80 likes | 323 Views
Project Cuckoo Monthly Review: November 2002. Dan Booth Jared Hay Pat Keller. Overview. Milestones Accomplishments Plans Issues. Milestones. Accomplishments. Project Plan Approved VCO - Researched Designs - Contacted Supplier Phase Detector - B 2 Logic Complete - Simulation Verified.
E N D
Project Cuckoo Monthly Review:November 2002 Dan Booth Jared Hay Pat Keller University of Portland School of Engineering
Overview • Milestones • Accomplishments • Plans • Issues University of Portland School of Engineering
Milestones University of Portland School of Engineering
Accomplishments • Project Plan Approved • VCO- Researched Designs- Contacted Supplier • Phase Detector- B2Logic Complete- Simulation Verified University of Portland School of Engineering
Accomplishments (cont.) • Divide by N- B2Logic Complete- Simulation Verified • Loop Filter- Schematic Complete • FTB - Found The Book University of Portland School of Engineering
Plans • Finalize VCO choice • Design Release- Verify Design- Advisor and Industry Rep. Approval • Start and complete .tpr file University of Portland School of Engineering
Issues • Understanding how the VCO will work with OUR project- Input or Output of VCO may have to be adjusted to comply with the functional specifications University of Portland School of Engineering
Conclusion • Recap • Questions University of Portland School of Engineering