MTA beam line installation Weekly Report September 07, 2007 Period covered: August 31 st to September 7 th (Week 5). MTA – Week3. MTA Weekly Report – Week 5. Shielding underneath hatch area is complete Restacking complete on 09/04 Finalizing some safety requirements:
E N D
MTA beam line installation Weekly ReportSeptember 07, 2007Period covered:August 31st to September 7th (Week 5) Shutdown’07 Week 5 F.G. Garcia MTA – Week3
MTA Weekly Report – Week 5 • Shielding underneath hatch area is complete • Restacking complete on 09/04 • Finalizing some safety requirements: • Added cover plates to aid S&S • Retrofit cover plate over the utility penetration • Re-used the slug of concrete to plug in the beam pipe penetration • Electrical Work • Cable pull ongoing • Load cables estimate to finish by Monday • Immediately start pulling instrumentation cables Next week: Continue with cable pull. • Mechanical Installation • All magnets have been stationed in place • Next step will be alignment! • Moving along with MW stands (45% complete). Shutdown’07 Week 5 F.G. Garcia
MTA Weekly Report – Week 5 • Alignment • Outside corner of the concrete blocks were shot by surveyors Next week: Rough alignment starts Monday, Sep 10th • LCW work • Copper pipe installation complete (Linac side) • Brazing/installing taps Next week: Contractors will be moving to the MTA side • Vacuum work • Making as much progress as possible with the assortment of the spool pieces and flanges • Ion pumps stands are complete • Beam pipe support stands are complete Shutdown’07 Week 5 F.G. Garcia