Sharing the scars of a P3 capital project John Illingworth Deputy CEO ~ Goodwin Development Trust
Our initial considerations Does your project:- • Fit the funders criteria • Match • State Aid • Land • Planning permission • Cashflow • OJEU Good SPD fit Sure Start Cap and Rev N/A ! You need to own some New build/refurb It goes out first £3.8 M
What do you know about building? • Who has delivered a £1M capital project before ? • Ask someone who has
How do I appoint ... • Valuer • Contractor • Architect • Mechanical & Electrical engineers • Structural engineers • Quantity Surveyors • Clerk of Works • Lawyer
What we did wrong • Assumed • Trusted • Believed honourable men • .......in hindsight
What did that assumption cost? • £145,000 • And a threat of a Judicial Review It isn’t just cash that costs
But can you do it yes you can !