An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Robust Adaptive Topology Configuration Project • Funded by: ARPA-E • Presented by: • John W. Stewart

  2. F2F meeting held on 15 March 2013 at TVA Power HQ in Chattanooga, TN. Participants from TVA included: John Stewart (RATC Project Manager) DeJim Lowe (R&D Manager) Tiffany Gibby (Telecom Manager) Theo Laughner (PQ Manager) Bill Hawkins (Protection) Josh Shultz (Transmission Operations) Industry/Researcher Technical Collaboration

  3. 15 March F2F meeting (cont) Participants from RATC team included: Mladen Kezunovic (PI; TAMU) Schmuel Oren (UCB) Kory Hedman (ASU) Tomo Popovic (TEES) Sami Ayyorgin (ACS) Gurunath Gurrala (ASU) Alex Sprintson Joe Gracia (ORNL) Industry/Researcher Technical Collaboration (cont)

  4. Overall RATC Project Objectives and Value Proposition Scenarios, Test Plans, Test Cases, Use Cases Specific Requirements for TVA Data Mode of interaction between RATC researchers and TVA Discussion Topics

  5. RATC team researchers will draft specific but concise test plans and test cases Context Specific data requirements Test cases will identify pertinent Milestones & Deliverables ORNL will facilitate the data requests TVA will track the status of the data transfers Next Steps