MICE MICO September ‘07. Chris Nelson. Beamline and Hall. Shielded area virtually complete SW corner Replacement West wall concrete ordered, corner pieces about to be ordered Delivery both ~6 weeks, installation next opportunity Extra wall near Door and roof subject to survey
E N D
MICE MICO September ‘07 Chris Nelson
Beamline and Hall • Shielded area virtually complete • SW corner • Replacement West wall concrete ordered, corner pieces about to be ordered • Delivery both ~6 weeks, installation next opportunity • Extra wall near Door and roof subject to survey • Extra shielding in plinth doorway • Plan using high density blocks, availability ~1 week • Agreement with Paul Wright RPA • Check numbers needed and Order today • Plinth rails installed & surveyed • Double check needed on alignment measurements • CKOV stand • Materials and parts ordered by Oxford • Discussion, & Extra small detail drgs lifting, dowel pins etc (being finished?) • CJN will organise PRR (Peter back next week)
Triplet baseplates at RAL • Installation details being finalised, hope to install 1-2 weeks time • But Need blockhouse access • Rolling platform • Review end September • Ordered air skates • First platform required March 08 • Future plans • False floor • Concrete plinth
MICE – platforms and baseplates CONCEPT – PLATFORM WITH AIR SKATES CLAMPED TO BASEPLATE IN INSTALLED LOCATION. WHEN ACCESS IS REQ’D THE CLAMPS ARE RELEASED AND THE TRACKER IS FLOATED TO A PARKED POSITION.
Mechanical Services • Water- order being written out • Other services/gases • Need for detector groups to request any required services • Compressed air line for when Linde equipment in use • Nitrogen for CKOV (bottle/gas line)?