1 / 12

Eskom’s Electrification Programme

Eskom’s Electrification Programme. Energy Portfolio Committee 14 th June 2011. Background/Introduction. National Electrification Fund Allocation Principles. National Electrification Fund Process for Allocation of Funding to Provinces. Medium Term expenditure Framework Allocation.

gmerrill
Download Presentation

Eskom’s Electrification Programme

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Eskom’s Electrification Programme Energy Portfolio Committee 14th June 2011

  2. Background/Introduction

  3. National Electrification Fund AllocationPrinciples

  4. National Electrification Fund Processfor Allocation of Funding to Provinces

  5. Medium Term expenditure Framework Allocation

  6. . Electrification – There have been two distinct eras of installation: pre-2000 and post-2000 Number of annual grid connections Thousand Cost per connection R '000 13.4 12.4 12.4 11.8 9.0 8.7 8.7 8.6 8.1 7.0 6.3 6.1 5.9 6.0 5.2 5.0 4.5 4.1 2011 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 • Self-funded and managed programme • Eskom exceeded the government's target of 1.75M connections between 1994 and 2000 • Connection every 30 seconds, pole every 10 seconds, 200M cable every minute • Connection costs steadily came down • Government funded programme • The numbers of annual connections by Eskom have dropped, partly due to • Increased investment in infrastructure • The stringent processes that need to be followed Total investment from 1991 – 2011 to date: R7.5 bn

  7. Close to 400 clinics electrified since 1991 More than 11 000 schools electrified since 1991 Electrification – schools and clinics The improvement of local infrastructure through strong impact projects is a key corporate social investment priority for Eskom

  8. … whereof 70% in proclaimed areas 2.9 million households with no access … Electrification – Still significant backlog of 2.5 to 2.9 million households (Eskom’s area of supply) Number of households without access to electricity1 Millions, 2011 Breakdown of households without access to electricity by area1 %, 2011Total: 2.5–2.9M 2.9 0.9 Unproclaimed areas Proclaimed areas 2.0 1. The figure is based on an assumed increase in households without access at a rate of between 2–5% per annum, from 2.3M in 2006. It is also in Eskom’s areas of supply.The certainty in these figures is low and checks will have to be done in the pre-engineering phase Source: Eskom

  9. PROVINCIAL DATA - BBBEE EMPOWERMENT

  10. Municipality Assistance - Infrastructure Offerings

  11. Municipality Assistance - Infrastructure Offerings

  12. THANK YOU !!!

More Related