Trial for Unbundled Local Loop. Phase 1 - Co-location Trials Physical Co-location Distant Co-location Phase 2 - End User Technical Trials Manual provision of Metallic Pair Facilities Phase 3 - Automation Trials Initially low volumes with Operator end-customers. Phase 1 - Co-location Trial.
E N D
Trial for Unbundled Local Loop • Phase 1 - Co-location Trials • Physical Co-location • Distant Co-location • Phase 2 - End User Technical Trials • Manual provision of Metallic Pair Facilities • Phase 3 - Automation Trials • Initially low volumes with Operator end-customers
Phase 1 - Co-location Trial BT Exchange OLO room OLO room Distant co-lo Distant co-lo BT exchange 4 OLOs sharing a room OLO room 7 co-locations Distant co-lo Distant co-lo Distant co-lo Distant co-lo BT exchange BT Exchange OLO room OLO room BT Exchange 4 co-locations 4 co-locations - 3 Field Force Areas (FFA) - 1 Physical Co-location per FFA - 2 Distant Co-locations per FFA - At Least 1 Dedicated OLO Room per FFA - 12 OLOs Maximum - 15 Co-locations Maximum
Phase 1 - Sites • Choice of 3 from 6 Field Force Areas • Battersea • Tunbridge Wells • Colchester • Coventry • Exeter • Edinburgh
Phase 2 - End User Technical Trial • Entry to Phase 2 from Phase 1 Operators • 10 to 20 loops per co-location (300 loops max) • Maximum manual provision rate ~ 5 lines per day • BT to test spectrum management compliance • No take-over, no number portability • Provision of loops will be by manual procedures - not to standard lead times • Maintenance not to normal standards
Phase 3 - Automation Trial (1) • Entry to Phase 3 from Phase 2 Operators • From 17/4/2001 onwards, testing of the automatic OSS interface between Operators and BT • Initially 1, then 2, to a max of 3 operators per week • All triallists connected to gateway by 25 May 2001 • Migration of Phase 2 loops onto OSS
Phase 3 - Automation Trial (2) • Bedding down period in June 2001, no further operators connected before 1 July 2001 • Triallists can increase orders - up to 150 per Operator • 2100 loops maximum by end of Phase 3 Trial • Take-over and number portability available for test • Loops continue to be provided and maintained on trial terms & conditions until formal launch
Timeline Summary Co-location Phase A 1 April 2000 31 Dec 2000 End-user technical trials Phase B 1 Dec 2000 12 April 2001 Automation Trial Phase C 17 April 2001 30 June 2000
Critical System Constraints • COSMOSS modifications for tracking co-location build, tie cables and backhaul - available July 2000 • CSS and other systems for pair provision & maintenance - available end March 2001 • Gateway to Operators and OSS , available for start of phase 3 trial -17 April 2001
Next Steps • Which Operators Involved in the Trial ? • Establish OPF Trial Team ? • Which Sites to be Used in the Trial ? • Orders for Co-location 1/04/2000