450 likes | 486 Views
Overview of Legal Issues in Regulatory Reforms : Bangladesh Power Sector November 11-15, 2002 Hyderabad, India Country Paper Presented by : Bangladesh Team. Outline. Introduction Country Profile Power Sector at a glance Current structure of power sector Current status of regulation
E N D
Overview of Legal Issues in Regulatory Reforms : Bangladesh Power Sector November 11-15, 2002 Hyderabad, India Country Paper Presented by : Bangladesh Team
Outline • Introduction • Country Profile • Power Sector at a glance • Current structure of power sector • Current status of regulation • Regulatory reform measures undertaken : An overview • Future reform programmes • Establishment of Energy Regulatory Commission & its salient features
Introduction • Electricity essential ingredient for economic and social development • Power the most important pre-requisite for attracting both domestic and foreign investment • GOB committed to providing with affordable and reliable electricity to all the citizens by 2020 • Scarcity of resources as well as the inefficiency of the utilities hinders development of the sector
Country Profile • The Country : The People’s Republic of Bangladesh • Capital City : Dhaka • Area : 147,570 Square km. • Population : 130 Million • Per Capita income : 315 US$ • GDP Growth Rate : 5.16%
Power Sector at a glance • Installed Capacity Total : 4,710 MW BPDB : 3,420 MW IPP & Mixed Sector : 1,290 MW • Generation Capacity : 3,750 MW • Peak Demand : 3,218 MW • Transmission Lines (230 & 132 Kv) : 3,764 KM • Grid Sub-station Capacity (230/132 Kv) : 3,250 MVA • Grid Sub-station Capacity (132/33 Kv) : 6,585 MVA • Distribution Lines (33 Kv, 11 KV & 0.4 Kv) : 1,93,196 KM • System Loss (T&D) : 29.60% • Consumer Number : 6.54 Million • Access to Electricity : 30% • Per Capita Generation : 136 kWh
Current Structure of Power Sector Owner & Regulator : • Government (Power Division) Generation : • Bangladesh Power Development Board (BPDB) • Independent Power Producers (IPPs) • Rural Power Company Ltd. (RPC) - A mixed sector power company
Current Structure of Power Sector (contd.) Transmission : • BPDB • Power Grid Company of Bangladesh Ltd. (PGCB) Distribution : • BPDB • Dhaka Electricity Supply Authority (DESA) • Dhaka Electric Supply Company Ltd. (DESCO) • Rural Electrification Board (REB) through Rural Electric Co-operatives called Palli Bidyut Samity (PBS)
Power Sector of Bangladesh MPEMR (Ministry of Power, Energy and Mineral Resources) Power Cell BPDB (Generation) EA & CEI IPP PBSs PGCB (An enterprise of BPDB) BPDB (Transmission) REB DESA DESCO BPDB (Distribution) Administrative Link Power Flow Link
Current Status of Regulation Regulatory Functions : • Power Division on behalf of Govt. functions as a Regulator • Formulates policies • Approves investment program of the public sector entities • Approves Tariff • Resolves disputes • Electrical Advisor & Chief Electric Inspector’s office and Power Cell perform some regulatory functions in electricity sector on behalf of Govt.
