1 / 13

A N DY Status Commissioning with colliding beams (p  +p  at s=500 GeV)

A N DY Status Commissioning with colliding beams (p  +p  at s=500 GeV). L.C.Bland, for AnDY 19 April 2011 Time Meeting, BNL. Local Polarimetry Tuned parameters for scaler board.

Download Presentation

A N DY Status Commissioning with colliding beams (p  +p  at s=500 GeV)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ANDY StatusCommissioning with colliding beams (p+p at s=500 GeV) L.C.Bland, for AnDY 19 April 2011 Time Meeting, BNL

  2. Local PolarimetryTuned parameters for scaler board • Gain-matching of ZDC shower maximum detector (SMD) derived from event analysis has been implemented for the scaler board measurements • An effective threshold on ZDC SMD energy deposition is applied to the scaler board data • Scaler board data for local polarimetry was acquired with final parameters for fill>15465 • Analysis of scaler board data is underway

  3. SHCR>4000 (jet trigger) SHCR>4000 (jet trigger) SHCL>4000 (jet trigger) SHCL>4000 (jet trigger) Pair trigger (SHCL>1400).(SHCR>1400) Pair trigger (SHCR>1400).(SECL>thrE) Pair trigger (SHCL>1400).(SECR>thrE) Pair Trigger • Drell-Yan will result in correlated response of left and right detector arms • Jet trigger does not span full space of pair correlations • A pair trigger was implemented and used for data recorded for fill>15465 • Converter plates were installed on 15 April, as needed for e/h discrimination As expected from simulations, pair trigger enables substantially lower threshold than jet trigger

  4. Integrated Luminosity Estimate to Date ~1.6mr crossing angle ~0mr crossing angle systematically increased thresholds for IP2 collisions ~2mr crossing angle • Presently, no accidentals correction (found to be large for ZDC). All rates are now scaled on bunch-crossing scalers, following 20110330 access and subsequent timing adjustments. • Requires calibration of effective cross section for BBC via vernier scan. • Need to reconcile assumptions about cross sections against vernier scan measurements in fill=15457 • Jet analyzing power measurement sets goal of 10 / pb for run 11. Many thanks to C-A for increasing the threshold for IP2 collisions 12/1/2014 4

  5. Conclusions and Plans • Repeated fills have demonstrated that IP2 collisions can have minimal impact on IP6,IP8 luminosity • With decreased b* and ~10 hour stores, run-11 has demonstrated that 15 / pb / week can be delivered to IP2 in runs 12,13 • Comparison of run-11 data to simulation is underway • We will proceed with a proposal to the 2011 PAC • >750M jet trigger events recorded in run 11 12/1/2014 5

  6. Backup 12/1/2014 6

  7. Reminder of GoalsLong-term and run-11 • Goals of ANDY project: • Establish that large-xF low-mass dileptons from the Drell-Yan process can be discriminated from background in s=500 GeV p+p collisions • Measure the analyzing power for Drell-Yan production with sufficient statistical precision to test the theoretical prediction of a sign change for DY in relation to semi-inclusive deep inelastic scattering • Establish if robust detection of Drell-Yan dileptons at large xF and low mass requires magnetic analysis  critical for future facilities at RHIC 12/1/2014 7

  8. ANDY Prioritiesfor remainder of RHIC run-11 • Run-11 goals: • Establish the impact of a third IR on RHIC performance for p+p collisions at s=500 GeV - Demonstrate luminosity at IP2, as required for Drell-Yan sample in runs 12 (without magnet),13 (with magnet). Estimate that 150 / pb gives 104 large-rapidity di-electrons with M>4 GeV/c2 for p+p at s=500 GeV. Is this possible in a 10-week run? • Demonstrate calibration of HCal • Measure analyzing power for large xF jet production. Non-zero AN required for jets if Drell-Yan production has an analyzing power. Complete the measurement of the analyzing power for jet production. A non-zero AN for jets is a requirement for Drell-Yan to have non-zero analyzing power. Recent theoretical work establishes intrinsic interest in the jet analyzing power measurement. 12/1/2014 8

  9. Run11 AN(Jet) arXiv:1103.1591 jet AN measurements are required to clarify signs of quark/gluon correlators related to Sivers functions. arXiv:1011.2692v1 s=200 GeV from p+pp “new” Sivers function “old” Sivers function 200GeV Non-zero jet analyzing power essentially a prerequisite before proceeding to Drell Yan 12/1/2014 • Siver’s effect only (no collin’s effect contribution) • Need AN(Jet) measurements before DY • With ~10/pb & P=50%, AnDY run11 can measure AN(Jet) 9

  10. Estimates • At present threshold for IP2 collisions (average intensity < 0.901011/bunch), integrate ~200 / nb / fill • 2 fills/day has been achieved • Consequently, 12.5 days are required to get 5 / pb • Maximum possible integrated luminosity (IP2 collisions for entire fill) would yield ~700 nb/fill • One week at 2 fills/day would provide 5 / pb • Two weeks at 2 fills/day would provide 10 / pb

  11. Minimal impact on STAR,PHENIX Higher Intensity for IP2 Collisions Fri. 8 April 1.501011/bunch IP2 collisions have begun <3 hours after physics ON

  12. Schematic of detector for Run-11 • Equipment in place: • HCal is two existing 9x12 modules from E864 (NIM406,227) • ECal are two small lead-glass modules from BigCal at JLab • BBC (from PHOBOS) and ZDC • Preshower is newly constructed scintillator arrays • Goals: • Establish impact of 3IR operation on PHENIX/STAR luminosity • Calibrate HCal • relative gain via cosmic-ray m • absolute energy scale via r,L,KS… • Measure hadronic backgrounds to benchmark simulations • Measure jet analyzing power (Lint~10 / pb, P=50%) 12/1/2014 12

  13. Trigger/DAQ electronics Left/right symmetric HCal Left/right symmetric ECal Blue-facing BBC Left/right symmetric preshower Beryllium vacuum pipe IP2 in January, 2011Run-11 Staging of ANDY 12/1/2014 13 See http://hena.lbl.gov/IP2/Business/status/<date> for pictures of progress

More Related