Guifré Cuní on behalf of the XALOC team BL13 — XALOC
ALBA warehouse offices Tech. building
Status of XALOC at September 2010 • Optics almost all completed • End-station under installation • Commissioning with beam just after installing undulator
XALOC optics layout XBPMs Ring Monochromator Vert. Foc. Mirror (VFM) Hor. Foc. Mirror (HFM)
Procurement End-Station in-house commercial mixed Beam condit. el’s Status: Designing Diffractometer Status: To be integrated Diffractometer table Status: Motor tests Sample changer Status: To be commiss. Detector table Status: Design finished Detector Status: Awarded
End-Station: diffractometer • MD2M First mini-diffractometer out of ESRF Full metrology done Received and tested To be integrated into the BL control Viewing system • on-axis • software available XYZ movable beamstop • In-house design Not included in the contract Mini-kappa • Removable • sphere of confusion ~5m Omega axis • air bearing • run-out 1 m, accuracy < 1 mdeg
End Station: Automatic sample changer Flexible 6-axis arm automatically exchangeable gripper
Controls • CATS with Custom I/O signals • 3 regions: Free, 1, 2 • SW allow MOVE/PIN/PLATE • Cryostream: • 3 positions IN, OUT, FAR • Motion: SW / Icepap • Security: PLC • Omega: ETEL/Icepap's slave + metrology • Monitoring + batch for operating CATS