1 / 20

Diesel Fuel Price Adjustment Special Provision

Diesel Fuel Price Adjustment Special Provision. Summary of New Revisions. Categories. Special Provisions prior to 2/10: Category A - Earthwork Category B - Subbase and Aggregate Base Courses Category C - Flexible Bases, Pavements, & Shoulders

griffith
Download Presentation

Diesel Fuel Price Adjustment Special Provision

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Diesel Fuel Price Adjustment Special Provision Summary of New Revisions

  2. Categories • Special Provisions prior to 2/10: • Category A - Earthwork • Category B - Subbase and Aggregate Base Courses • Category C - Flexible Bases, Pavements, & Shoulders • Category D - Rigid Bases, Pavements, & Shoulders • Category E - Structures

  3. Categories • New Revisions: • Category A split into: • Small Excavation - 50,000 to 1,000,000 CY • Large Excavation - > 1,000,000 CY • Flexible Base Replacement (316), Stone Matrix Asphalt (419), & Manual Bituminous Patching (450) added to Category C • Concrete Pavement Patching (516) added to Category D

  4. Categories • New Revisions: • ATPB (360) & CTPB (303) moved from Categories C & D (respectively) to Category B • Milling (491 & 492) added as new Category F • *Notes added to Categories B, C, & D to: • Exclude ineligible work items • Explain how adjustment will be computed when work is measured & paid for under varying units of measure (e.g. on a “Material Used Basis” or on an “Area Basis”).

  5. Categories • Excluded Work Items: • Presplit Blasting items associated with Section 203 (Category A) • Cleaning Existing Ditches item associated with Section 204 (Category A) • Shoulder Backfill items associated with Sections 654 & 656 (Category C) • Patching Joint, New Pavement Joint, & Subbase Material for Concrete Pavement Patching items associated with Section 516 (Category D)

  6. Categories • Items Paid on Material Used Basis: • “Coarse Aggregate” and “Bituminous Material” items associated with Cold-Recycled Base Course (Sections 341 & 342) • “Coarse Aggregate for . . .” and “Bituminous Material for . . .” items associated with FB-1 Wearing & Binder, Seal Coats, & Surface Treatments (Sections 439, 440, 470, 471, 480, & 481) • Adjustment will be computed based on the “Coarse Aggregate” / “Coarse Aggregate for . . .” item quantity only.

  7. Categories • Items Paid on an Area Basis Where Depth is Not Indicated in Item Description: • Seal Coats and Surface Treatments (Sections 470, 471, 480, & 481) • A depth equal to the maximum allowable size of the type of aggregate used, as specified in Section 703.2, Table C, will be assumed.

  8. Fuel Usage Factors • Category A • Small Excavation: 0.34 gal/CY • Large Excavation: 0.25 gal/CY • Category B • Increased from 0.62 to 0.71 gal/Ton • Category C • Reduced from 2.98 to 2.00 gal/Ton

  9. Fuel Usage Factors • Category D • Increased from 0.98 to 1.77 gal/CY • Category E • Reduced from 8.00 to 4.00 gal/$1000 of work performed • Category F • Established at 1.15 gal/CY

  10. Conversion Factors • Category B (CY -> Tons) • New CF established at 3,240 lbs./CY • Category C (SY -> Tons) • Reduced from 120 to 110 lbs / inch of depth / SY • Category F (SY -> CY) • Established 2 inches as average depth for variable depth milling (Sect. 491). • Established 1 inch as average depth for profile milling (Sect. 492).

  11. Category E Structures • Consider all work identified on S-drawing / BPAA-drawing • Lump sum item (8xxx-xxxx) with one or more associated items; or • Rehab work tabbed as one or more separate contract items • Exclude: • Fabricated Structural Steel • Prestressed Concrete Bridge Beams • Bearings & Bearing Pads • Design-related work

  12. Category E Structures • Include: • Items on S-drawing or BPAA-drawing tabbed as “Roadway Items”; and • Removal, Painting & Containment, and Causeways (whether or not tabbed on S-drawing or BPAA-drawing). • Value of all applicable Structure work for the project must exceed $1,000,000.

  13. Category E - Example 1 • A project includes the following contract items:

  14. Category E - Example 1 • Item 8600-0007 has the following Component Item Schedule:

  15. Category E - Example 1 • The value of all Structure work for the project is computed as follows: • Retaining Wall (LS) $2,769,000.00 • Fabricated Structural Steel ($ 872,467.20) • Painting Existing Structural Steel $ 100,000.00 • Containment $ 35,000.00 • Total Value $2,031,532.80 • The Total Value of all Structure work exceeds $1,000,000 • Payments made under the above items, excluding the Fab Steel component item, are subject to price adjustment under Category E.

  16. Payment / Rebate • Price Adjustments to be computed on a quarterly basis. • Initial adjustment quarter to begin as of the month/year when the first item of applicable work is performed. • New adjustment quarters to begin every 3 months thereafter. • Quarterly price adjustments amounting to less than $1,000 will be disregarded.

  17. Payment / Rebate • Example: • Consider a project that includes items for Class 1 Excavation, Milling, and Superpave HMA Wearing Course. • If Class 1 Excavation operation is the first of these items to be initiated and work begins in August 2012: • Initial Adjustment Quarter: August thru October 2012 • New Adjustment Quarters would begin in November 2012, February 2013, May 2013, etc.

  18. Implementation • Revised specification has been approved by FHWA and is to be included in all projects let after February 25, 2010. • A revised Excel spreadsheet has been provided by BoCM.

  19. Thank You

  20. Questions

More Related