30 Years of Live Working in Romania. Economical Benefits of Live Working (case study)

30 Years of Live Working in Romania. Economical Benefits of Live Working (case study). Marius Oltean- SC Smart SA- Romania Ioan Sevastre- SC Smart SA- Romania Ioan Rodean -CN Transelectrica SA- Romania Valentin Zaharescu- CN Transelectrica SA- Romania. Content.

Download Presentation

30 Years of Live Working in Romania. Economical Benefits of Live Working (case study)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 30 Years of Live Working in Romania.Economical Benefits of Live Working (case study) Marius Oltean- SC Smart SA- Romania Ioan Sevastre- SC Smart SA- Romania Ioan Rodean -CN Transelectrica SA- Romania Valentin Zaharescu- CN Transelectrica SA- Romania

  2. Content 1. Introduction. A Brief Overview of LW History 2. The Beginning 3. Further Activity 4. The Present Time 5. LW Persectives in România 6. Technical and Economical Benefits of LW (case study) CITTES 2011

  3. Some history…. The first country in the world that tried to work live was USA -1913. Canada -1929. Former USSR -1940. Sweden -1949. France- 1958 GDR- 1969 3/29 CITTES 2011

  4. The Begining In 1975 the interest for a new technology was revealed in Romania. As consequence in 1978 a contract between Romania and DDR, for LW implementation was signed. 4/9 CITTES 2011

  5. 1979 -the training of a work team from IRE Sibiu in the German Democratic Republicat Berlin-Neuenhagen . The second training took place in Sibiubetween 18-28.09.1979, under the surveillance of german instructors. 5/29 CITTES 2011

  6. The first five 400kV technologies: The replacement of suspension strings; The working at the phase conductors; The preparation for dyeing of the supporting pilons; The painting of the metallic supporting pilons The removing of the unwanted objects from the pilons. 6/9 CITTES 2011

  7. 7/9 CITTES 2011

  8. the first live work performed in Romania, 25.09.1979,on the pilon 198 of 400kV Sibiu –Tantareni OHL. suspension insulator replacement and technical revision of the conductors, using an insulated lather and a mobile charriot. 8/9 CITTES 2011

  9. 9/9 CITTES 2011

  10. 1979 the first technical regulation for Live Working on 110-400kV, PE141/79, 10/9 CITTES 2011

  11. Further Activity 1982 – 1985: the training courses for five teams at Sibiu. 1983: manufacturing of 5 Live Working suites. 1987: manufacturing of the tool set for live maintenance of 750KV overhead lines 1982- 1994: 58 live maintenance technologies for 110-400kV overhead lines were elaborated and tested. 1996: manufacturing of the first tool-set for MV Live maintenance 11/9 CITTES 2011

  12. 2001: together with the outsourcing of the maintenance activities of TRANSELECTRICA National Company, live maintenance = SMART S.A . 12/29 CITTES 2011

  13. 2002: the Live Working National Committee 23.07.2003: Romanian National Live Working Association (A-LST-R). www.lst.ro Every three years-an International Live Maintenance Symposium. 13/29 CITTES 2011

  14. The specialists from Romania at the international LW Conferences ESMO, CITTES and ICOLIM(especialy) -theoretical papers and practical demonstrations 14/29 CITTES 2011

  15. The Present Time • 80 Live Maintenance technologies. • Smart crews are able to perform LW maintenance on OHL and in substations, from 20 to 400kV • there are also some erecting, designing and consultance companies which are interested in LW. 15/9 CITTES 2011

  16. LW Persectives in România The CN Transelectrica SA intends to elaborate a lasting program of organization and development of hot-line work. One of the targets: the establishing of a National LW Training Center. S.C. SMART S.A. intends to to extend this activity. Interest for LW implementation especially for Medium Voltage coming from the distribution companies. 16/29 CITTES 2011

  17. Technical and Economical Benefits of LW (case study) • Is really Live Working necessary? • Is really Live Working efficient? • Is really the implementation of Live Working technically and economically justified? CITTES 2011

  18. LOSSES AND CONGESTION IN TRANSMISSION POWER GRID Gaps and voltage-breaks are a source of economic loss (damages) in industry, commerce, agriculture, transport or are creating inconvenience in supplying residential customers. The interruption of power supply is accompanied by damages, lack of production, reduced quality of products, reduced productivity in manufacturing scrap, defects in equipments, technological process disturbances (superior in time to the power interruption), accidents, additional costs for salaries, materials, energy, etc. 18/29 CITTES 2011

  19. For refineries, paper mills or production of electronic components, even a few seconds break can lead to processes stopping and therefore economics losses. For stationary situations in NPG, Transelectrica SA performed all sorts of studies. As a result series of practical measures were taken, one of them and perhaps the most important is the extension of Live Maintenance. 19/29 CITTES 2011

  20. Four types of characteristics: - the A model. The consumers case on which the effects of voltage loss occur after duration of critical outage (tA), which are evidenced by a certain amount of damage (dA), the further losses are negligible; - the B model. The case of companies on which the amount of businesses damage is proportional only with outage time and occur after a certain time (tB) (cement factories, businesses engineering); - the C model. This is a combination of the first two models. The effects of disconecting occurr only after a longer period, but have a important value beyond the critical time (tC). Further damage is proportional to the disconnecting duration (in the aluminum industry, technological processes in steel etc.). - the D model. With different critical period’s t1, t2, t3, for various plants, conected technological processes and which lead then to various damage proportional to time (chemical plants, petrochemicals, some spinners). 20/29 CITTES 2011

  21. LIVE WORKING APPLICATION IN TRANSMISSION POWER GRID Conventionally, in the event of deenergising of an 400 kV OHL, with taking over of the consumers in this area through other OHLs of TPG, results in energy loss, on detour lines, of about 5 MW / h active power. In a specific case of interruption of a OHL 400 kV, for only 10 days, 8 hours/day, may be produced daily active energy loss in the order of 120 MW/h and of 1200 MW/h, for 10 days total. With the 10 days interruption duration for technical revisions for 20 400 kV OHLs, during a calendar year, the energy losses reach 24,000 MW / h and their cost would be around 720,000 Euros. 21/29 CITTES 2011

  22. 22/29 CITTES 2011

  23. A first example: live replacement of bus-bar insulation in 400/110/6kV Braşov substation. 23/29 CITTES 2011

  24. COMPARATIVE ANALYSIS FOR INSULATION REPLACEMENT IN 400 KV BRAŞOV SUBSTATION 24/29 CITTES 2011

  25. Suplimentary considerations on the advantages of Live Working Insulation replacement on a 220 kV tension tower. It is assumed that the 220 kV OHL active power is 150 MW. 25/29 CITTES 2011

  26. COMPARISON BETWEEN LW AND CLASSIC WORK 26/29 CITTES 2011

  27. Conclusions • With a 30 tradition the Live Maintenance in Romania is an ongoing activity. There is an interest fot this kind of work from transmission company. The distribution companies in Romania are still searching for the real benefits of LW. • The presented studies demonstrates, against general current which considers that LIVE WORKING is performed with higher costs than the work on deenergised line that Live Working has an important economic advantage. • Regarding the congestions Live Working is not only a recommendable technology, it is mandatory in congestion management. CITTES 2011

  28. THANK YOU FOR YOUR ATTENTION!!! CITTES 2011