1. 1 Western Interconnection2006 Congestion Study
Marv Landauer - BPA
PNWER Annual Summit
Edmonton
July 18, 2006
2. 2 Western Interconnection2006 Congestion Study EPAct 05 required DOE to perform a Congestion Study
SSG-WI/WECC Study was underway
Open Stakeholder process
SSG-WI/WECC/WGA made proposal to DOE in September to perform required study
Proposal accepted by DOE
Study results delivered to DOE in May
DOE currently preparing draft report due to Congress in August
3. 3 Western Interconnection2006 Congestion Study 2008 Prod/Cost Modeling Study
Existing system with reasonably certain additions
2015 Prod/Cost Modeling Study
Resource Scenario from Utility IRPs and State RPSs
Historical Path Usage Study
1999 thru 2005
Existing studies of congestion in the West
Subregional Studies, etc
4. 4 Western Interconnection2006 Congestion Study Production/Cost Modeling
Program calculates cost of generation production needed to meet total load requirements
Full Western Transmission System
Hourly loads for full year
Wind and hydro generation is fixed
Economically dispatches remaining generation to meet load within transmission constraints
Does not recognize contracts
5. 5
6. 6
7. 7 Western Interconnection2006 Congestion Study Conclusions
WCATF identified 14 Congestion Areas in WI in 2006 Study.
6 other Congestion Areas were identified from sub-regional planning studies.
The WCATF Congestion Areas were not ranked but alternative metrics and ranking methods were explored.
DOE will rank Congestion Areas in its report to Congress in August
Studies indicated that future Congestion Areas are highly dependent upon the location of future resources.
Full Study results posted at www.wecc.biz
8. 8 Integrated Planning Concept (BPA) Objective: Achieve least-cost planning in a functionally separated industry.
Premise: Most commitments to long-term transmission service, particularly those that require expansion, are tied to utility load service.
Concept: Establish a planning cycle that links individual utility resource planning with a region-wide open season transmission planning.
Benefits:
Improve our ability to develop transmission when needed.
Regional adequacy assessment.
9. 9 Integrated Planning Concept (BPA)