Indira Awaas Yojana. Performance Review Committee 7 th June, 2013. Salient features of IAY Guidelines. Unit assistance for construction of new house & housesite component enhanced (Cabinet decision - 10 th Dec, 2012)
E N D
IndiraAwaasYojana Performance Review Committee 7th June, 2013
Salient features of IAY Guidelines • Unit assistance for construction of new house & housesite component enhanced(Cabinet decision - 10th Dec, 2012) • An Empowered Committee - oversee operationalisation of new guideline • Special projects from Reserve fund to be sanctioned by EC (5% of Annual budget for scheme retained by MoRD) • Administrative expenses – 4% of funds released • Greater role for State in • Allocation of district wise targets • Distributing admin cost to districts • Identifying Difficult Areas • Habitation & Individual house approach for better coverage of target group • IT enabled Monitoring through AwaasSoft
Allocation • Annual allocation for States/UTs based on existing formula ( 75% weight to houselessness & 25% weight to Poverty ratio) rationalised to achieve fair category wise distribution • Targets for SCs, STs and Minorities made in proportion to population of these categories in States/UT’s • Upto 20% of district allocation can be used for upgradation • Once SECC is finalised allocation would be based on houseless people from BPL population for each category
Administrative Cost • District allocation to include two parts, • Fixed expenditure which would be same for all districts • Working expenses in proportion to the targets allotted • Formula for distribution to intermediate & Village Panchayats in accordance to workload assigned Distributed to districts in proportion to their targets in 2013-14. Eligible items of expenditure • IEC material on designs & technology options • Construction of prototypes & models for demonstration • Cost of hardware/software for MIS, data entry, photographs, quality supervision & monitoring • Training of master masons, CRPs & NGOs, Elected representatives • Honorarium to CRPs & service charges to NGOs etc.
Convergence…with other schemes With Nirmal Bharat Abhiyanfor construction of Sanitary toilet in IAY houses • IAY beneficiaries to be accorded priority • State/District Water and Sanitation Mission would be agency in charge • State Dept. in charge of MGNREGS to issue directions to GP’s on dovetailing MGNREGS funds with NBA funds • IAY Implementing agency to send progress reports to MoDW&S • Last installment of IAY & NBA funds to be released only after construction of toilet is completed • Letter on implementation jointly issued - uploaded on website State/ Implementing Agency should promote convergence with other schemes like RGGVY, RSBY,AABY etc. * Letter dated 16/5/2013
Use of AwaasSoft • Uploading Annual selection list before release of 1st installment • Registration of complete beneficiary details • Financial & Physical progress as reflected in AwaasSoft would be considered for all purposes • All transaction have to be done through AwaasSoft • Use of AwaasSoft reports for monitoring • Regular uploading of photos every quarter • Follow up till completion
Progress of MIS 2012-13 Training requirements?
Physical Performance 2012-13 (In thousand units)
Financial Performance 2012-13 (In lakhsof Rupees)
Common Issues • All releases will be linked to AwaasSoft entries • Compliance of conditions imposed during release of 2nd installment, 2012-13 to enable releases in 2013-14 • Special audit of special packages sanctioned • Bank details of DRDAs – CPSMS registration mandatory • Action Taken Report on complaints and NLMs report • DRDA’s to submit information as per check list • Performance Audit – CAG 2007-08 to 2012-13 - States should provide necessary information & support
Arunachal Pradesh 2013-14 Istinstalment – District wise targets awaited 2012-13 – 2nd installment • Proposal not received - Dibang valley, Lower Dibang valley and Papumpare • Released during 2013-14 - East Siang, East Kumang and West Siang • Request for 780 houses for the families of freed bonded labour belonging to Suiling tribe in East Kameng district – needs to be sent to EC
Special Packages 5% IAY Border Package
Assam 2013-14 1stinstalment - under examination 2nd installment 2012-13 • Sanctions for Sonitpur, Golaghat, Darang, Kamrup (M) & KarbiAnglong issued • Bongaigaon is under examination • Kamrup (Rural) – proposal not received Special Package • Proposal for 2nd installment under FRA - 2011-12 awaited • Proposal for 2nd installment under 5% from Kamrup (M) and Nalbari awaited • Request for 68,832 additional houses for beneficiaries under FRA & people affected by erosion need to be brought to the EC for approval
Manipur 2013-14 1stinstalment - under examination 2012-13 – 2nd installment • Proposals not received from Chandel, Bishnupur and Thoubal Special Package – Settlement of accounts 5% IAY – 2009-10 to Senapati district – UC, AR & Completion Certificate awaited Borderdistricts – 2009-10 Chandel - UC, AR & Completion Certificate awaited Senapati - 2nd installment not availed Request for 1263 houses as additional target for the families of insurgency affected in Thanlon T.D block of Churachandpur district – needs to be sent to EC
Meghalaya 2013-14 Istinstalment – sanctions issued to 5 districts 2012-13 - 2ndinstalment • South Garo hills – proposal not received • East Khasi Hills - under objection
Mizoram 2013-14 Istinstalment – sanctions issued to all districts
Nagaland 2013-14 Ist installment – submitted to IFD Special Package - Settlement of accounts • 5% IAY – 2007-08 to Peren district • 5% IAY - 2008-09 to Mokokchung district Both have not availed 2nd installment
Sikkim • 2013-14 Istinstalment – revised district wise targets awaited • 2012-13 – 2nd installment – Not availed by all districts
Tripura 2013-14 Istinstalment – revised district wise allocation awaited 2012-13 – 2nd installment • North Tripura - under objection Special Package • Border package - 2010-11 to North Tripura district – 2nd installment not availed • Incentive package - 2010-11 to all 4 districts • UC, AR & Completion Certificate awaited • Incentive package- 2011-12 to all 4 districts • Dhalai district has to submit UC,AR & Completion Certificate • Other districts have to submit proposals for 2ndinstalment