Lakeside Project

Lakeside Project. Utah Abandoned Mine Reclamation Program. Division of Oil, Gas & Mining Department of Natural Resources. Purpose : To seal hazardous abandoned mines. Abandoned Mine Hazards. Roof collapse Unstable side walls Total darkness – you can easily get lost

hazina
Download Presentation

Lakeside Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lakeside Project Utah Abandoned Mine Reclamation Program Division of Oil, Gas & Mining Department of Natural Resources

  2. Purpose : To seal hazardous abandoned mines

  3. Abandoned Mine Hazards • Roof collapse • Unstable side walls • Total darkness – you can easily get lost • Hidden vertical shafts inside • Toxic gases • Lack of oxygen

  4. Project would close: • 14 portals • 19 shafts • Affect <5 acres

  5. Right of Entry (ROE) • Permission is obtained from all land owners prior to any construction work • Private land • Public (Bureau of Land Management) • State Trust Lands (minerals) • Private (Surface)

  6. Legal Authority • Utah has primacy under the Surface Mining Control and Reclamation Act of 1977, SMCRA

  7. Project Costs • Funded by a tax on current coal production

  8. Project Selection • Ranking priority system considers: • Population: Resident and Transient • Mining Districts: historic mining areas • Mine density • Roads and accessibility

  9. Project Schedule • Work would occur in late summer/fall of 2008 • Work would require 4 weeks

  10. Some of the laws we comply with: • National Environmental Policy Act NEPA • National Historic Preservation Act • Antiquities Act • Endangered Species Act

  11. Environmental Assessment • Analyzes potential impacts on the environment • Includes clearances from: • State Historic Preservation Officer • US Fish and Wildlife Service • Sign-offs from: • Office of Surface Mining • Bureau of Land Management

  12. Surveys & Data Collection • Abandoned Mine Inventory • Cultural & Historical Surveys • Bat Surveys • Paleontological Surveys (not applicable for Lakeside Project)

  13. Abandoned Mine Inventory

  14. Historical and Cultural Inventory House Foundation

  15. Bat Surveys

  16. Paleontological Survey

  17. AMRP’s Intent • Cause the least amount of disturbance possible • Design mine closures so that historical features are preserved • Revegetate all areas disturbed

  18. Mine Closure Designs

  19. Hand Backfill

  20. Equipment Backfill -before & after

  21. Equipment Backfill – before & after

  22. Equipment tracks raked & seeded

  23. Bat Gates Locked steel gates allow for access and bat usage

  24. Pinned Grate – before & after

  25. Pinned Grate – before & after

  26. Shaft Grate - Concrete Grade Beam

  27. Block Wall – before & after

  28. Block Wall – before & after

  29. Stone Wall – before & after

  30. Stone Wall – before & after

  31. Closure # Avg. Costs • Machine Backfill 21 <$10/CY • Hand Backfill 5 ~$100/CY • Block Wall 1 ~$40/SF • Stone Wall 0 ~$40/SF • Bat Gate 1 ~$75/SF • Grade Beam Grate 1 ~$50/SF • Pinned Grate 4 ~$45/SF • PUF 0 ~$450/CY • Compound Custom 0 varies