CHARM Update J. Mekki
CHARM Update • Goal of the facility: • Complexmixed particlefieldpresentwithin the accelerators • Simultaneouseffect (TID, DD, SEE) • In the framework of the R2E project the testing of electronicequipment in a radiation fieldsimilar to CERN acceleratorsis crucial → Assure mid-long termoperationrequirements • Facility not onlyuseful for CERN accelerators but also for : • Groundlevel and atmosphericenvironment(neutron energyspectra) • Spaceenvironment(representative for the inner proton radiation belt) • Size of the test area (severaltens of m3): • Large objectscanbeirradiated • Evenobjects in operationwith services connected (power, cooling…) • Can also host satelittes, part of cars or planes.
East Area Facilities 24 GeV/c proton beam
East Area Facilities 24 GeV/c proton beam IRRAD proton facility PH/DT 24 GeV/c proton beam LHC experiments
East Area Facilities 24 GeV/c proton beam CHARM R2E Project
East Area Facilities 24 GeV/c proton beam Technical local Connection to the radiation area
East Area Facilities 24 GeV/c proton beam Control room Dry run test
East Area Facilities 24 GeV/c proton beam Platform for the Dry Run test of heavy equipment e. g. UPS, Power converters
CHARM 24 GeV/c proton beam
Montrac conveyer • Implementation • Hypertack • 6 NE48 (RadTOL)
News • Schedule: • We are on the way → around 2 monthsbeforegetting first beam → Everypieces/blocks/systems of CHARM are building/mountingeachday. • Commissioningshouldstart in August. • OperationshouldstartduringSeptember up to the 8th of December. • In order to prepare the CHARM operationschedule, the beam time requestform has been sent to the RadWGlist and externalusers. • For the moment someusers (alsoexternal) showedinterest of suchfacility (e. g. BNL, LHC experiments etc…) • FromRadWG, I have not yetreceivedanyfilledform. • Anycommentsregarding the beam time requestform ? • Information: • The new websiteisavailableherehttp://charm.web.cern.ch/CHARM/ • You canalsofind information about the availablecables on-site. http://charm.web.cern.ch/CHARM/Cables.php
Varying Radiation Field Beam Positiontarget in:HEH: >1011cm-2h-1TID: >100 Gyh-1 target out:HEH: >1013cm-2h-1TID: >10 kGyh-1 Beam Pos. Longitudinal Lateral Positions HEH: 108cm-2h-1 – 1011cm-2h-1TID: 0.1Gyh-1 – 100Gyh-1 (gradients to be considered) Full racks, crates, set of cards, componentsHEH: 107cm-2h-1 – 1010cm-2h-1, TID: 10mGyh-1 – 10Gyh-1