1 / 12

University of Calgary Continuing Education

University of Calgary Continuing Education. Construction Contract Law and Documents Week 13 Contract Types Forms of Contract. Types of Contractual Relations. Design-Bid-Build Stipulated Price Cost Plus Construction Management (CCDC5A) Construction Management at Risk (5B) Design-Build

hartt
Download Presentation

University of Calgary Continuing Education

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. University of Calgary Continuing Education Construction Contract Law and Documents Week 13 Contract Types Forms of Contract

  2. Types of Contractual Relations • Design-Bid-Build • Stipulated Price • Cost Plus • Construction Management (CCDC5A) • Construction Management at Risk (5B) • Design-Build • EPC/EPCM • Integrated Project Development

  3. Standard CCDC/CCA Contracts • CCDC 2 Stipulated Price Contract • CCDC 3 Cost Plus Contract • CCDC 4 Unit Price Contract • CCDC 5A – Construction Management – for services • CCDC 5B – Construction Management – for services and construction

  4. Standard CCDC/CCA Contracts • CCDC 14 Design-Build Stipulated Price Contract • CCDC 15 Design Services Contract between Design-Builder and Consultant • CCDC 17 Stipulated Price Contract for Trade Contractors on Construction Management Project • Civil Works Project

  5. Standard CCA Contract • CCA-1 Stipulated Price Subcontract • CCA-19 Stipulated Price Sub-Subcontract

  6. Project Documentation • Project budget • Your cost – not revenue • Enumerate all resource profiles • Show all anticipated cost changes (ie: prices)

  7. Project Documentation • Project schedule • Detailed so that changes in order of work can be identified • Show resources on critical activities • Show owner supplied deliveries or work • Allowance for approvals shown explicitely

  8. Project Documentation • Updating Project Plan • Critical to ensure credibility (we do this normally – not just to show the error of the other party) • Must reflect true activity – don’t try to hide your own dirty laundry • Should be accurate record of the plan revisions necessitated by changing conditions

  9. Project Documentation • Correspondence • Must be formal and organized • All formal documentation, initially, should be to the notice address • Subsequent, project kickoff meetings would define operational changes to flow of documents – must be confirmed in writing to notice address • Separate files for each claim – suggested

  10. Project Documentation • Review Contract • Note all notice requirements • Note notice address • No matter what, unless you have a formal instruction, always send Notices to Notice Address • Pay particular attention to notices regarding delays, unexpected work, changes to the work – these are the prime source of claims for extras.

  11. Project Documentation • Routine • Each level of management should review reports from level below • Each level of management should prepare material for level above • Concept of overlapping and complementary information

  12. Project Documentation • Examples • Superintendent daily diary (independent corroboration of all site activity – personnel changes, tardiness, everything) • Weekly site report by superintendent • Perhaps prepared by site engineer by endorsed by site supervisor • Reviewed by Project Manager • Monthly report by project manager • Reviewed by company management.

More Related