St Paul United Methodist Church. Faith Works! “Building for Christ’s Ministry” Informational Meeting February 27, 2007. Agenda. History of the Faith Works! campaign The Faith Works! video The Building approval process The Building plans The Financial plan Q&A.

Download Presentation

St Paul United Methodist Church

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. St Paul United Methodist Church Faith Works! “Building for Christ’s Ministry” Informational Meeting February 27, 2007 Informational Meeting

  2. Agenda • History of the Faith Works! campaign • The Faith Works! video • The Building approval process • The Building plans • The Financial plan • Q&A Informational Meeting

  3. History of the Faith Works Campaign • Future Search Process • Future Ministry Retreat / Fair • Building and Grounds Study Committee • Ministry team needs survey • Community growth projections • Current facilities nearing capacity • Building Committee Formed • Preliminary building plans Informational Meeting

  4. Demographic and Trend Analysis -Building Study Committee Report 2002 • Population of PWC increased 30.6% from 1990 and 2000 - 280,813 • County projects 328,400 by 2005; 363,300 by 2010 and 384,300 by 2015 • Within 5 miles of St Paul additional 3000 housing units planned over next 5-10 yrs • Conversion of commercial property to high density residential Informational Meeting

  5. The Faith Works! Video Informational Meeting

  6. The Building Approval ProcessUMC Book of Discipline • 2543.6 • Preliminary architectural plan • Preliminary cost estimate • Preliminary financial plan • Building committee recommendation • 2543.7 • Develop detailed plans and specifications • Secure a reliable and detailed cost estimate • Get approval from the Charge Conference and District Committee on Buildings and Location • 2543.8 • With approval, project can begin if 2543.11 has been met (loan is secured so bills can be paid as they come in) Informational Meeting

  7. The Building Approval Process • Admin Board vote on Building Committee recommendation of preliminary building plan and financial plan (5/17/05) approved • District Committee of Buildings and Location (5/25/05) approved • Church Conference to approve financial plan (5/31/05) approved • Development of detailed drawings, permitting and financial arrangements • District Committee of Buildings and Location (6/21/06) approved • Charge Conference to approve drawings, building plans and financial plan (6/27/06) approved Informational Meeting

  8. The Building Plans • 43% increase in space—additional 14,060 sq ft • Fellowship Hall increases by 2000 sq ft • Enlarged Kitchen • Update and expand restrooms including accessibility • Elevator and locations of classrooms greatly enhance building’s accessibility Informational Meeting

  9. The Building Plans (continued) • Nursery close to sanctuary; • Drive-through entrance at chapel door; • Centralized offices for administration/pastors • Enhanced music office, choir room and storage Informational Meeting

  10. The Building Plans (continued) • Preschool/toddler wing with water and toilet between two rooms (code) • Outside exits for selected preschool rooms • 7 New classrooms • Preschool office • Updated parking lot design (lighting and curbing) • Sprinkler system for new construction Informational Meeting

  11. The Building Plans the Sanctuary (continued) • Chancel renovation • Rough-in for future sound and audio visual systems • Extended platform area; for choir, pulpit, lectern, piano • Permanent Bell tables • Removes 3 rows of pews • Removable communion rails Informational Meeting

  12. Current Implementation Plan • Start with; Site work • Parking lots, storm water management, sidewalks and curbing • Transition into Building expansion • Fellowship Hall, kitchen, restrooms, and elevator • Renovations • Classrooms, sanctuary, and offices Informational Meeting

  13. Cost and Accountability • Cost Estimate • Building costs; $2,625K • Site work; $ 690K Total; $3,315K • Financial Planning based on; $3.3M - $550K (Bubb2) = $2.75M Informational Meeting

  14. Cost and Accountability • Building Committee aggressively managing project cost growth • Sources of cost growth include: • Inflation over time • County approvals (ie, firewalls & sprinkler system) • Detailed designs and revised estimates Informational Meeting

