1 / 28

Ola 230 / 115 kV Project

Ola 230 / 115 kV Project. 2010 ITS-1. North Americus Series Reactors. 2010 ITS-2a. North Americus Series Reactors. 2010 ITS-2b. McDonough 4 & 5 Network Improvement. 2010 ITS-3. McDonough 4 & 5 Network Improvement

gsteger
Download Presentation

Ola 230 / 115 kV Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Ola 230 / 115 kV Project 2010 ITS-1

  2. North Americus Series Reactors 2010 ITS-2a

  3. North Americus Series Reactors 2010 ITS-2b

  4. McDonough 4 & 5 Network Improvement 2010 ITS-3 McDonough 4 & 5 Network Improvement Construct the Jack McDonough – Smyrna 230 kV line via Cumberland (convert from 115 kV) and Galleria (new) substations. Add a 5 element, 230 kV ring bus at Smyrna and replace the 300 MVA 230 / 115 kV transformer with two 400 MVA transformers. The loss of the Jack McDonough – Peachtree 230 kV T.L. will cause overloading of the facilities surrounding McDonough.

  5. Pegamore 230 kV Project 2010 ITS-4

  6. Thomson 500 / 230 kV Project 2010 ITS-5 Construct 35 miles.

  7. Union Point – Warrenton 115 kV T.L. 2010 ITS-6

  8. Install a 0.5% series reactor on the low side of the 500 / 230 kV transformer. Fig. 1 One-line diagram of the Klondike 500 / 230 kV Substation. Klondike 230 Reactor Project 2010 ITS-7

  9. Plt. Jack McDonough Problem: Loss of the Groover Lake segment of the Douglasville – Greenbriar 115kV line overloads the East Point – Gordon Rd. Jct. as early as 2011. 230kV to Mableton, Jack Mac-West Mar.115 to Jack Mac.-West Mar. 115 Factory Shoals Groover Lake Douglasville Fact Shls Jct Hightower. Jct Gord Rd. Jct Gordon Rd. 115kV Thornton Road Adamsville • Solution: • Breaker up Buzzard Roost 230kV • Add 230kV line Thornton Rd. to Factory Shoals. • Add 230/115 autobank and 115 breakers at Factory Shoals. Greenbriar Buzzard Roost Boat Rock Bakers Ferry Post Road 230kV East Point Factory Shoals 2011 ITS-8

  10. Arkwright – Gordon #1 115 kV T.L. 2011 ITS-9

  11. East Social 230 kV Series Reactor 2013 ITS-10

  12. East Carrollton 230 / 115 kV Substation 2014 ITS-11

  13. Goshen – Waynesboro 115 kV T.L. 2014 ITS-12

  14. Hatch – Offerman 230 kV T.L. 2014 ITS-13

  15. Bethabara 230 / 115 kV Project 2014 ITS-14

  16. East Walton 500 / 230 kV Project 2015 ITS-15

  17. Thomson Primary – Vogtle 500 kV T.L. 2016 ITS-16

  18. South Metro Phase III Project 2017 ITS-17

  19. Dorchester 230 kV Project 2017 ITS-18

  20. ITS-19 Install a 500 / 230 kV transformer at Middle Fork and loop in the South Hall – Oconee 500 kV T.L. Replace the existing 300 MVA 230 / 115 kV transformer with a 400 MVA transformer. ITS-20 Build a new 500 kV Middle Fork – Thomson 500 kV T.L. (approximately 110 miles long) Middle Fork 500 / 230 kV Project 2017 ITS-19 2017 ITS-20 Middle Fork – Thomson 500 kV T.L.

  21. Hopewell – McGrau Ford 2nd 230 kV 2017 ITS-21

  22. O’Hara 500 /230 kV Transformer #2 2017 ITS-22

  23. South Hall – Suwanee 230 kV T.L. 2017 ITS-23

  24. East Walton – South Hall 500 kV T.L. 2018 ITS-24

  25. Sharon Springs – Suwanee 230 kV T.L. 2018 ITS-25

  26. South Coweta – Yates 115 kV T.L. 2018 ITS-26

  27. Blankets Creek – Holly Springs 115 kV 2019 ITS-27

  28. Commerce Primary – Middle Fork 115 kV 2019 ITS-28

More Related