200 likes | 314 Views
Dzhelepov Laboratory of Nuclear Problems. Status Report for E391a (Continuation of the previous PAC on April). G.Y.Lim IPNS, KEK. Group Meeting at the JINR 26 th – 29 th July 2003. After the previous PAC. Start assembling the front barrel
E N D
Dzhelepov Laboratory of Nuclear Problems Status Report for E391a(Continuation of the previous PAC on April) G.Y.Lim IPNS, KEK Group Meeting at the JINR 26th – 29th July 2003
After the previous PAC • Start assembling the front barrel • Continuous fabrication of the central barrel • Evacuation test of the downstream section
Middle Section Downstream section Upstream section E391a Detector
Upstream Section • Module fabrication was done – Dec. 2002 • Instrument for assembling was fabricated • Collaboration work with KEK machine shop • Start assembling - August 2003 • Will take one month • Evacuation/cosmic test will be done Sep. 2003
5th August 2003 Slide show for FB assembling
22nd August (Expected) Continuously
CC02 Shashlik type of beam counter Arrived at KEK on 4th July from U. of Chicago Beam test at pi2 July 2nd ~8th, 2003 8 % resolution @ 1GeV, 10 p.e./MeV deposit (Very preliminary !!!)
After CC02 installation ・・・ Aiming to finish by the end of August
Middle section • Module fabrication – Final stage
50 plates/week Finish at the middle of Sep.
Stacking on every Wed. Working more than 8 person End of September
Middle section • Module fabrication – Final stage • Vacuum vessel is being constructed • Competition bid – Hitachi Zosen Ltd. • Will arrive at KEK at the end of Oct. 2003 • Assembling scenario was fixed • Collaboration work with Entek • Assembling will be done by the middle of Dec. 2003
Downstream section • Assembling was finished – Sep. 2002 • Beam test (Engineering run) – Oct. – Dec. 2002 • Evacuation test – June 2003 • First time of operation for calorimeter in vacuum • Test for the water cooling mechanism
Cooling System • Control PMT temperature within 1 0C with circulating water
Divider CsI Temperature Measurement
50C Cooling water 100C Cooling water 150C Cooling water 200C Cooling water We got clear Cosmic response pQ/cm
Temp. dependency Normalized by the engineering data MeV/pC Cosmic Peak position Light Yield : -1.3% / 0C Cosmic Peak width(sigma) CsI temp. (0C)
Schedule Cosmic and evacuate test for the upstream Beam FB assembling CB fabrication BCV CB assembling Middle section fabrication Membrane Start data taking Check Membrane Unite three sections Downstream vacuum test Moving downstream BA and CC05 installation CV PMT install A/D Card upgrade ADC Replacement Additional Cabling Evacuate system Cosmic test/counter tuning CC04/CC05 Fabrication CC04 Installation Cooling system for Barrel Aug. Sep. Oct. Nov. Dec. Jan. Feb.
Summary • E391a is aiming at measuring the BR( KLp0nn ) • Realizing Step-by-step • Preparation of E391a • Three parts are being prepared in parallel • Manage to catch up the schedule • Prompt start • Well tuned electronics and DAQ at the engineering run • Cosmic test for each detector components • Minimum beam time for tuning