  15. Cost and Accountability • Building Committee Trade-offs to control costs • No third floor above Fellowship Hall • Consolidated staff offices built in old Fellowship Hall • Pre-school rooms will share restrooms (one restroom / two classrooms) • Pre-school exits reduced (only for 2 ½ year old classrooms) Informational Meeting

  16. The Financial Plan • Faith Works! Capital Campaign • Planned series of 5 three-year campaigns • First Campaign kicked off Oct 2004 • Pledges totaled $869,265 • Collected to date; $529,517 (thru Jan) • Sale of Bubb 2 Property • Bank Loan (15 year mortgage) Informational Meeting

  17. The Financial Plan Sale of Bubb 2 • Bubb 2 property; • Roughly 2.5 acres • Zoned for single family development • Property includes one house • Current mortgage: $172,000 • Remaining proceeds to reduce bank loan; $550,000 • Current status: Sales offer pending Informational Meeting

  18. The Financial Plan Bank Loan • 15 year Mortgage • Amortized based on 30 year schedule • Interest will be calculated at 7.875% fixed for 10 years, with the rate adjusting to the 5-year US Treasury plus 2.625% in year 11 • Estimated loan amount; $3M • Repayment (estimated) • Monthly payments (30 yr); $21,752 • Monthly payments (15 yr); $28,455 • Monthly payments (30 yr); $19,939 with $2.75M loan • Monthly payments (15 yr); $26,083 with $2.75M loan Informational Meeting

  19. The Financial Plan Current Status - Faith Works! • Bank Loan Closing; Pending Church Conference vote to proceed • Faith Works! Pledges $869,264 (1st campaign) • Faith Works! giving; (through Jan 07) 2004 $ 22,441 2005 $251,330 2006 $247,266 2007 $ 8,480 Total $529,517 Avg mthly $21,181 Informational Meeting

  20. The Financial Plan Current Status - General Fund • General Fund giving year to date; • $54,201 Average monthly giving to date • $55,384 Average monthly giving required to meet 2007 General Fund “Operating” Budget = $1,183 shortfall • $66,677 Average monthly giving required to meet 2007 General Fund Budget (includes all apportionments) = $12,476 shortfall Informational Meeting

  21. Pending Decision • Proceed with program as planned • Do not proceed with building program • Options may include: • Stop entirely • Delay start • Pursue reduced scope program Informational Meeting

  22. Questions & Answers Informational Meeting

  23. Questions • Could the building project be re-structured, re-phased or re-defined? • Yes, options include; • Multi-phased building program • Selected sub-set of current plan • Impacts • Increased total project costs • Potentially voids current approvals (county, local church, district, and bank) • Changing scope of project could impact FW pledges • Additional delay as approval process starts over Informational Meeting

  24. Questions • What are we going to do about the current facility? (cleanliness, paint, repairs) • Trustees issues in constrained “facility unscheduled maintenance” budget • Maintenance items deferred • to conserve budget • Pending direct or indirect impacts from the building program Informational Meeting

  25. Questions • How can we afford this effort and maintain vital ministries? • Attendance is down / giving is down. • Projected shortfall with current (2007) General Fund budget is roughly $150K • However, Faith Works! contributions have remained relatively steady while attendance has declined • Average monthly Faith Works! contributions to date are sufficient to cover the 30 year amortized monthly payments (assuming $2.75M loan) • Generally accepted statistic that building programs draw new members and recover inactive members Informational Meeting

  26. Questions • What if we delay implementation? • The Special Use Permit (SUP) was approved by the county in Feb 2005 • Generally; the SUP remains valid as long as we proceed in time to secure the Occupancy Permit before Feb 2010 • Architectural plans should remain valid • Building costs will increase • Re-apply for bank loan (terms TBD) Informational Meeting

  27. Back up Charts Informational Meeting

  28. Informational Meeting

  29. 2007 Apportionments District Add’l $21.1K Informational Meeting

  30. Conference Apportionment Formula Informational Meeting

  31. Called Charge Conference MinutesJune 27, 2006 (Excerpt) Informational Meeting