1 / 5

Proposal to adjust investment lead times

Proposal to adjust investment lead times. Transmission Workstream 4 th May 2006. Release of incremental capacity. UNC B2.2.3 (c) (i) obliges National Grid to release incremental capacity at each ASEP to the level of either 150% of NTS SO baseline;

gil-cohen
Download Presentation

Proposal to adjust investment lead times

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proposal to adjust investment lead times Transmission Workstream 4th May 2006

  2. Release of incremental capacity • UNC B2.2.3 (c) (i) obliges National Grid to release incremental capacity at each ASEP to the level of either • 150% of NTS SO baseline; • or an amount determined by the application of the IECR • The IECR allows National Grid to • Extend the investment lead time governing the release of incremental entry capacity • Undertake a 14 day consultation on the proposals • Submit the consultation report and proposals to the Authority • This is only undertaken in the event that we are unable to physically provide up to 150% of NTS SO baseline at the ASEP with a 3 year lead time

  3. Incremental Capacity release 150% of NTS SO Baseline available from October 2010

  4. Requirement for adjusting investment lead time • Milford Haven • Any incremental capacity in excess of 25% of NTS SO baseline will require a duplicate pipeline which will take 4 years to deliver • Obtaining consent under the Environmental Impact Assessment • Planning permission • Easements from landowners • Easington, Bacton and St Fergus • Any incremental capacity in excess of the % shown in the previous table will require a greenfield compressor • From auction gate closure to commercial availability of a greenfield compressor is approximately 44 months • Completion of a public enquiry • Approval of HV electric power supply • Parallel working • There may be a requirement for an additional consultation if new ASEPs wish to take part in the September QSEC auction.

  5. Consultation process • Consultation issued on 28th April • Representations to • To be received by 17:00 on 12th May 2006 Dave Adlam NG House Warwick Technology Park Gallows Hill Warwick CV34 6DA Email: dave.adlam@uk.ngrid.com

More Related