1 / 9

M.A.P

M.A.P. Case Study – Scott Howell. In Partnership with. Case Study.

hiroko
Download Presentation

M.A.P

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. M.A.P Case Study – Scott Howell In Partnership with

  2. Case Study • Scott suffers from Myotubular Myopathy, a rare condition that causes weakness and wasting of muscles, confining him to a wheelchair and leaving him unable to breathe unaided. Scott requires a ventilator and the assistance of a carer 24 hours a day. • Building Components was commissioned jointly by Steve Johnston of Wirral Partnership Homes and Paul Rolfe of Wirral Council to supply suitable accommodation for four year old Scott Howell. • Scott’s existing home was not suitable for conversion so an extension was proposed. Building Component’s proposal was a MAP (Modular Adaptation Pod) consisting of a bedroom and wet room. The bedroom design needed to accommodate all medical equipment Scott required, this included 30 electrical items all requiring designated power outlets.

  3. Wet Room • The wet room was designed with a level access shower which was capable of accommodating a 2.0m x 900mm shower trolley.

  4. Manufacture • The M.A.P is constructed from light weight steel to meet all current building regulations and is a structural entity, however in this instance the roof strength was increased to accommodate an electrical hoist. The hoist has a capacity of 300kg.

  5. Manufacture • The project under Building Components control split into three elements. Firstly, the internal modification to the property was undertaken by WPH due to their knowledge of the housing system. Secondly, the external groundwork and installation was carried out by BC. Thirdly, the manufacture of the M.A.P was carried out by the pod manufacturer. • Work started on all three elements simultaneously, TWO weeks after planning approval was given. • All three elements were completed TWO weeks later. The installation then took place on the Monday of the third week.

  6. Installation • Scott was on site to see his present arrive on the back of an articulated lorry, wrapped in a big blue plastic bag. This was accompanied by an 80 tonne crane. • The lift started at 10:45am and by 12:15pm the lights were on and hot water was flowing from the sink tap.

  7. Completion • Scott moved in two days later after all of his medical equipment was installed and tested.

  8. The Client

  9. Contact Ray Philpin 37 Simpsons Walk Horsehay Telford Shropshire TF4 2PA 07850 593825 01952 504082 ray@buildingcomponents.co.uk

More Related