270 likes | 283 Views
Los Angeles County's Green Street Task Force, comprising various departments, aims to identify optimal locations for constructing green streets to address stormwater quality. With a screening process and feasibility studies, the project seeks to prioritize and select top sites for implementation, focusing on sustainability and efficiency. Lessons learned and funding from measures passed enrich the Safe Clean Water Program, integrating stormwater and transportation efforts for a greener, safer community.
E N D
LA County’s Green Street Task Force: Stormwater & Transportation working together TJ Moon County of Los Angeles Department of Public Works
Los Angeles County Stormwater Quality Nutrients Trash 33 TMDLs l Metals Bacteria Leads Nation Toxics
Stormwater Quality Solutions Regional Projects Green Streets Low Impact Development
Green Street Task Force Participants • Stormwater Quality • Road Maintenance • Transportation Planning • Traffic & Lighting • Geotechnical • Parks and Recreation Objectives • Collaboration • Sustainability • Efficiency
Stormwater Green Street Master Plan Question: • Where are the most optimal locations to construct Green Streets to address stormwater quality? Master Plan Goal: • Create Prioritization Process • Identify top 100+ half-mile road segments 5336 Total Miles
Screening Process Overview County Roads Phase 1 Screening Phase 2 Screening Phase 3 Screening Phase 4 Feasibility Field Recon Steep Slope Geotechnical Modeling Utilities Contamination Groundwater Table Final Site Selection Environmental Geotechnical
Phase 1 Screening Phase 1 Screening Steep Slope Slope > 5% Contamination 60 feet buffer from contamination sites 40% Remain 60% Out 5,336 Total Miles
Phase 2 Screening Phase 2 Screening Phase 2 Phase 1 Geotechnical • Landslides • Bedrock • Liquefaction • Seismic • Surface Soils Groundwater Table • GW depth Varies • Usually more than 10+ feet • Not Considered 40% Remain 60% Out 36% Remain 64% Out
Phase 3 Screening Phase 3 Screening Phase 2 Modeling • Impervious drainage area drives water quality need 36% Remain 64% Out
Phase 3 Screening Tributary Area Step 1: Identify catch basins and open channels
Phase 3 Screening Tributary Area Step 2: Cluster catch basins to create downstream node
Phase 3 Screening Tributary Area Step 3: Digital Elevation Model + Flow Direction
Phase 3 Screening Tributary Area Step 4: Drainage Area Delineation
Phase 3 Screening Impervious Area Step 5: Impervious Score
Phase 3 Screening Storm Drain Step 6: Qualitative Selection • Major storm drain • Large Parkway Space • Maximize Drainage Area
Phase 3 Screening Phase 2 Phase 3 Screening Phase 3 Modeling • Impervious drainage area drives water quality need Final Site Selection • Top 110 Sites Selected • 55 Miles 36% Remain 64% Out 99% Out
Phase 4 Feasibility Phase 4 Feasibility Field Recon Utilities • IPad entry • GPS • Photos • Automatic reporting • Existing Substructure Map • Recording of Dig Alert for Geotech Field Recon Utilities Environmental Geotech Phase 1 Assessment • 3 CPTs per Site • 330 Total CPTS • 80’ Deep Environmental Geotechnical
Phase 4 Feasibility - Geotechnical • 110 Potential Sites • 3 Cone Penetration Tests per Site • 80 Feet Deep • Full Understanding of Soils • Soils will dictate the BMP Type Sand Clay
10 Feet Deep Phase 4 Feasibility - Geotechnical Sand Clay • How do we maximize infiltration? • Take advantage of sandy soils • Depth may be deeper • Adjust BMP for sandy soil 75 Feet Deep 60 Feet Deep 50 Feet Deep 30 Feet Deep 40 Feet Deep 20 Feet Deep
Lessons Learned • Lesson Learned #1 • Not enough space to capture sufficient stormwater • Solution • Go deeper – Infiltration Wells • Regional Green Streets
Lessons Learned Existing Storm Drain Dry Wells • Solution • Green Alley Master Plan • Lesson Learned #2 • Alleys are a great location
Measure W Tax Measure passed on November 2018 Estimated Revenue: $300 M SAFE CLEAN WATER PROGRAM
Stormwater & Transportation Coming Together
Stormwater & Transportation Coming Together • Project Planning can include: • Road Rehabilitation • Safety (Vision Zero) • Connectivity Corridors • Stormwater Capture • Native Landscaping • Heat Island Effect • Multiple Funding Sources!
Safety: Vision Zero Street East Rancho Dominguez Street Improvement Project Stormwater Capture Feature Compton Blvd Road Improvement Limits Road Improvement Limits E. Rancho Dominguez Park Atlantic Ave E. Rancho Dominguez Library • Connect Library + Parks • Enhance Safety Ex. Storm Drain
Contact Information Paul Alva palva@dpw.lacounty.gov (626) 458-4325 TJ Moon tmoon@dpw.lacounty.gov (626) 458-4380