An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gauteng Department of Health Presentation to the NCOP on Conditional Grants 11 May 2007

  2. Overview • Budget Trends • Pre-audited expenditure • Capital and maintenance • Monitoring • 2007/08 Budget and MTEF

  3. Conditional Grants • National Tertiary Services Grant (NTSG) • Health Professions Training and Development Grant (HPTDG) • Revitalisation Grant (Capital) • Provincial Infrastructure Grant (Capital) • HIV and AIDS Grant • Forensic Pathology Services Grant (FPS)

  4. Budget Trends The allocation for the NTSG and HPTDG has not kept up with CPIX or medical inflation.

  5. Pre-audited expenditure at year closure 06/07

  6. Conditional Grants Graph

  7. 2006/07 Expenditure • All conditional grants have been spent in full except for • Forensic Pathology Services which has under spent by R8,8 million • Replacement of cold rooms and body cabinets at institutions. equipment not delivered • Vehicles ordered in 06/07 but not delivered by the end of 31 March 2007. • Salary costs for the 1st quarter were paid by SAPS, claim of R3m was received but lower than anticipated • 70% of posts filled by August due to delay in recruitment processes. • Delay in the approval of facility projects by National Public Works, DAC gave standing delegations to enable procurement processes to take place without waiting for National. • Emergency repairs on mortuaries done to the value of R4,6m, department received a claim of R164k.

  8. 2006/07 Expenditure • Revitalisation – R63,8 million • During the 06/07 financial year it was reported that there will be an over expenditure on this grant • Projects were scaled down significantly to avoid over expenditure, in some projects Public works negotiated with contractors to stop work where possible without incurring penalties • Although additional funding was received in the 2006/07 Adjustments budget in January 07, it was difficult to bring on track those projects where contractors were stopped this resulted in the under expenditure specifically the revitalisation grant • Applied to Treasury for a roll over of funds.

  9. Capital and Maintenance Expenditure

  10. Capital and Maintenance Expenditure • The under-expenditure on buildings relates to the unspent revitalisation and forensic pathology grants • The under-expenditure on equipment is due to commitments incurred during 06/07 but deliveries and payment were not done before year closure as well as less equipment purchased than was budgeted for.

  11. Monitoring • Financial • Monitoring is done monthly by analysing reports and verifying information • Between Health and Works • Within Health between Branches and Directorates • Between Health and Treasury • Between Gauteng Health and the National Department of Health • Compliance with reporting requirements • Monitoring has been strengthened in 2006/7. • Executive Support Programme Manager dealing specifically with capital expenditure was appointed • Project managers have been appointed and they work closely with the Department of Public Works to monitor projects • Financial Manager within the ESPM branch has been appointed to manage and monitor project spending

  12. 2007/08 and MTEF Budget

  13. 2007/08 and MTEF Budget

  14. Challenges • Lack of adequate funding for all capital Infrastructure projects • Lack of due diligence in project implementation and management by project teams characterised by poor delivery, extensions and cost escalations of projects • Insufficient funding for medical equipment and declining budgets in real terms

  15. Certified Business Plans 07/08

  16. Thank you