Board-Level) Test. • DFB • Functional (Board-Level) Test. • EFI (Suite-Level Integrated Instrument) • DC- and AC-Functional Tests. • SPB Deploy Tests (Simulated and Actual). • AXB Deploy Tests (Simulated). • Fields Phasing and Timing Test. • DC- and AC-CMRR, Slew Rate Test. • Suite-Level CPTs (DC- and AC-Functional, pre- and post-EMC, etc.). • Suite-Level EMI/EMC Test (CE and CS only; see IDPU Presentation).
SPB Acceptance Vibration Protocol • Per UCB THEMIS Document THM-SPB-PRO-423 • All 3 Axes • Sine Survey, .25 G, 5 – 2000 Hz • Sine Strength per Swales TM2430-RevD, 29 November 2004 • Random • Per Swales Document TM2430-RevD • 7.09 G RMS • 1 min duration • All Vibration Testing Performed at Same Facility, Quanta Labs • Retesting (if required) • ‘Workmanship Shake’ • Validate any design changes following original Flight build shake • Validate rework of any failures on previous vibration test • Entire vibration protocol, single axis only Acceptance Sine Strength Specification Acceptance Random Specification 4X SPB Flight Units on Vibration Plate
SPB Acceptance Vibration Tests Run
SPB Vibration Testing Overview • Deviations from Test Specification (Notching/Force Limiting/Aborts) • None • SPB First Natural Frequency: 144 Hz (Requirement: >75 Hz) • Good Sine Sweep Consistency from Unit to Unit (within 15 Hz) • Retesting due to Hardware Failure • Backing out of bolts (2 X Bolts not torqued correctly at Flight Build) • Resolution: Bolts torqued and spot-bonded, single axis re-vibe completed • Single Strand of Cable pulled out of connector at Spool (Assy error) • Resolution: Wire repaired, single axis re-vibe completed • Retesting due to Hardware Redesign • Release Ring Spring Redesigned to Ensure Constant Force on Doors • Resolution: All springs Replaced in all units • Single Axis Retest Completed • Preamp Ferrule Crimp Redesigned (Contact discovered to be inconsistent during testing) • Resolution: Ferrule material changed and recrimped • Single Axis Retest Completed • Status • Flight Units F1-F4 Vibration Acceptance Testing Completed • F5 Scheduled for Vibration 10 May 2005
AXB Acceptance Vibration Protocol • Per UCB THEMIS Document THM-AXB-PRC-302 • All 3 Axes • Sine Survey, .25 G, 5 – 2000 Hz, 2 octaves/minute • Sine Strength per Swales TM2430-RevD, 29 November 2004 • Random per Swales Document TM2430-RevD • Qualification: 13.01 G RMS, 2 min duration • Acceptance: 9.21 G RMS, 1 min duration • All Vibration Testing Performed at Same Facility, Quanta Labs • Retesting (if required) • ‘Workmanship Shake’ • Validate any design/procedure changes following original Flight build shake • Validate rework of any failures on previous vibration test • Entire vibration protocol, single axis only
AXB Acceptance Vibration Tests Run AXB X Axis AXB Y Axis Note: Jan 11 2005 testing was to qualification levels due to design modifications relative to the engineering test unit. AXB Z Axis
AXB Vibration Testing Overview • Deviations from Test Specification (Notching/Force Limiting/Aborts) • Due to resonances in testing fixture, notching was required on the Y Axis to prevent overtesting of the booms • THM-AXB-FLT-001, 1570 Hz to 1670 Hz, input 0.0016 g2/Hz • THM-AXB-FLT-002, 1580 Hz to 1745 Hz, input 0.0016 g2/Hz • AXB Z First Natural Frequency: 300 Hz (Requirement: >75 Hz) • Good Sine Sweep Consistency from Unit to Unit (within 15 Hz) • AXB X & Y frequencies modeled fixture resonances, suggesting first natural frequency higher than 1800 Hz • Retesting due to Improper Test Procedure • Accelerometer was not located at the boom’s center of mass during vibration • Resolution: Accelerometer placed at center of mass and single axis test completed • Retesting due to Hardware Failure • Sensor door mount cracked during re-stow of boom (Assembly Error) • Resolution: Assembly replaced and single axis test completed • Status • Flight Units F1-F5 Vibration Acceptance Testing Completed • F6 (Flight Spare) Scheduled for Vibration May 2005
EFI PreAmp Thermal Testing Status • ETU 1 Preamp had no problems but FR4 board was switched to Thermount 85 NT for ETU 2 and flight • Six ETU 2 Qual Units went through 24 cycles, Two of those units added an additional 14 cycles for a total of 38 • Upper limit recently changed from 65 to 90 in September 04 due to receipt of optical testing data on DAG 213.
