1 / 5

ISTP (and other…) Update

NSTX-U. Supported by. ISTP (and other…) Update. Stefan Gerhardt. Coll of Wm & Mary Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Lehigh U Nova Photonics ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD

gilden
Download Presentation

ISTP (and other…) Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NSTX-U Supported by ISTP (and other…) Update Stefan Gerhardt Coll of Wm & Mary Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Lehigh U Nova Photonics ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD U Colorado U Illinois U Maryland U Rochester U Tennessee U Tulsa U Washington U Wisconsin X Science LLC Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Inst for Nucl Res, Kiev Ioffe Inst TRINITI Chonbuk Natl U NFRI KAIST POSTECH Seoul Natl U ASIPP CIEMAT FOM Inst DIFFER ENEA, Frascati CEA, Cadarache IPP, Jülich IPP, Garching ASCR, Czech Rep NSTX-U Monday Physics Meeting Feb. 20, 2015 B318

  2. CD-4 Requirements • 50 kA plasma • Penultimate activity is ISTP-001, “NSTX-U Coil Energization Tests” • Then go to XMP-100 • 40 kV beam into the armor • Handled via startup and conditioning beam procedures

  3. Solid Progress Being Made on Both Fronts • ISTP-001 • Started last Thursday • Have run all coils at 10% and 50% of their CD-4 limits • Have run most coils at 100% of their CD-4 limits • Includes 65 kA TF. • Demonstrated I^2t, overcurrent, overtime trips of various types. • Using these shots to correct many many magnetics issues. • Final commissioning of the gas delivery/injection system is maybe the final hurdle at this point. • Significant progress made over the weekend, but still at least a few full shifts of work • NB #2 source B is now HV conditioning towards to 40 kV beam target. • Some setbacks on 2A and 2C.

  4. What about after CD-4?That is, after BOTH the Plasma and NBI milestones are met. Apr. 2015 May 2015 June 2015 July 2015 • Commit resources to completing key MPTS tasks before the bakeout…target 1 week. • Spend most of May on the bakeout. • ISTP, MPTS R&R, commissioning in later May and June. • Research ops in July and onward. • Many background engineering tasks during this time. • More dummy load testing. • Gas injection systems • Control system work Bakeout ISTP Commissioning Research Plasma Operation CD4 MPTS R&R pre-bake-out MPTS

  5. You may ask… Apr. 2015 May 2015 June 2015 July 2015 • What about access to the NTC? • Very restricted access during bakeout • Very restricted access during MPTS R&R, or other times when the laser is firing. • 2nd shift access during this and the next ISTP. • Weekend access. • Sporadic first shift access…coordinate with Al is your best bet. • Opportunities arise if you are ready to take advantage of them • Maintenance weeks • What does it take to get work done? • Most tasks can be done on a D-Site work permit. • Many tasks can be done under the “reinstall what was taken off” work package. • Only major new work requires a “blue folder”. • Plan your work a few days in advance ( and ASAP)…it can take a few days to get work permits approved. • Don McBride can help with the permits and procedures (but note he works Mon-Wed). Bakeout ISTP Commissioning Research Plasma Operation CD4 MPTS R&R pre-bake-out MPTS

More Related