Current Status of Regulation (contd.) Performance Based : • No effective performance based regulation • Have some kind of incentive regulation for the consumers mainly through tariff and tariff structure for load management perspective • Penalty to consumers for low Power Factor
Current Status of Regulation (contd.) Tariff : • Government approves tariff • Tariff is not cost reflective • Two-part metering tariff - peak & off-peak • No provision for stakeholders participation like public hearing in the tariff approval process • No scope of appeal to the Court against Govt. decision • Provision of subsidy to domestic and agriculture consumers
Involvement of Judiciary in Power Sector Regulation • Provision of punishment under The Electricity Act, 1910 • Theft of electricity • Malicious use of electricity • Damages of electrical equipment, line materials, etc. • Recovery of bills - • Public Demand Recovery Act, 1913
Overview of legal framework : An example Electricity Act 1910 ( amendment `93) Electricity Act 1910 Section • Provision of penalty for users including officer / employee of the utilities • Imprisonment for a term of maximum 5 years or fine maximum Tk 10,000 or both penalties No provision of penalty for abettors 44 A Penalty for abettors in certain offences
Regulatory Reform Measures Undertaken : An Overview • Power Sector Reform started in 1977 through the creation of Rural Electrification Board (REB) to expedite and strengthen rural electrification program • DESA created in 1991 as a part of distribution unbundling process to supply electricity in Dhaka metropolis
Regulatory Reform Measures Undertaken : An Overview (Contd.) • To introduce competition, induct foreign private capital and increase power supply “Private Sector Power Generation Policy” developed and adopted in 1996 • 1290 MW IPP power plants contracted & it is under operation • GOB has approved “Policy Guidelines for Small Power Plants in Private Sector” to develop power plant up to 10 MW capacity. • Already a 10 MW Power Plant established and some are in progress under this policy
Regulatory Reform Measures Undertaken : An Overview (Contd.) • As a part of unbundling process - • PGCB created in 1996 to take over transmission business from BPDB. It already taken over about 63% of the transmission assets from BPDB • DESCO established in 1996. It is currently functioning at Mirpur area of Dhaka Metropolis • Corporatization of Ashuganj Power Station implemented • Cabinet approved constitution of the “West Zone Power Distribution Company” under BPDB on September 2002
Example : Power Purchase Provision from IPPs BPDB • No provision of power purchase from IPP in Presidential Order (P.O. 59 of 1972) P.O. amended in April 2001 as follows : • The Power Board may purchase power from any person or entity authorised to generate electricity by the appropriate authority at such rate as may be determined by the Government
Example : Power Purchase Provision from IPPs (contd.) REB • REB Ordinance (LI of 1977) : Shall receive supply of electricity from BPDB at such rates and on such terms and conditions as may be determined by the Government • REB Ordinance amended in April 2001 as follows : Shall receive supply of electricity from BPDB and any power generating station run by any person or entity under a contract with the Government at such rates and on such terms and conditions as may be determined by the Government
Example : Power Purchase Provision from IPPs (contd.) DESA • No provision in DESA Act (Act 36 of 1990) • DESA Act amended in April 2001 as follows : DESA may purchase power from any person or entity authorized to generate electricity by the appropriate authority at such rate as may be determined by Government
Future Reform Programs Generation • Bangladesh Power Development Board (BPDB) be converted into a holding company under Companies Act • The existing generating stations of BPDB be converted into a number of corporatized entities under BPDB holding company
Future Reform Programs (contd.) Transmission • PGCB remains responsible for transmission business in the whole of Bangladesh
Future Reform Programs (contd.) Distribution • BPDB distribution segment be converted into a number of subsidiary companies under BPDB Holding Company • DESA be converted into a company under Companies Act, 1994 • Palli Bidyut Samities will continue its business in their distribution areas under Rural Electrification Board
Power Market after Reform • Single Buyer Model be adopted • Single Buyer purchases all the power/energy from the generators and sells to different distribution companies. • Multi-buyer and Competitive Pool may be adopted when the market becomes mature and stable
Future Reform Programs Independent Regulation • An independent Energy Regulatory Commission (ERC) be established for regulating electricity, gas and petroleum sector
