1 / 9

INVESTMENT PROMOTION AND FINANCING FACILITY

INVESTMENT PROMOTION AND FINANCING FACILITY. Marghoob Bin Hussein Proc Specialist, The World Bank Dhaka. March 26 and 28, 2008. Key Topics. Types of Selection of Entrepreneurs (Options 1 and 2) Option 1 – Process Option 2 – Process

huy
Download Presentation

INVESTMENT PROMOTION AND FINANCING FACILITY

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INVESTMENT PROMOTION AND FINANCING FACILITY Marghoob Bin Hussein Proc Specialist, The World Bank Dhaka March 26 and 28, 2008

  2. Key Topics • Types of Selection of Entrepreneurs (Options 1 and 2) • Option 1 – Process • Option 2 – Process • Documents requiring World Bank review and Entrepreneur’s basic responsibilities • Timeline for Procurement • Note: • Entrepreneurs also mean project promoters / investors / concessionaire

  3. Selection of Entrepreneurs – Provisions under the Financing Agreement Principle: Economy, Efficiency & Transparency of the system Selection of the entrepreneur: Option 1: The entrepreneur is selected by a GoB authority (i.e. a Line Ministry) through international competitive bidding (ICB) procedures of The World Bank (WB). All subsequent procurement will follow applicable rules of said entrepreneur. Para 3.13.a of WB’s Procurement Guidelines (PG) Option 2: If the entrepreneur is not selected through a competitive process, but the project is of importance in meeting GoB’s utility (i.e. power, water etc.) obligation to the public. All downstream procurement by that entrepreneur will follow WB-PG. Para 3.13.b of WB’s PG

  4. Cash Flow Example10 years, 100 Million, market Interest rate, Government bond 10% Key Issues: 1. PFI is bearing 100% risk of debt financing. 2. 56% of investment cost is the maximum IPFF (BB) can finance. This may reduce subject to financial viability on a project-by-project basis. Bangladesh Bank (BB) 56 Million 10.25% Private Financial Institution (PFI) Other Financial Institutions or Private Investors 14 Million Debt or other funding 56 Million Debt Market % Private Infrastructure Project 30 Million Equity Project Promoter / Entrepreneur

  5. World Bank Review • Procurement Plan • Bidding Documents • Bid Evaluation Reports Entrepreneur’s responsibilities • Preparation of the above three documents and timely submission to PFI for further forwarding to WB for clearance, with a copy sent to BB in each case. • Adhering to approved procurement plan. • Timely submission of copy of conformed signed contract documents to WB. • Close interaction with WB for clarification and consultation (except at evaluation stage)

  6. Notification of Award Contract signing Bid Submission IFB Advertised Bid Evaluation Bidding 4 - 8 weeks < 4 weeks > 6 weeks Bidding Timeline from Advertisement to Award of Contract

  7. Project Rationale • Why IPFF? • Local investors do not have access to long-term taka loan, typical infrastructure loan tenure is 5-7 years, whereas IPFF provides for 12-15 years. Projects with belated return benefits from long tenure. • The risk is borne totally by PFI, but PFI hedges this risk by obtaining 80% of debt financing through low-interest government rates.

  8. Project Pipeline • During the last nine months, the following type of projects have approached IPFF: • Small Power Plants (11-22-33 and 66 MW) • Captive Power Plants (4-8 MW) • Inland Container Terminal • Currently the bag has only US$ 50 million, with a possible additional financing of US$ 75 million, if the current amount finishes by August 2009.

  9. Thank You Q & A

More Related