CAST Budget Changes BIVV-IBSR. SC meeting – CAST Brussels 27 February 2007. Budget changes. WP0: 7% of grant instead of 7% of total budget Impact only for SC members Reduce WP0 budget with 146.708€ Reduced travel costs Reduction in MM Total grant of project has not changed.
E N D
CASTBudget ChangesBIVV-IBSR SC meeting – CAST Brussels 27 February 2007
Budget changes • WP0: 7% of grant instead of 7% of total budget • Impact only for SC members • Reduce WP0 budget with 146.708€ • Reduced travel costs • Reduction in MM • Total grant of project has not changed Kick-Off meeting CAST
Changes per partner • WP0: all SC partners -60,64% • These amounts were transferred to your own WP (for WP leaders), claim travel costs for SC on WP budget Kick-Off meeting CAST
BIVV • WP0 (100%): -71.546,59€ • WP2 (50%): +45.543,19€ • WP5 (50%): +34.400€ • WP6 (50%): +63.150€ Kick-Off meeting CAST
TOI • WP0 (100%): -11.587,80€ • WP1 (50%): +23.175,59€ Kick-Off meeting CAST
INRETS • WP0 (100%): -8.123,31€ • WP3 (100%): +8.123,31€ Kick-Off meeting CAST
VTI • WP0 (100%): -11.686,85€ • WP4 (50%): +23.373,71€ Kick-Off meeting CAST
PRP • WP0 (100%): -8.713,87€ • WP3 (50%): +5.760€ • WP6 (50%): +11.667,74€ Kick-Off meeting CAST
SWOV • WP0 (100%): -35.050,45€ • WP6: (50%): +70.100,89€ Kick-Off meeting CAST