Beam Operation Experience at Quantum Beam Project in STF

Beam Operation Experience at Quantum Beam Project in STF. Kirk. The answer is…. No change during “beam” operation in KEK-STF even after many earthquakes !!. MHI-12 and -13 were very stable in Quantum beam experiment. But…. We have a few examples for change in Cryomodule test.

hiero
Download Presentation

Beam Operation Experience at Quantum Beam Project in STF

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Beam Operation Experience at Quantum Beam Project in STF Kirk TTC Meeting 2014@DESY

  2. The answer is… No change during “beam” operation in KEK-STFeven after many earthquakes!! MHI-12 and -13 were very stable in Quantum beam experiment TTC Meeting 2014@DESY

  3. But…. We have a few examples for change in Cryomodule test TTC Meeting 2014@DESY

  4. History of Cavity Performance in KEK-STF • Vertical Test in CW mode • Cryomodule Test in Pulsed mode

  5. Status of RF Conditioning for MHI-12 1500μsec 600μsec STF Cavity Group Meeting (2013/5/13)

  6. Status of RF Conditioning for MHI-12 1500μsec STF Cavity Group Meeting (2013/5/13)

  7. Status of RF Conditioning for MHI-12 1500μsec 600μsec STF Cavity Group Meeting (2013/5/13)

  8. Status of RF Conditioning for MHI-12 1500μsec STF Cavity Group Meeting (2013/5/13)

  9. Comparison of Radiation Level History MHI-12 MHI-13 The radiation level was never changed during the CM test.

  10. Cavity performance degraded by “Earthquake” during beam operation? TTC Meeting 2014@DESY

  11. Earthquake events at KEK-STF TTC Meeting 2014@DESY

  12. Log Trend in 12/Oct/2012 MHI-12 MHI-13 TTC Meeting 2014@DESY

  13. Log Trend in 24/Oct/2012 MHI-12 MHI-13 TTC Meeting 2014@DESY

  14. Log Trend in 31/Oct/2012 MHI-12 MHI-13 TTC Meeting 2014@DESY

  15. Log Trend in 7/Dec/2012 MHI-12 MHI-13 TTC Meeting 2014@DESY

  16. After these earthquakes, the cavity performance was never changed!! TTC Meeting 2014@DESY

  17. Cavity Performance for STF-2 TTC Meeting 2014@DESY

  18. In future… The high power test in STF-2 will start from 2015. TTC Meeting 2014@DESY