EFI SPB Thermal Testing Status • Qual ETU motor was a motor only stress test, no problems seen • SPB design changed from flying with doors closed to flying with doors open. ETU was retested after the small modifications this required • Calibration runs done with the sphere keyreels to determine release tension at hot and cold deployment conditions
EFI AXB Thermal Testing Status • F2 AXB will be used in Suite F1 TVAC because F1 AXB had to be delivered to swales • F1 AXB accumulated an extra 6 cycles on its own • F2 AXB will get 6 cycles with Suite F1 and 6 cycles with Suite F2
SciCal • SPB and AXB units tested in pairs using Flight BEB (Feb ’05). • Complete functionality of BEB, Preamp, and Bias System (BIAS, USHER, GUARD, etc.) tested and calibrated: • DC Bias Calibration (Sensor bias current vs. BIAS DAC setting). • DC Transfer Function: • Preamp output voltage vs. Sensor input voltage. • Floating Ground, Usher, Guard and Distal Braid output voltage vs. Sensor input voltage and DAC setting. • System noise spectrum, 1 Hz to 8 kHz. • AC Transfer Function: • Preamp, Floating Ground, Usher, Guard, and Distal Braid gain and phase vs. Sensor input (1 Hz – 16 kHz, 100-600 kHz (SPB only)). • Results agree with predictions based on individual Preamp and BEB calibrations.
BEB and DFB Functional Tests • BEB Functional Tests: • Current consumption on all services. • Voltage Gain, Voltage Offset, and Phase Shift: • Floating Ground, Bias, Usher, Guard, Braid. • All ACTEL functions: • Bias control DACs. • ACTEST signal generation. • AMUX control. • DFB Functional Tests: • Current Consumption on all Services in each mode of operation. • Voltage gain, Voltage Offset, Crosstalk, CMRR, and Phase Shift • Analog and Digital. • All ACTEL functions: • Digital Filters • FFT production • Derived Quantities calculation.
EFI Functional Tests • DC- and AC-Functional Tests: • Stowed internal DC- and AC-Functional Tests work as planned. • TM output is as predicted from Instrument-Level DC- and AC-Functional tests during boom unit Acceptance testing. • Deploy Tests: • SPB: • Deploy tests performed with Hi-Fi Simulators (Flight motors with mechanical load), simple resistive loads, and Flight SPB units. • Door actuation and pair-wise matched deploy of both pairs successful. • AXB: • Deploy tests performed with Flight FrangiBolts and simple resistive loads. • Actuation by both Primary and Secondary firing circuits successfully tested.
Noise, CMRR and Slew Rate • System Noise Tests: • System noise levels measured with Sensors in several configurations (Stowed; with Sheath Plasma Simulators; grounded). • System noise levels somewhat higher than requirement set in IN.EFI-11 (few times 10-4(mV/m)/Hz-1/2), but should not degrade quality of AC measurements in a significant fashion. • DC- and AC-Common Mode Rejection Ratio and Slew Rate Tests: • DC CMRR of DC-coupled E-field channels measured using near-full-scale inputs (+/- 85 V). • AC CMRR of E-field channels measured at 10, 100, and 1000 kHz using 15 Vpp input signal. • System Slew Rate measured at same time as AC CMRR using V channels.
Phasing and Timing Test • 12-Channel, 16-bit, 500 ksamp/s/channel DAC system used to provide identical tone burst signals to all 6 EFI, all 3 SCM, and all 3 FGM sensor inputs. • EFI signals coupled through parallel RC networks that mimic the nominal Sensor plasma sheath properties. • SCM signals coupled through 3-axis coil system in shielded mu-Metal box (mu-Metal box used for SCM calibration, integration, and test). • FGM signals coupled through 3-axis coil system in shielded mu-Metal box (TCU system used for FGM calibration, integration, and test). • TM data gathered at nominal FastSurvey, ParticleBurst and WaveBurst data rates. • Complete end-to-end test of Fields data system on THEMIS. • Reduction of data in in-process, but nominal gain vs. frequency of EFI sensors has been noted, as well as capture of overlap region between FGM and SCM coverage in frequency (approx. 10 Hz).
System Noise • EFI Spectral Coverage and System Noise Estimates Maximum Spectra (DC-Coupled) 1/f3 1/f flat CDI BBF AKR band 1-LSB Spectra (DC-Coupled) Preamp and Rbias Current Noise Preamp Voltage Noise axial radial 10-Hz Ac-coupled roll-in Spin frequency 4-kHz Anti-aliasing roll-off
F1 Testing To-Be-Completed • IDPU/BEB • DC Functional Test in IDPU/ESA TVAC. • EFI • Suite-Level LPT/CPT throughout Environmental Testing. • TVAC SPB and AXB Deploy Test (Simulated). • End-to-end calibration of AKR band response.