What’s the Intent of Future Regulatory Reforms • Govt. wears too many hats i.e. owns, operates & regulates • Intent is shifting of Govt. regulation towards Independent regulation Ownership Govt. Control Market Control Regulation
Legal Issues • A legal framework is required for establishment of ERC • Initially a draft legislation was prepared for establishing an ERC for regulating Electricity Sector • Cabinet approved the draft • February 2002, Govt. decided to establish a single ERC for regulating Electricity, Gas & Petroleum sector • With this aim, draft act prepared & expected to be enacted soon by the Parliament
Nature & Extent of the Proposed Regulation • Independent Regulation • High level body vested with adequate powers to discharge responsibilities which embrace • Executive functions - within the broad Govt. policy relating to the sector • Issue licences • Set Tariff • Set & enforce of standards of performance • Promote Competition • Advisory functions - Advise Govt. on all matters connected with energy • Quasi judicial functions - Dispute resolution
Nature & Extent of the Proposed Regulation (contd.) • Extent of regulation is a quantum of regulation for the sector • What type regulation required • Soft hand or • Hard hand • Our intent -- Medium hand regulation
Why Independent Regulation • Power Sector Reforms already started & it’s a continuous process • Private power generation started (about 1290 MW which is one third of present installed capacity) • Separation of commercial business from network business is under way and private participation be encouraged in commercial business • By the year 2006 and 2012 generation capacity to be enhanced by 6,789 MW & 9,564 MW respectively for which (including T&D network development) investment needs about 3.68 b US$ & 6.70 b US$
Why Independent Regulation (contd.) • Not possible to fulfill this huge amount of investment by Govt. alone • Private sector participation is essential • To increase confidence of private sector investors • Independent Regulation essential in the sector to take corrective action in a timely manner & to ensure level playing field for both public & private sectors
Establishment of ERC delayed? • Yes, delayed • Preparation started in 1996 • To give legal framework Power Cell Working on it • Establishment of Independent ERC is delayed due to : • Suspicion • Lengthy bureaucratic process • Sometimes Donors’ pressure • Lack of political commitment
Salient Feature of the Energy Regulatory Commission Act, 2002 Constitution of the Commission Chairman - 1 Members - 4 • Appointed for 4 years and may be extended for another term subject to satisfactory performance
Salient Feature of the Energy Regulatory Commission Act, 2002 (contd.) Appointment of the Chairman & Members • Appoint by the Govt.
Salient Feature of the Energy Regulatory Commission Act, 2002 (contd.) Removal of Chairman & Members • For removal of the Chairman or Members of the Commission, a Committee will be constituted by the Govt. comprising a Judge of the Supreme Court
Salient Feature of the Energy Regulatory Commission Act, 2002 (contd.) Funding • All the expenses of the Commission will be met from the annual budget of the Govt. • Fees, charges etc. • Surplus money be deposited to the consolidated fund of the state
Salient Feature of the Energy Regulatory Commission Act, 2002 (contd.) Powers of the Government • Govt. will issue policy directives for overall development of the power sector
Salient Feature of the Energy Regulatory Commission Act, 2002 (contd.) Resolution of disputes between the Commission & Govt. • If any conflict of interest arises between the Commission and Government, Government’s decision is final
Salient Feature of the Energy Regulatory Commission Act, 2002 (contd.) Tariff • Commission will approve the Tariff on the basis of the policy directives issued by the Govt. • Public hearing will be made during tariff setting
Salient Feature of the Energy Regulatory Commission Act, 2002 (contd.) Appeal against the decision of the Commission • Orders of the Commission are appealable before the High Court.
Salient Feature of the Energy Regulatory Commission Act, 2002 (contd.) Rules • Govt. may make rules by Gazette notification
Salient Feature of the Energy Regulatory Commission Act, 2002 (contd.) Regulations • Commission may make regulations by Gazette notification
Salient Feature of the Energy Regulatory Commission Act, 2002 (contd.) Proceedings of the Commission • All the proceedings before the Commission shall be deemed to be a judicial proceeding within the meaning of sections 193, 219 and 228 of the Penal Code (XLV of 1860) and the Commission shall be deemed to be a Civil Court
Thank You C:/P\LF\2002\Amzad\Regulatory Reforms -- India (Hydrabad)-3.ppt