Environmental Controls I/IG

Environmental Controls I/IG. Lecture 8 Waste & Vent Systems Waste & Vent Sizing Procedure Bathroom Design. Waste & Vent Systems. Fundamentals. Siphon action can drain water Trap blocks sewer gas Vent breaks siphon. S: p. 988, F.22.8. Air Gaps.

goro
Download Presentation

Environmental Controls I/IG

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Environmental Controls I/IG Lecture 8 Waste & Vent Systems Waste & Vent Sizing Procedure Bathroom Design

  2. Waste & Vent Systems

  3. Fundamentals Siphon action can drain water Trap blocks sewer gas Vent breaks siphon S: p. 988, F.22.8

  4. Air Gaps Eliminate the potential for cross contamination S: p. 991, F.22.11

  5. Vents and Stacks Note: Drain fittings are 45º Individual vents Circuit vents Soil stack Vent stack Stack vent “Wet stack” Vent through roof (VTR) S: p. 990, F.22.10

  6. Drains & Sewers Note: Drain fittings are 45º House drain House sewer Storm drain Clean outs House traps Fresh air inlet S: p. 989, F.22.9

  7. Waste & Vent Sizing Procedure

  8. 1. Identify waste & soil locations Clusters are more efficient S: p. 995, F.22.17

  9. 2. Layout system vertically & horizontally Grouped fixtures can be stacked in a vertical riser S: p. 1009, F.22.31

  10. 3. Size Traps Trap size is used when connecting to main S: p. 998, T.22.2

  11. 4. Calculate Drainage Fixture Units (DFU) Pipe sizes based on DFU S: p. 998, T.22.2

  12. 5. Determine loads Fixture location may control size S: p. 1003, F.22.24

  13. 6. Determine slope and size of horizontal drains Slope may be constrained by depth of floor cavity S: p. 1001, T.22.5

  14. 7. Verify maximum vent length Measured from plans S: p. 1003, F.22.24

  15. 8. Size vents according to DFU and length Calculate for each vent load and developed length S: p. 1000, T.22.4

  16. 9. Verify space requirements and adjust design Common adjustments • “Wet” walls  6” cavity • Slope and ceiling exposure • Cleanout access

  17. Bathroom Design

  18. Design Considerations ADA compliance • ANSI Standard A117.1 1986 • Wheel chair access • Grab bars • Counter top/fixture heights Visual privacy Acoustical privacy