350 likes | 361 Views
This 3-story cast-in-place concrete structure in Laredo, TX, houses science labs, classrooms, offices, and features a planetarium and the Dean's Office Tower.
E N D
The New Science BuildingTexas A&M International UniversityLaredo, TX Nicole Griffith
The New Science Building • 3 Story Cast-in-Place Concrete Structure • 80,000 S.F. • Estimated Cost of $18 Million • Houses Science Labs, Classrooms, Offices • Features a Planetarium and the Dean’s Office Tower
The New Science Building • Owner: Texas A&M University System • General Contractor: Constructors & Associates, Inc. • San Antonio, TX • Construction Began June 2003 • Main Building Completed December 2004 • Planetarium Complete May 2005 by Owner
Thesis Overview • 4D Modeling • Structural and Construction Feasibility Review of the Planetarium Concrete
CM Depth 4D Modeling
Reasons for Using 4D Modeling • Complicated Schedule Setup Makes Sequencing and Level of Detail Difficult to Maintain • Unique Structure of the Planetarium Can Make Visualizing the Construction Process Difficult • 4D Modeling is a Key Technology Vitally Important to the Construction Industry
4D Modeling • Create 3D Model of the Structure Using Autodesk Revit 7.0 • Export into AutoCAD 2004 format • Export into Common Point 4D • Link to Structure Schedule
4D Modeling • Revit is a Parametric Modeling Tool • Model using Building Components • Unique Structures, Such as the Planetarium, can be Difficult to Represent • Must be Exported into AutoCAD First in Order to Export into Common Point • Looses Detail, Difficult to Control Layers
Results • Multiple Sequencing and Level of Detail Errors Discovered in the Structure Schedule • Using a 4D Model Could Have Eliminated Problems that Resulted Due to Confusion from the Construction Schedule
CM Depth/Structural Breadth Structural and Construction Feasibility Review of the Planetarium Concrete Structure
Planetarium Concrete • Architectural Concrete Structural Base • As-Cast Smooth Finish • No Further Finishing After Formwork Removal • Plastic-Laminated Plywood Formwork • Result was Unacceptable to the Owner • Variations in Color • Inconsistent Texture • Surface Imperfections (Lift Lines, Air Pockets) • Visible Formwork Joints
Planetarium Concrete • Investigate Both the Project Specifications as well as Standard ACI Specifications • Look for Inconsistencies, Areas for Concern • Review and Suggest Alternate Formwork • Review and Suggest Alternate Concrete Mix Design/Specifications • Review and Suggest Alternate Concrete Placement Methods
Standard Specifications • Perform Slump Tests on Trial Batches at Highest & Lowest Expected Ambient Temperatures • Not Specified or Performed for Project • Poured in mid-July Creates Cause for Concern
Project Specifications • No Fly Ash • No Form Ties • Mock-Ups & Pre-Installation Meetings • Not Implemented Due to Time Constraints • Small Samples Submitted Instead • Well-Sealed Formwork Joints • Not Properly Constructed
Formwork • Conventional Forms • Most Economical for This Type of Project • Simple, but Proper Construction is Important • Non-Reactive Form Release and Other Agents • Smooth Finish is Not Optimal for Appearance Elevates Visibility of Surface Defects
Resulting Recommendations • Use Plywood Formwork with a Textured Plastic Liner • Use a Non-Reactive Form Release Agent That Will Not Affect the Appearance of the Concrete Finish
Resulting Recommendations • Consider the Use of Fly Ash in the Design of the Architectural Concrete • Fly Ash Contains Properties That May Help Resolve the Problems Encountered • Be Sure That Any Additives, Such as Water Reducing Agents and Curing Compounds, Will Not Alter the Finished Appearance of the Concrete
Resulting Recommendations • Maintain Similar Temperatures for Concrete, Rebar, Formwork, and Any Other Affected Materials at all Times When Concrete is Being Poured to Eliminate Color and Texture Variations and Lift Lines
Resulting Recommendations • Provide a Large-Mass Mockup of the Architectural Concrete Using Same Materials and Methods of Placement to Ensure the Quality of the Final Product • Be Sure to Pour the Concrete for the Mockup at the Same Temperature as is Expected for the Actual Pour
Resulting Recommendations • Coordinate all Interested Parties, Particularly the Concrete Contractor and Steel Erector, Before the Production of Shop Drawings, to Ensure That All Parties Are Aware of Others’ Requirements for Construction so that Delays and Additional Costs Can be Avoided
Conclusions • Use a 4D Model to Eliminate Problems That May Result Due to Confusion from the Construction Schedule, Sequencing, and Level of Detail Errors • Reconsider the Concrete Mix Design, Formwork Type, and Placement Requirements of the Planetarium Architectural Concrete in Order to Achieve the Desired Finish
Acoustical Breadth Planetarium Acoustical Analysis
Acoustical Analysis • Owner’s Representative Had Concerns Regarding the Acoustical Quality of the Planetarium • The Planetarium Space Itself • The Effect of Mechanical Room Noise Adjacent to the Planetarium Space
Reverberation Time • Performed on Planetarium Space • Results Were Acceptable – 0.95 s @ 500 Hz • Acoustical Quality Was Much Poorer During Construction
STC Calculation • Performed for the Mechanical Room Walls • Result Was STC Rating of 42 – Acceptable • Well-Constructed Insulated Walls