1 / 18

Case Study: QANTAS Introduction of 737-800 Aircraft

Case Study: QANTAS Introduction of 737-800 Aircraft. 2002. Background. Domestic Competition September 11th - WTC Attacks Industry Turmoil Contingency Plans Activated September 14th - ANSETT Collapse Complete Reversal of Plans Tactical Capacity response

ghita
Download Presentation

Case Study: QANTAS Introduction of 737-800 Aircraft

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Case Study: QANTAS Introduction of 737-800 Aircraft 2002

  2. Background • Domestic Competition • September 11th - WTC Attacks • Industry Turmoil • Contingency Plans Activated • September 14th - ANSETT Collapse • Complete Reversal of Plans • Tactical Capacity response • Domestic capacity required - quickly!

  3. The Challenge • Complete all work necessary to introduce a new aircraft type, from scratch, including significant interior and structural modification, in ninety days! • Not only that, but we actually want to be able to use it! • Do this in the most challenging aviation environment ever seen! • Oh…and don’t forget Christmas.

  4. Project Timelines • Commence Planning 22 October 01 • Budget Preparation 22 October 01 • Aircraft Selection 29 October 01 • Specification Frozen 15 November 01 • Production Commenced 16 November 01 • First Rollout 3 December 02 • First Delivery 15 January 02 • Entry into Service 4 February 02

  5. Project Structure

  6. Scope - E & M Readiness • Project Management • Administration • Financial Management • Delivery Support • Specification Support • Pre-service • Airworthiness • Air Operators Certificate (CASA) • Certificate of Airworthiness *

  7. Scope - E & M Readiness • Engineering • Maintenance Program* • Maintenance Requirements/Documentation • Procurement • Spares • Tools and Equipment • Maintenance Training * • Managed Operational Handover

  8. Project - Key Elements • Project Plan • Reporting Structures • Allocating Responsibility • Milestone tracking • Finance Plan • Risk Management Plan • Communication Plan • Resource Plan

  9. Project • Defined Management Structure • Overhead kept to a minimum • Let the Manager Manage • Escalation • Immediate • Rare • Tracking • Milestones defined • Focus on critical path

  10. Project • Financial • Competent managers • Freedom to Act • Formal Reporting • Team Meeting • Managers Meeting • E&M Steering Committee • Project Steering Committee

  11. Risk Management • Brainstormed early at all levels • Assessed • Likelihood, Influence, Impact • Allocated • Clear accountability • Reported • Weekly

  12. Communication • Formal Reporting Structure • Published Widely • Single Points of Contact • Clearly Defined responsibility • Accountable • Cross Functional • Peer Communication • Escalation rarely required • Advertise

  13. Resources • Subject Matter Experts • Hand Picked - Skilled but inexperienced • Responsibility, Authority, Accountability • Freedom to Act (and supported) • Focussed • Outcomes not process • Management Support • Seconded and released as required

  14. Success Measures • Aircraft Delivery • On Schedule • Pre-service Modification • 3 days late (scope and learning curve) • Recovered on later copies • Entry Into Service • 4 days late (crew training) • Operational Handover • Reliability meets/exceeds world benchmarks

  15. Lessons Learned • Outcomes over method • People over process • Communicate • Scope Containment • Responsibility, Authority, Accountability • Recognise and Advertise • Do not use email as a medium to resolve issues

  16. As a Project Manager • Keep the Overhead Small • Process, Reporting, Documentation • No Surprises • Be aware of the breadth. Stay in touch. • Focus on what will hurt you • BUT watch the rest • Manage - it’s your Job • Let your people do the work

  17. As a Project Manager • Leverage everything you can find • A330 Delivery Project • Client 737-800 • Key resources • Take Risks to Solve Problems • Communicate them (particularly up) • Encourage your people , but remain aware • Build your network, and use it! • Get on the phone, Meet people

  18. Thank you. Questions?

More Related