1 / 22

The Hall A Compton Polarimeter

The Hall A Compton Polarimeter. Sirish Nanda Jefferson Laboratory Hall A Collaboration Meeting June 22, 2007. e -. . . e -. Compton Polarimetry. s +. E,E’. k,k’. s -. <A th > =2 %. k max =340 MeV. Figure-of-Merit ~ s x A 2 ~ k 2 x E 2.

germann
Download Presentation

The Hall A Compton Polarimeter

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Hall A Compton Polarimeter Sirish Nanda Jefferson Laboratory Hall A Collaboration Meeting June 22, 2007

  2. e-   e- Compton Polarimetry s + E,E’ k,k’ s - <Ath>=2 % kmax=340 MeV • Figure-of-Merit ~ s x A2 ~ k2 x E2

  3. The Hall A Compton Polarimeter Upgrade Motivation: Improve accuracy of polarization experiments by providing 1% beam polarimetery down to 1 GeV. High precision Parity violating experiments are feasible with this upgrade Scope: • New Electron Detector • High resolution silicon microstrips to improve tracking resolution New Photon Detector Improve systematic uncertainties experienced in the counting method While preserving counting abilities High Power Green Fabry-Perot Cavity Twice the Analyzing power of present IR cavity Four-fold increase in Figure-of-Merit Participating Institutions:Jefferson Lab, Saclay, Syracuse, Clermont-Ferrand, Uva, Duke,Carnegie-Mellon

  4. Expected Performance Simulation by David Lhuillier < 1% error @0.85 GeV obtained in about 4 hrs with 50 uA beam

  5. Electron Detector LPC Clermont-Ferrand (contact: B. Michel) • Specification • 768 ch 240 mm pitch silicon mstrips • 4 Planes, 192 strips/plane, 1 cm spacing between planes • 120 mm Vertical motion to allow coverage of Compton Edge from 0.8-11 GeV • New custom front-end, FPGA trigger module (ETROC) • New DAQ and Analysis Software

  6. Electron Detector Assembly

  7. Electron Detector Status • Detector & Electronics (Michel Brossard) • Four planes of Silicon microsrtip delivered by Canberra Systems • Front-end analog electronics completed • ETROC Trigger system in fabrication • Test scheduled for July/Aug 07 • Fifth spare microstrip ordered from Canberra • Mechanical (Francois Daudon) • Detector chamber design completed and approved • Parts in fabrication • Vertical motion controller to be done • DAQ (Alex Camsonne) • CODA readout for new ETROC • New electron event decoder • The new detector will be compatible with old DAQ and Analysis with only 48 strips active Just in case… • Support Structure and Installation (Alan Gavalya, Tim Whitlach, Chris Curtis, Ed Folts…) • Survey alignment scheme finalized • Support structure in design • Preliminary installation plan developed On track for Jan-Feb 08 installation

  8. Photon DetectorCarnegie-Mellon University (Contact: Gregg Franklin) • Calorimeter • Simulation and Conceptual design Completed • Single large crystal GSO/Single PMT • High light output, fast decay time (less than 60 ns) • Preserve triggered counting capabilities. • Small sample test at CMU this summer with loaner from the detector group • Crystal procurement negotiations with Hitachi in Progress • Integrating DAQ • Flash ADC prototype has been beam tested (R. Michaels) • Improvements needed • New ADCs in procurement • Further beam tests planned for 2007/8

  9. Green Fabry-Perot CavityJefferson Lab and Duke University (contact: SN) • Specification • Intracavity power 1.5 kW • Wavelength 532 nm • Mode CW, TEM00 • CIP Spot size () 65 m • Locking PDH • Solutions • Primary: a) Tunable “smart” single pass Green Laser -> “Passive” High Finesses cavity, • Feedback to laser PZT to lock (Botao Jia) • b) Tunable “smart” IR Laser + single pass PPLN SHG -> “Passive” High Finesse • Cavity, Feedback to laser PZT (Diana Parno) • Alternate: non-tunable “dumb” Green Laser + Electro-optic frequency modulator -> “Active” low Finesse cavity. Feedback to cavity exit mirror PZT (Could use help)

  10. Optical Setup

  11. Setup in Compton Lab

  12. Assembled Cavity Photograh: Alan Gavalya

  13. Beam Splitter Tunable Laser Cavity Oscillator PID-Regulator Photo detector Phase Shifter 0 Error signal Mixer Low Pass Filter Pound-Drever-Hall Locking Scheme Detect phase of the resonance from reflected light Feedback to tunable element to stay “locked” to resonance

  14. Locking Experience Problems: Salcay PDH Electronics: Did not work with Prometheus green laser Commercial Electronics: Required substantial modifications. Produced unstable intermittent locks of short duration Mechanical: Cavity Input mirror showed mechanical instability Picomotor mount re-design solved mechanical instability (Ravi) For locking electronics We pursued a home brew…

  15. Digital CavLock Prototypehome-brewed approach • ARM7 RISC 32-bit Processor (Analog Devices ADuc7026) • 12-bit ADCs and DACs • Fast interrupt handler • Flash memory • Feed-Back Servo • Resosnace Phase detector • PID Regulator • Fast and Slow Error Feedback to Laser 4” Host PC C++ Control Program via JTAG Port

  16. Locking with CavLock 10-sec Scope Trace • On-demand lock within seconds • Stable and reliable Lock for hours • Production version to be implemented soon (Fernado Barbosa) Transmission Reflection Fast Scan Slow Search 40-min Strip Chart 20 minutes Reflection Transmission Lock Command Fast Ramp + Error Signal Slow Ramp Unlock Command Minutes

  17. Cavity Power • We have succeeded in locking, Next is optimization of Cavity Power • So, How much power do we really need? • Must have 0.5 - 1 kWwe can be in business with this if the beam tune is clean • Should have 1 - 2 kWOur design goal for routine operation • Would like to have 2 - 3 kWgives us better operating margin when the beam tune is poor • Too Much > 3 kW Present DAQ will choke at the counting rate • Unlikely > 5 kW Limit of present optics damage threshold

  18. PPLN SHG • The Prometheus Green laser has some problems • The laser may not be able provide the injection power we need to achieve 1.5 kW we should have in the cavity • The pump diodes have short lifetime requiring frequent offsite service • We are developing our own ~ kHz linewidth tunable green laser by frequency doubling a Lightwave 1064 nm IR Laser to 532 nm (Diana) • With a PPLN:MgO crystal from HC Photonics 10-15 mW 532 nm output has been achieved with 700 mW IR input. Pursuing power amplification to several hundred milliwats with a fiber amplifier

  19. 12-GeV Compton • Scope • Reduce Chicane deflection from 30 to 22 cm to use existing dipole magnets • Raise FP cavity and Photon detector by 8 cm • Vertical motion for e-detector to cover higher energy e-detector Green FP Cavity -detector Raised Dipoles and Optics Line between 6 and 12 GeV Compton Polarimeter design and implementation effort is very fuzzy!

  20. Compton Upgrade Schedule • Electron Detector: • Installation: Jan-Feb 08 • Commissioning Mar-Apr 08 • Green FP Cavity • Installation: Apr-May 08 • Commissioning: Jun-Jul 08 • Photon Detector • Installation: Sep 08 • Commissioning: Oct 08 Production Operation: 2009

  21. Summary • Electron detector progress is consistent with Jan 08 Installation • Progress with Green FP cavity development • Robust locking has been achieved • Power optimization in progress • PPLN based backup green laser solution is in sight • Photon detector design proceeding well Project progress is limited by manpower Participation welcome!

  22. Schedule