Working Together to Improve the Decision Making Process. 2013 Region Construction Conference. Overview. Improving project decision making and relationships between contractors, consultants and DOT on construction projects is WisDOT priority New evaluation process
E N D
Working Together to Improve the Decision Making Process 2013 Region Construction Conference
Overview • Improving project decision making and relationships between contractors, consultants and DOT on construction projects is WisDOT priority • New evaluation process • Construction Materials Support Center conducts survey January 2013
Contractor Evaluation of Project Team • Project Team Evaluation of Contractor • Project Communication Enhancement Effort (PCEE)
Contractor Evaluation of Project Team • Revamped evaluation form to obtain specific information • Positive, objective feedback • Valued results
Project Team Evaluation of Contractor • Address past inconsistencies in responses • Industry needs candid feedback • This constructive feedback can be used to improve project staff and crews
Project Communication Enhancement Effort (PCEE) • 2006 – began discussion. Resulted in developing select tools to enhance communication and working relationships • Tools developed, not mandatory and not fully embraced • Spring board for 2013 survey to review tools and to obtain information on overall project level decision-making
Timely Decision Making Survey 489 Responses
Timely Decision Making Survey • Timely decision making is a problem that needs to be addressed
Satisfaction with timeliness of decisions Timely Decision Making Survey
Relationships that could/should be improved to facilitate timely decisions Timely Decision Making Survey
Types of decisions that are the most problematic: • Processing of contract modifications • Ability to have decisions reviewed by others of higher authority • Non conformance of materials issues • Field changed conditions • Non performance of QMP issues
Communication tools identified by survey for improvement effort: NEW • Rolling 3-Week Look-Ahead Schedule • Designated materials contact person • Line of communication/decision timeline form • Progress meeting with standardized note format and responsible parties identified • Request For Information (RFI) process • Preconstruction meeting with standardized agenda NEW
Next Steps • Workgroup to fully review survey results and recommend solutions for implementation this construction season • Discussion at all Regional Construction Conferences this spring • Resurvey 2014 to ensure progress